52.236-8 Other Contracts.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 2000 1citing case
At a glance

Courts have cited this section in 1 opinion since 2000.

As prescribed in 36.508, insert the following clause:

Other Contracts (APR 1984)

The Government may undertake or award other contracts for additional work at or near the site of the work under this contract. The Contractor shall fully cooperate with the other contractors and with Government employees and shall carefully adapt scheduling and performing the work under this contract to accommodate the additional work, heeding any direction that may be provided by the Contracting Officer. The Contractor shall not commit or permit any act that will interfere with the performance of work by any other contractor or by Government employees.

(End of clause) [48 FR 42478, Sept. 19, 1983, as amended at 60 FR 34761, July 3, 1995]
The 1 case that cites 48 C.F.R. § 52.236-8 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENSauer Inc. v. Richard J. Danzig, 224 F.3d 1340 (Fed. Cir. 2000).
cites § 52.236-8 1×cited by 75 cases
Where it cites § 52.236-8
“The contract contained the standard Federal Acquisition Regulation provision regarding other contracts being performed at or near the worksite, see 48 C.F.R. § 52.236-8 , as well as other provisions relating to concurrent contractor activity at the work site.”
The case’s holding
A party asserting that liquidated damages were improperly assessed bears the burden of proving the extent of the excusable delay caused by unforeseeable factors beyond its control.
Later courts cite it for
“as a general rule, a party asserting that liquidated damages were improperly assessed bears the burden of showing the extent of the excusable delay to which it is entitled.” · 10 citing courts

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.