C.F.R. homeSearch C.F.R.
C.F.R.Title 48Chapter 1—Federal Acquisition RegulationSubchapter H—Clauses and FormsPart 52—Solicitation Provisions and Contract ClausesSubpart 52.2—Text of Provisions and Clauses

48 C.F.R. § 52.249-9 (2026)

52.249-9 Default (Fixed-Price Research and Development).

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 2003–2011 5citing cases
At a glance

Courts have cited this section in 5 opinions since 2003.

As prescribed in 49.504(b), insert the following clause:

Default (Fixed-Price Research and Development) (APR 1984)

(a)(1) The Government may, subject to paragraphs (c) and (d) below, by written Notice of Default to the Contractor, terminate this contract in whole or in part if the Contractor fails to—

(i) Perform the work under the contract within the time specified in this contract or any extension;

(ii) Prosecute the work so as to endanger performance of this contract (but see subparagraph (a)(2) below); or

(iii) Perform any of the other provisions of this contract (but see subparagraph (a)(2) below).

(2) The Government's right to terminate this contract under subdivisions (1)(ii) and (1)(iii) of this paragraph may be exercised if the Contractor does not cure such failure within 10 days (or more, if authorized in writing by the Contracting Officer) after receipt of the notice from the Contracting Officer specifying the failure.

(b) If the Government terminates this contract in whole or in part, it may acquire, under the terms and in the manner the Contracting Officer considers appropriate, work similar to the work terminated, and the Contractor will be liable to the Government for any excess costs for the similar work. However, the Contractor shall continue the work not terminated.

(c) Except for defaults of subcontractors at any tier, the Contractor shall not be liable for any excess costs if the failure to perform the contract arises from causes beyond the control and without the fault or negligence of the Contractor. Examples of such causes include (1) acts of God or of the public enemy, (2) acts of the Government in either its sovereign or contractual capacity, (3) fires, (4) floods, (5) epidemics, (6) quarantine restrictions, (7) strikes, (8) freight embargoes, and (9) unusually severe weather. In each instance the failure to perform must be beyond the control and without the fault or negligence of the Contractor.

(d) If the failure to perform is caused by the default of a subcontractor at any tier, and if the cause of the default is beyond the control of both the Contractor and subcontractor, and without the fault or negligence of either, the Contractor shall not be liable for any excess costs for failure to perform, unless the subcontracted supplies or services were obtainable from other sources in sufficient time for the Contractor to meet the required delivery schedule or other performance requirements.

(e) If this contract is terminated for default, the Government may require the Contractor to transfer title and deliver to the Government, as directed by the Contracting Officer, any (1) completed or partially completed work not previously delivered to, and accepted by, the Government and (2) other property, including contract rights, specifically produced or acquired for the terminated portion of this contract. Upon direction of the Contracting Officer, the Contractor shall also protect and preserve property in its possession in which the Government has an interest.

(f) The Government shall pay the contract price, if separately stated, for completed work it has accepted and the amount agreed upon by the Contractor and the Contracting Officer for (1) completed work for which no separate price is stated, (2) partially completed work, (3) other property described above that it accepts, and (4) the protection and preservation of the property. Failure to agree will be a dispute under the Disputes clause. The Government may withhold from these amounts any sum the Contracting Officer determines to be necessary to protect the Government against loss from outstanding liens or claims of former lien holders.

(g) If, after termination, it is determined that the Contractor was not in default, or that the default was excusable, the rights and obligations of the parties shall be the same as if the termination had been issued for the convenience of the Government.

(h) The rights and remedies of the Government in this clause are in addition to any other rights and remedies provided by law or under this contract.

(End of clause) [48 FR 42478, Sept. 19, 1983, as amended at 60 FR 34762, July 3, 1995]
The 5 cases that cite 48 C.F.R. § 52.249-9 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENMcDonnell Douglas Corp. v. United States, 567 F.3d 1340 (Fed. Cir. 2009).
cites § 52.249-9 2×cited by 22 cases
Where it cites § 52.249-9
“48 C.F.R. § 52.249-9 (1984). Under the contract, the contractors were to design, manufacture, and test eight A-12 prototypes according to a specified schedule, with the first aircraft to be delivered in June 1990 (the “first flight” date) and the remaining seven to be delivered…”
Later courts cite it for
“tjhe government was justifiably insecure about the contract's timely completion," and "we are less concerned about the label of the contracting officer's action so long as, in fulfilling his duty, the contracting officer exercised reasoned judgment and did not act arbitrarily.” · 1 citing court
2
GREENMcDonnell Douglas Corp. v. United States, 323 F.3d 1006 (Fed. Cir. 2003).
cites § 52.249-9 1×cited by 56 cases
Where it cites § 52.249-9
“That FAR clause provides: (a) (1) The Government may, subject to paragraphs (c) and (d) below, by written Notice of Default to the Contractor, terminate this contract in whole or in part if the Contractor fails to— (ii) Prosecute the work so as to endanger performance of this…”
The case’s holding
A default termination for failure to make progress requires an objective inquiry into whether the contracting officer had a reasonable belief based on tangible, direct evidence of unlikely completion.
Later courts cite it for
“in determining whether a default termination was justified, a court must review the evidence and circumstances surrounding the termination, and that assessment involves a consideration of factual and evidentiary issues.” · 7 citing courts
3
GREENGen. Dynamics Corp. v. United States, 563 U.S. 478 (2011).
cites § 52.249-9 1×cited by 40 cases
Where it cites § 52.249-9
“” 48 CFR §52.249-9 (g) (2010). Our opinion does not express a view on those issues.”
The case’s holding
A court must leave the parties where they stand when the state secrets privilege prevents the adjudication of a prima facie valid defense in a government contract dispute.
Later courts cite it for
“protecting our national security sometimes requires keeping information about our military, intelligence, and diplomatic efforts secret.” · 4 citing courts
4
GREENArmour of Am. v. United States, 96 Fed. Cl. 726 (Fed. Cl. 2011).
cites § 52.249-9 2×cited by 10 cases
Where it cites § 52.249-9
“See 48 C.F.R. § 52.249-9 . McDonnell Douglas XIV, 567 F.”
5
GREENMcDonnell Douglas Corp. v. United States, 76 Fed. Cl. 385 (Fed. Cl. 2007).
cites § 52.249-9 1×cited by 4 cases
Where it cites § 52.249-9
“” 48 C.F.R. § 52.249-9 . Early cases ruled that timely completion must be impossible before the agency may terminate a contract for failure to make progress.”
Later courts cite it for
“enabled the court to consider the contractors' progress in light of factors that are probative of their ability and willingness to perform,” · 1 citing court

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
200320072011

One bar per year. Tallest: 2 cases in 2011. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Fed. Cir.2Fed. Cl.2SCOTUS1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com