Conn. Gen. Stat. § 25-32d (2025)
Water supply plans
Edition and currency
Other sources
Courts have cited this section in 8 opinions since 1998, 3 of them in the last five years.
(b) Any water supply plan submitted pursuant to this section shall evaluate the water supply needs in the service area of the water company submitting the plan and propose a strategy to meet such needs. The plan shall include: (1) A description of existing water supply systems; (2) an analysis of future water supply demands; (3) an assessment of alternative water supply sources which may include sources receiving sewage and sources located on state land; (4) contingency procedures for public drinking water supply emergencies, including emergencies concerning the contamination of water, the failure of a water supply system or the shortage of water; (5) a recommendation for new water system development; (6) a forecast of any future land sales, an identification which includes the acreage and location of any land proposed to be sold, sources of public water supply to be abandoned and any land owned by the company which it has designated, or plans to designate, as class III land; (7) provisions for strategic groundwater monitoring; (8) an analysis of the impact of water conservation practices and a strategy for implementing supply and demand management measures; (9) on and after January 1, 2004, an evaluation of source water protection measures for all sources of the water supply, based on the identification of critical lands to be protected and incompatible land use activities with the potential to contaminate a public drinking water source; and (10) a brief summary of the water company's underground infrastructure replacement practices, which may include current and future infrastructure needs, methods by which projects are identified and prioritized for rehabilitation and replacement and funding needs.
(c) For security and safety reasons, procedures for sabotage prevention and response shall be provided separately from the water supply plan as a confidential document to the Department of Public Health. Such procedures shall not be subject to disclosure under the Freedom of Information Act, as defined in section 1-200. Additionally, procedures for sabotage prevention and response that are established by municipally owned water companies shall not be subject to disclosure under the Freedom of Information Act, as defined in section 1-200.
(d) Any water supply plan, including any subsequent revisions to such plan, submitted by a water company pursuant to this section shall be accompanied by a redacted copy of such plan, or subsequent revision to such plan. When submitting a redacted copy of a water supply plan, a water company shall redact the information exempted from disclosure under subsection (e) of this section.
(e) The following records filed with any public agency by a water company are confidential and shall not be subject to disclosure under the Freedom of Information Act, as defined in section 1-200:
(1) Cybersecurity plans and measures, supervisory control and data acquisition systems, information and communications systems, system access codes and specifications, vulnerability assessments, internal security audits, security manuals, security training or security reports, including, but not limited to, security assessments, plans and procedures, operational and design specifications of water and sewage treatment facility security systems or risk management plans;
(2) Emergency contingency plans and emergency preparedness plans, incident management plans, response, recovery and mitigation plans or critical customer lists, including plans provided by a person to a federal or state agency or a federal, state or local emergency management agency or official, or documents or portions of documents that identify or describe procedures for sabotage prevention and response, except drought management and response plans shall be subject to disclosure;
(3) Design drawings or maps identifying specific locations, detailed schematics and construction details of wells, source water intakes, water mains, tunnels, storage facilities, water and sewage treatment facilities or pump stations and pressure reducing stations, and other distribution system pressure and flow control valves and facilities, provided information regarding general location of water mains, wells and interconnections shall be subject to disclosure;
(4) Dam specifications or dam safety documents described in sections 22a-401 to 22a-411, inclusive, including (A) inspections reports, engineering studies or reports, drawings, plans and specifications detailing construction or rehabilitation, and (B) emergency action plans prepared pursuant to section 22a-411a including plans provided to a federal or state agency or a federal, state or local emergency response or emergency management agency or official;
(5) Building floor or structural plans, specifications of structural elements or building security systems or codes;
(6) Detailed network topology maps;
(7) Specific locations of or specifications regarding electrical power, standby generators or fuel systems for water system facilities, except that general information regarding electrical power, standby generators or fuel systems for water system facilities may be disclosed;
(8) Operational specifications, schematics and procedures of water and sewage treatment plant processes and associated equipment and chemicals, including, but not limited to, facility use of chlorine gas storage and delivery and the location of chemicals, except that a general description of any such treatment plant may be disclosed;
(9) Logs or other documents that contain information regarding the movement or assignment of water system and sewage treatment facilities and security personnel;
(10) Distribution system hydraulic models; or
(11) Any other record if there are reasonable grounds to believe the disclosure of such record may result in a safety risk. Upon request by the water company, such record may be reviewed by the Commissioner of Administrative Services, in consultation with the chief executive officer of the executive branch state agency or municipal water or sewage treatment entity that has custody of such record, to determine if such reasonable grounds exist.
(f) The Commissioner of Public Health, in consultation with the Commissioner of Energy and Environmental Protection and the Public Utilities Regulatory Authority, shall adopt regulations in accordance with the provisions of chapter 54. Such regulations shall include a method for calculating safe yield, the contents of emergency contingency plans and water conservation plans, the contents of an evaluation of source water protection measures, a process for approval, modification or rejection of plans submitted pursuant to this section, a schedule for submission of the plans and a mechanism for determining the completeness of the plan. The plan shall be deemed complete if the commissioner does not request additional information within ninety days after the date on which the plan was submitted or, in the event that additional information has been requested, within forty-five days after the submission of such information, except that the commissioner may request an additional thirty days beyond the time in which the application is deemed complete to further determine completeness. In determining whether the water supply plan is complete, the commissioner may request only information that is specifically required by regulation. The Department of Energy and Environmental Protection and the Public Utilities Regulatory Authority, in the case of any plan which may impact any water company regulated by that agency, shall have ninety days upon notice that a plan is deemed complete to comment on the plan.
(g) Any water company, when submitting any plan or revision or amendment of a plan after July 1, 1998, which involves a forecast of land sales, abandonment of any water supply source, sale of any lands, or land reclassification, shall provide notice, return receipt requested, to the chief elected official of each municipality in which the land or source is located, the Nature Conservancy, the Trust for Public Land and the Land Trust Service Bureau and any organization on the list prepared under subsection (b) of section 16-50c. Such notice shall specify any proposed abandonment of a source of water supply, any proposed changes to land sales forecasts or any land to be designated as class III land in such plan. Such notice shall specify the location and acreage proposed for sale or reclassification as class III land and identify sources to be abandoned and shall be provided no later than the date of submission of such plan or revision. Such notice shall indicate that public comment on such plan or revision shall be received by the Commissioners of Public Health and Energy and Environmental Protection not later than sixty days after the date of notice. The Commissioner of Public Health shall take such comment into consideration in making any determination or approval under this section.
(P.A. 84-502, S. 1, 3; P.A. 88-354, S. 5; P.A. 89-305, S. 21, 32; 89-327, S. 6, 7; P.A. 90-271, S. 17, 24; P.A. 93-381, S. 9, 39; P.A. 95-124, S. 1, 3; 95-257, S. 12, 21, 58; P.A. 96-180, S. 92, 166; P.A. 97-314, S. 3; P.A. 98-157, S. 7, 15; P.A. 02-102, S. 1; P.A. 03-278, S. 85; P.A. 09-220, S. 2; P.A. 11-80, S. 1, 74; P.A. 17-211, S. 3.)
History: P.A. 88-354 added Subsec. (b)(7) re forecasts of future land sales; P.A. 89-305 amended Subsec. (b)(3) by adding requirement that plans include an assessment of sources located on state land and by adding new Subdiv. re strategic groundwater monitoring; P.A. 89-327 amended Subsec. (b) by making technical changes to numeration and adding new Subdiv. re analysis of water conservation practices and requirement that provisions of the plan under Subdivs. (4) and (9) be prepared in accordance with the memorandum of understanding; P.A. 90-271 corrected an internal reference in Subsec. (b); P.A. 93-381 replaced commissioner of health services with commissioner of public health and addiction services, effective July 1, 1993; P.A. 95-124 deleted Subsec. (b)(9), which required a water plan to include information deemed necessary by the Commissioners of Public Health and Environmental Protection or Public Utilities Control Authority, deleted the words “but not be limited to” in Subsec. (b) before the list of what the plan must include and in Subsec. (c) before what the regulations must include, amended Subsec. (c) to require that the regulations include a method for calculating safe yield, the contents of emergency and conservation plans and a mechanism for determining completeness of the plan and to require that plan be deemed complete under specified circumstances and time frames; P.A. 95-257 replaced Commissioner and Department of Public Health and Addiction Services with Commissioner and Department of Public Health, effective July 1, 1995; P.A. 96-180 amended Subsec. (c) to authorize the commissioner to request information required by regulation in reviewing water supply plans, deleting a former limitation re only regulations required by this subsection, effective June 3, 1996; P.A. 97-314 amended Subsec. (a) to require notice of revisions of water supply plans to be sent to certain private, nonprofit, land-holding organizations; P.A. 98-157 amended Subsec. (a) by deleting notice requirements re revision of water supply plan, Subsec. (b)(6) to require that plan identify the acreage and location of land proposed to be sold, sources of public water supply to be abandoned, and any land owned by the company which it has designated, or plans to designate, as class III land, Subsec. (c) by adding that Departments of Environmental Protection and Public Utility Control, in the case of any plan which may impact any water company regulated by the agency, shall have 90 days upon notice that a plan is deemed complete to comment on the plan, and by adding a new Subsec. (d) setting out notice requirements when any water company submits a plan or revision or amendment of a plan after July 1, 1998, and requiring the Commissioner of Public Health to take into consideration any public comments when making any determination or approval under this section, effective July 1, 1998; P.A. 02-102 amended Subsec. (a) by making a technical change, added Subsec. (b)(9) re evaluations of source water protection measures on and after January 1, 2004, added new Subsec. (c) re sabotage prevention and response procedures, redesignated existing Subsecs. (c) and (d) as Subsecs. (d) and (e) and amended redesignated Subsec. (d) re requirement for regulations to include “the contents of an evaluation of source water protection measures”; P.A. 03-278 made a technical change in Subsec. (e), effective July 9, 2003; P.A. 09-220 amended Subsec. (a) by changing time frame re filing revised water supply plan to not less than 6 or more than 9 years after date of most recently approved plan, by requiring water companies that fail to adhere to drinking water standards to file revised plans 6 years after date of most recently approved plan, by requiring that plan revisions shall minimally consist of updates to elements that have changed since date of most recently approved plan and by making technical changes, and added Subsec. (b)(10) re brief summary of the water company's underground infrastructure replacement practices; P.A. 11-80 changed “Department of Public Utility Control” and “Public Utilities Control Authority” to “Public Utilities Regulatory Authority”, changed “Commissioner of Environmental Protection” to “Commissioner of Energy and Environmental Protection” and changed “Department of Environmental Protection” to “Department of Energy and Environmental Protection”, effective July 1, 2011; pursuant to P.A. 11-80, a reference to “Commissioner of Environmental Protection” was changed editorially by the Revisors to “Commissioner of Energy and Environmental Protection” in Subsec. (a), effective July 1, 2011; P.A. 17-211 added new Subsec. (d) re redacted copy of water supply plan, added new Subsec. (e) re confidentiality of water company records, and redesignated existing Subsecs. (d) and (e) as Subsecs. (f) and (g), effective July 1, 2017.
| (Return to Chapter Table of Contents) |
(Return to List of Chapters) |
(Return to List of Titles) |
- Where it cites § 25-32d
- “Under General Statutes § 25-32d (a), [34] water companies are required to submit *987 a water supply plan to the department of public health for approval "with the concurrence of the Commissioner of Environmental Protection.”
- The case’s holding
- State action antitrust immunity applies only when challenged conduct is specifically directed or required by statute rather than merely approved by regulators or implied by a general mandate.
- Later courts cite it for
- “it is well settled that in construing statutes, our fundamental objective is to ascertain and give effect to the apparent intent of the legislature. . . . we seek to determine, in a reasoned manner, the meaning of the statutory language as applied to the facts of the case, including the question of whether the language actually does apply.” · 3 citing courts
- Where it cites § 25-32d
- “Among these statutory responsibilities are, for example, the preparation of detailed water supply plans, under General Statutes § 25-32d, and the provision of water conservation educational materials, pursuant to General Statutes § 25-32k. We view the scope of the present…”
- The case’s holding
- A municipality that owns and controls a water division is itself a water company, so all its land is subject to the department's jurisdiction under the water company statutes.
- Where it cites § 25-32d
- “’ A water supply plan is required to ‘evaluate the water supply needs in the service area of the water company submitting the plan and [to] propose a strategy to meet such needs.”
- Where it cites § 25-32d
- “In malting a decision on an application, the commissioner shall consider (1) capital expenditures and other resource commitments made prior to July 1, 1982, in connection with a proposed diversion, but such expenditures or commitments shall not be binding in favor of such…”
- The case’s holding
- Whether conduct constitutes an unreasonable impairment under the environmental protection act depends on whether that conduct complies with the specific regulatory scheme governing it.
- Later courts cite it for
- “when there is an environmental legislative and regulatory scheme in place that specifically governs the conduct that the plaintiff claims constitutes an unreasonable impairment under the act, whether the conduct is unreasonable under the act will depend on whether it complies with that scheme” · 8 citing courts
- Where it cites § 25-32d
- “gnment of security personnel at government-owned or leased institutions or facilities; “(viii) Emergency plans and emergency recovery or response plans; and “(ix) With respect to a water company, as defined in section 25-32a, that provides water service: Vulnerability…”
- Where it cites § 25-32d
- “In August, 2022, Aquarion instituted the present general rate case, seeking, among other things, to recover its deferred conservation expenses from ratepayers.”
- Where it cites § 25-32d
- “nment of class I land, except as provided in subsection (d), and shall not grant a permit for a change in use of class I land unless the applicant demonstrates that such change will not have a significant adverse impact upon the present and future purity and adequacy of the…”
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
One bar per year. Tallest: 2 cases in 2005. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.
Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.
Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.
Edition shown: laws through the 2024 session: the source has not yet published 2025 Public Acts (checked Sept. 2026). Syfert holds no earlier or later version of this section.