Colo. Rev. Stat. § 40-4-102 (2024)
Extensions and improvements prescribed - when
Edition and currency
Other sources
Courts have cited this section in 3 opinions since 1976.
(1) Whenever the commission, after a hearing upon its own motion, upon appeal by a public utility or power authority from a local government action pursuant to section 29-20-108 (5), C.R.S., or upon complaint, finds that the additions, extensions, repairs, or improvements to or change in the existing plant, equipment, facilities, or other physical property of any public utility or of any two or more public utilities ought reasonably to be made, that a new structure should be erected to promote the security or convenience of its employees or the public or in any other way to secure adequate service or facilities, or that the conditions imposed by a local government action unreasonably impair the ability of a public utility or power authority to provide safe, reliable, and economical service, the commission shall make and serve an order directing that such additions, extensions, repairs, improvements, or changes be made or such structure be erected in the manner and within the time specified in such order. If the commission orders the erection of a new structure, the selection of the site for such structure shall be subject to the approval of the commission. If a public utility or power authority appeals an order from a local government action under section 29-20-108, C.R.S., the commission may require that the public utility or power authority reimburse the commission for the reasonable expenses, attorney fees, and expert witness fees the commission incurs in reviewing the appeal. Any fee collected pursuant to this section shall be remitted to the state treasurer, who shall credit such fee to the public utilities commission fixed utility fund created pursuant to section 40-2-114.
(2) If any additions, extensions, repairs, improvements, or changes or any new structures which the commission has ordered to be erected require joint action of two or more public utilities, the commission shall notify the public utilities that such additions, repairs, improvements, or changes or new structures have been ordered and that the same shall be made at their joint cost, whereupon the public utilities shall have such reasonable time as the commission may grant within which to agree upon the portion or division of cost of such additions, repairs, extensions, improvements, or changes or new structures which each shall bear. If, at the expiration of such time, such public utilities fail to file with the commission a statement that an agreement has been made for a division or apportionment of the cost or expense of such additions, extensions, repairs, improvements, or changes or new structures, the commission has the authority, after further hearing, to make an order fixing the proportion of such expense to be borne by each public utility and the manner in which the same shall be paid or secured.
Source: L. 13: p. 476, § 25. C.L. § 2936. CSA: C. 137, § 26. CRS 53: § 115-4-2. C.R.S. 1963: § 115-4-2. L. 69: p. 933, § 20. L. 2001: (1) amended, p. 597, § 4, effective May 30.
Cross references: For the legislative declaration contained in the 2001 act amending subsection (1), see section 1 of chapter 183, Session Laws of Colorado 2001.
- Where it cites § 40-4-102
- “PSCo claims that, under Article XXV of the Colorado Constitution and section 40-4-102, 11 C.R.S. (2000), PUC has the exclusive jurisdiction to balance various public and private interests affected by the actions of public utilities.”
- The case’s holding
- A nuisance claim requires a plaintiff to establish that a defendant has unreasonably interfered with the use and enjoyment of the property.
- Later courts cite it for
- “is looked upon with disfavor, and a complaint should not be dismissed unless it appears beyond a doubt that a plaintiff can prove no set of facts in support of her claim which would entitle her to relief.” · 3 citing courts
- Where it cites § 40-4-102
- “(1984), and the Commission has the authority to require an electric utility to make “additions, extensions, repairs, or improvements” to the utility’s existing facilities if the Commission finds such changes are necessary to “secure adequate service or facilities” for the public…”
- Where it cites § 40-4-102
- “1963, section 40-4-102, 4 provides: “(1) A person who intentionally sets fire to, burns, causes to be burned, or by the use of any explosive, damages or destroys, or causes to be damaged or destroyed, any building or occupied structure of another without his consent, commits…”
- Later courts cite it for
- “require that the 'building' or 'structure' actually 'burn,' which is defined . . . as ignition of or an alteration or destruction of the fiber or texture of the materials composing the 'building' or 'structure.” · 1 citing court
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
One bar per year. Tallest: 1 case in 1976. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.
Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.
Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.
Edition shown: C.R.S. 2024: the 2025 and 2026 sessions are not included. Syfert holds no earlier or later version of this section.