C.F.R. homeSearch C.F.R.
C.F.R.Title 48Chapter 1—Federal Acquisition RegulationSubchapter B—Acquisition PlanningPart 9—Contractor QualificationsSubpart 9.4—Debarment, Suspension, and Ineligibility

48 C.F.R. § 9.405-1 (2026)

9.405-1 Continuation of current contracts.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1997–2018 4citing cases
At a glance

Courts have cited this section in 4 opinions since 1997.

(a) Contractors debarred, suspended, proposed for debarment, or voluntarily excluded. (1) Notwithstanding the debarment, suspension, proposed debarment, or voluntary exclusion, of a contractor, agencies may continue contracts or subcontracts in existence at the time the contractor was debarred, suspended, proposed for debarment, or voluntarily excluded, unless unless the agency head directs otherwise. A decision as to the type of termination action, if any, to be taken should be made only after review by agency contracting and technical personnel and by counsel to ensure the propriety of the proposed action.

(2) For contractors debarred, suspended, proposed for debarment, or voluntarily excluded, unless the agency head makes a written determination of the compelling reasons for doing so, ordering activities shall not—

(i) Place orders exceeding the guaranteed minimum under indefinite quantity contracts;

(ii) Place orders under Federal Supply Schedule contracts, blanket purchase agreements, or basic ordering agreements; or

(iii) Add new work, exercise options, or otherwise extend the duration of current contracts or orders.

(b) Ineligible contractors. A covered agency, as defined in 9.110-1, shall terminate existing contracts and shall not place new orders or award new contracts with contractors that have been declared ineligible pursuant to 10 U.S.C. 983 (see 9.110), except for contracts at or below the simplified acquisition threshold or contracts for the acquisition of commercial products and commercial services.

[85 FR 67621, Oct. 23, 2020, as amended at 86 FR 61021, Nov. 4, 2021; 90 FR 512, Jan. 3, 2025]
The 4 cases that cite 48 C.F.R. § 9.405-1 most heavily, weighted by court and treatment. RelevanceNewestTreatment
cites § 9.405-1 1×cited by 38 cases
The case’s holding
A statute restricting federal procurement of certain products is not a bill of attainder if it furthers an actual nonpunitive purpose such as protecting national security.
Later courts cite it for
“some conceivable nonpunitive purpose, but rather an actual nonpunitive purpose.” · 1 citing court
2
GREENMark Dunning Indus., Inc. v. United States, 58 Fed. Cl. 216 (Fed. Cl. 2003).
cites § 9.405-1 3×cited by 9 cases
Where it cites § 9.405-1
“48 C.F.R. § 9.405-1 governs the effects of debarment.”
Later courts cite it for
“the sba is the best interpreter of its own regulations.” · 2 citing courts
3
GREENPhillips v. Mabus, 894 F. Supp. 2d 71 (D.D.C. 2012).
cites § 9.405-1 1×cited by 29 cases
Where it cites § 9.405-1
“' Reply at 9 (citing 48 C.F.R. § 9.405-1 (b)(3)). This provision is not dispositive here, as it only governs contractors who have been officially debarred.”
The case’s holding
De facto debarment occurs when government conduct or statements effectively blacklist a contractor from pursuing work without adequate notice and a meaningful hearing.
Later courts cite it for
“de facto debarment occurs when a contractor has, for all practical purposes, been suspended or blacklisted from working with a government agency without due process, namely, adequate notice and a meaningful hearing.” · 3 citing courts
4
GREENCom. Drapery Contractors, Inc. v. United States, 967 F. Supp. 1 (D.D.C. 1997).
cites § 9.405-1 1×cited by 4 cases
Where it cites § 9.405-1
“Federal acquisition regulation claim relating to cancellation The parties disagree about whether GSA’s actions in cancelling the contracts were governed by the federal acquisition regulation concerning continuation of contracts, 48 C.F.R. § 9.405-1 , or by GSA’s own implementing…”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
199720072018

One bar per year. Tallest: 1 case in 1997. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
D.D.C.2D.C. Cir.1Fed. Cl.1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com