What general requirements apply to pipelines regulated under this part?

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1987 1citing case
At a glance

Courts have cited this section in 1 opinion since 1987.

(a) No person may operate a segment of pipeline listed in the first column of paragraph (a)(3) of this section that is readied for service after the date in the second column, unless:

(1) The pipeline has been designed, installed, constructed, initially inspected, and initially tested in accordance with this part; or

(2) The pipeline qualifies for use under this part according to the requirements in § 192.14.

(3) The compliance deadlines are as follows:

PipelineDate
(i) Offshore gathering pipelineJuly 31, 1977.
(ii) Regulated onshore gathering pipeline to which this part did not apply until April 14, 2006March 15, 2007.
(iii) Regulated onshore gathering pipeline to which this part did not apply until May 16, 2022May 16, 2023.
(iv) All other pipelinesMarch 12, 1971.

(b) No person may operate a segment of pipeline listed in the first column of this paragraph (b) that is replaced, relocated, or otherwise changed after the date in the second column of this paragraph (b), unless the replacement, relocation or change has been made according to the requirements in this part.

PipelineDate
(1) Offshore gathering pipelineJuly 31, 1977.
(2) Regulated onshore gathering pipeline to which this part did not apply until April 14, 2006March 15, 2007.
(3) Regulated onshore gathering pipeline to which this part did not apply until May 16, 2022May 16, 2023.
(4) All other pipelinesNovember 12, 1970.

(c) Each operator shall maintain, modify as appropriate, and follow the plans, procedures, and programs that it is required to establish under this part.

(d) Each operator of an onshore gas transmission pipeline must evaluate and mitigate, as necessary, significant changes that pose a risk to safety or the environment through a management of change process. Each operator of an onshore gas transmission pipeline must develop and follow a management of change process, as outlined in ASME B31.8S, section 11 (incorporated by reference, see § 192.7), that addresses technical, design, physical, environmental, procedural, operational, maintenance, and organizational changes to the pipeline or processes, whether permanent or temporary. A management of change process must include the following: reason for change, authority for approving changes, analysis of implications, acquisition of required work permits, documentation, communication of change to affected parties, time limitations, and qualification of staff. For pipeline segments other than those covered in subpart O of this part, this management of change process must be implemented by February 26, 2024. The requirements of this paragraph (d) do not apply to gas gathering pipelines. Operators may request an extension of up to 1 year by submitting a notification to PHMSA at least 90 days before February 26, 2024, in accordance with § 192.18. The notification must include a reasonable and technically justified basis, an up-to-date plan for completing all actions required by this section, the reason for the requested extension, current safety or mitigation status of the pipeline segment, the proposed completion date, and any needed temporary safety measures to mitigate the impact on safety.

[35 FR 13257, Aug. 19, 1970, as amended by Amdt. 192-27, 41 FR 34605, Aug. 16, 1976; Amdt. 192-30, 42 FR 60148, Nov. 25, 1977; Amdt. 192-102, 71 FR 13303, Mar. 15, 2006; Amdt. 192-129, 86 FR 63298, Nov. 15, 2021; Amdt. 192-132, 87 FR 52268, Aug. 24, 2022; Amdt. 192-135, 89 FR 33280, Apr. 29, 2024]
The 1 case that cites 49 C.F.R. § 192.13 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENANR Pipeline Co. v. Iowa State Com. Comm'n, 828 F.2d 465 (8th Cir. 1987).
cites § 192.13 2×cited by 3 cases
Where it cites § 192.13
“See 49 C.F.R. §§ 192.13 , .305, .307, .501-17 (1986).”
Later courts cite it for
“iowa may be able to enact legislation to protect its valuable topsoil and other aspects of the environment, and to provide private damage remedies, as long as the state regulations do not conflict with existing federal standards.” · 2 citing courts

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com