8.405-2 Ordering procedures for services requiring a statement of work.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 2009–2021 10citing cases
At a glance

Courts have cited this section in 10 opinions since 2009, 1 of them in the last five years.

(a) General. Ordering activities shall use the procedures in this subsection when ordering services priced at hourly rates as established by the schedule contracts. The applicable services will be identified in the Federal Supply Schedule publications and the contractor's pricelists. For establishing BPAs and for orders under BPAs see 8.405-3.

(b) Statements of Work (SOWs). All Statements of Work shall include a description of work to be performed; location of work; period of performance; deliverable schedule; applicable performance standards; and any special requirements (e.g., security clearances, travel, special knowledge). To the maximum extent practicable, agency requirements shall be performance-based statements (see subpart 37.6).

(c) Request for Quotation procedures. The ordering activity must provide the request for quotation (RFQ), which includes the statement of work and evaluation criteria (e.g., experience and past performance), to schedule contractors that offer services that will meet the agency's needs. The RFQ may be posted to GSA's electronic RFQ system, eBuy (see 8.402(d)).

(1) Orders at, or below, the micro-purchase threshold. Ordering activities may place orders at, or below, the micro-purchase threshold with any Federal Supply Schedule contractor that can meet the agency's needs. The ordering activity should attempt to distribute orders among contractors.

(2) For orders exceeding the micro-purchase threshold, but not exceeding the simplified acquisition threshold. (i) The ordering activity shall develop a statement of work, in accordance with 8.405-2(b).

(ii) The ordering activity shall provide the RFQ (including the statement of work and evaluation criteria) to at least three schedule contractors that offer services that will meet the agency's needs or document the circumstances for restricting consideration to fewer than three schedule contractors based on one of the reasons at 8.405-6(a).

(iii) The ordering activity shall specify the type of order (i.e., firm-fixed-price, labor-hour) for the services identified in the statement of work. The contracting officer should establish firm-fixed-prices, as appropriate.

(3) For proposed orders exceeding the simplified acquisition threshold. In addition to meeting the requirements of 8.405-2(c)(2)(i) and (iii), the following procedures apply:

(i) Each order shall be placed on a competitive basis in accordance with (c)(3)(ii) and (iii) of this section, unless this requirement is waived on the basis of a justification that is prepared and approved in accordance with 8.405-6.

(ii) The ordering activity contracting officer shall provide an RFQ that includes a statement of work and the evaluation criteria.

(iii) The ordering activity contracting officer shall—

(A) Post the RFQ on eBuy to afford all schedule contractors offering the required services under the appropriate multiple-award schedule(s) an opportunity to submit a quote; or

(B) Provide the RFQ to as many schedule contractors as practicable, consistent with market research appropriate to the circumstances, to reasonably ensure that quotes will be received from at least three contractors that can fulfill the requirements. When fewer than three quotes are received from schedule contractors that can fulfill the requirements, the contracting officer shall prepare a written determination to explain that no additional contractors capable of fulfilling the requirements could be identified despite reasonable efforts to do so. The determination must clearly explain efforts made to obtain quotes from at least three schedule contractors.

(C) Ensure all quotes received are fairly considered and award is made in accordance with the evaluation criteria in the RFQ.

(4) The ordering activity shall provide the RFQ (including the statement of work and the evaluation criteria) to any schedule contractor who requests a copy of it.

(d) Evaluation. The ordering activity shall evaluate all responses received using the evaluation criteria provided to the schedule contractors. The ordering activity is responsible for considering the level of effort and the mix of labor proposed to perform a specific task being ordered, and for determining that the total price is reasonable. Place the order with the schedule contractor that represents the best value (see 8.404(d) and 8.405-4). After award, ordering activities should provide timely notification to unsuccessful offerors. If an unsuccessful offeror requests information on an award that was based on factors other than price alone, a brief explanation of the basis for the award decision shall be provided.

(e) Use of time-and-materials and labor-hour orders for services. When placing a time-and-materials or labor-hour order for services, see 8.404(h).

(f) Minimum documentation. The ordering activity shall document—

(1) The schedule contracts considered, noting the contractor from which the service was purchased;

(2) A description of the service purchased;

(3) The amount paid;

(4) The evaluation methodology used in selecting the contractor to receive the order;

(5) The rationale for any tradeoffs in making the selection;

(6) The price reasonableness determination required by paragraph (d) of this subsection;

(7) The rationale for using other than—

(i) A firm-fixed price order; or

(ii) A performance-based order; and .

(8) When an order exceeds the simplified acquisition threshold, evidence of compliance with the ordering procedures at 8.405-2(c).

[69 FR 34234, June 18, 2004, as amended at 70 FR 43579, July 27, 2005; 76 FR 14553, Mar. 16, 2011; 77 FR 197, Jan. 3, 2012; 89 FR 30253, Apr. 22, 2024]
The 10 cases that cite 48 C.F.R. § 8.405-2 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENMORI Assocs., Inc. v. United States, 102 Fed. Cl. 503 (Fed. Cl. 2011).
cites § 8.405-2 3×cited by 72 cases
Where it cites § 8.405-2
“§ 253b(a) and the implementing regulation at 48 C.F.R. § 8.405-2 (d); the Procurement Integrity Act (“PIA”), 41 U.”
The case’s holding
Lost potential profits from arbitrary procurement actions constitute irreparable injury sufficient to support a claim for injunctive relief.
Later courts cite it for
“it is well-established that the potential profits that are lost to offerors when arbitrary procurement actions would deprive them of the opportunity to compete for a contract will normally be sufficient to constitute irreparable injury.” · 5 citing courts
2
GREENTelos Corp. v. United States, 129 Fed. Cl. 573 (Fed. Cl. 2016).
cites § 8.405-2 3×cited by 18 cases
Where it cites § 8.405-2
“Telos argued that the Court impermissibly allowed the streamlined approach to acquisitions under the Federal Supply Schedule (FSS) program, subpart 8.”
The case’s holding
Lost profits and adverse consequences to employees are considered the unavoidable results of a contract coming to an end.
Later courts cite it for
“while an appeal is pending from an interlocutory order or final judgment that grants, dissolves, or denies an injunction, the court may suspend, modify, restore, or grant an injunction on terms for bond or other terms that secure the opposing party's rights.” · 5 citing courts
3
GREENAkal Sec., Inc. v. United States, 87 Fed. Cl. 311 (Fed. Cl. 2009).
cites § 8.405-2 1×cited by 45 cases
Where it cites § 8.405-2
“” 48 C.F.R. § 8.405-2 (d) (2008). The Agency has not provided Akal with a debriefing on the award of the Indiana BPA.”
The case’s holding
The strength of a plaintiff's merits arguments largely determines the court's view of irreparable injury.
Later courts cite it for
“must show that without a preliminary injunction it will suffer irreparable harm before a decision can be rendered on the merits.” · 10 citing courts
4
GREENSpectrum Comm, Inc. v. United States, 126 Fed. Cl. 778 (Fed. Cl. 2016).
cites § 8.405-2 2×cited by 1 case
Where it cites § 8.405-2
“48 C.F.R. § 8.405-2 (d) (2012). Unlike competitive procurements under FAR Part 15, procurements under FAR Part 8.”
5
NO FLAGGen. Dynamics Mission Sys., Inc. v. United States, No. 18-49 (Fed. Cl. Apr. 9, 2018).
cites § 8.405-2 2×cited by 0 cases
Where it cites § 8.405-2
“at 31 (quoting 48 C.F.R. § 8.405-2 (d)). In this case, the RFQ provided that “[t]he [PET would] evaluate total evaluated price.”
6
NO FLAGCenterra Grp., LLC v. United States, No. 18-219 (Fed. Cl. June 7, 2018).
cites § 8.405-2 1×cited by 0 cases
Summary
No passage or summary on file for this case yet.
7
NO FLAGSparksoft Corp. v. United States, No. 18-1708 (Fed. Cl. Jan. 31, 2019).
cites § 8.405-2 1×cited by 0 cases
Where it cites § 8.405-2
“222-46; compensation realism; price UNITED STATES, ) reasonableness; 48 C.F.R. § 8.405-2 (d); ) ambiguity in solicitation; agency’s answers Defendant, ) to questions ostensibly limiting its ) assessment of compensation realism; and ) declaratory relief ) SCOPE INFOTECH, INC.”
8
NO FLAGLand Shark Shredding, LLC v. United States, No. 18-1568 (Fed. Cl. Mar. 21, 2019).
cites § 8.405-2 1×cited by 0 cases
Where it cites § 8.405-2
“405-2(d) requires the contracting officer to make an independent evaluation of LSS’s price reasonableness. The Plaintiff disagrees with that argument because in this case LSS was asked to bid prices per bin, not hourly labor rates.”
9
NO FLAGMetro. Interpreters & Translators, Inc. v. United States, No. 19-748 (Fed. Cl. Oct. 16, 2019).
cites § 8.405-2 1×cited by 0 cases
Where it cites § 8.405-2
“48 C.F.R. § 8.405-2 (d) (2018). The RFQ also explicitly stated that: 3.”
10
NO FLAGLand Shark Shredding, LLC v. United States, No. 20-1230 (Fed. Cir. Jan. 11, 2021).
cites § 8.405-2 1×cited by 0 casesunpublished
Where it cites § 8.405-2
“” The fact that a separate determination is not required does not mean that it cannot be performed, and in any event, such an anal- ysis is required here under 48 C.F.R. § 8.405-2 (d). (“The ordering activity shall evaluate all responses received us- ing the evaluation criteria…”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
200920152021

One bar per year. Tallest: 3 cases in 2019. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Fed. Cl.9Fed. Cir.1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com