49 C.F.R. § 192.627

Tapping pipelines under pressure

Read at: eCFRecfr.gov CornellLII GovInfogovinfo.gov CasesGoogle Scholar

Each tap made on a pipeline under pressure must be performed by a crew qualified to make hot taps.

Notes of Decisions
Cited in 1 case (1 in the last 5 years), 2021–2021 · leading case: Southcross Energy Partners GP, LLC. v. Ivy Gonzalez, 625 S.W.3d 869 (Tex. App.—San Antonio 2021).
Southcross Energy Partners GP, LLC. v. Ivy Gonzalez, 625 S.W.3d 869 (Tex. App.—San Antonio 2021). “5 Alternatively, Southcross was required to ensure the “tap made on a pipeline under pressure [was] performed by a crew qualified to make hot taps,” 49 C.F.R. § 192.627 , and this “qualified crew” requirement is therefore a nondelegable duty.”