(1)(a) By January 1, 2027, each county with a population of 75,000 or greater shall create and implement a program for the purpose of making available development preapplication consultation services at an applicant’s request. This subsection may not be construed to affect or require the modification of a county program that makes available the same or substantially similar development preapplication consulting services to an applicant for a development permit or development order, including a program that requires mandatory preapplication meetings for specified types of developments, if such county program exists on or before July 1, 2026.1. The preapplication consultation services authorized in this subsection are limited to those applications for permits as defined in s. 163.3169. 2. The county may use a qualified contractor or a qualified contractor firm as defined in s. 163.3169 to fulfill the preapplication consultation services required in this subsection. (b) A development preapplication consultation services program must, at minimum, provide all of the following:1. The minimum information that must be submitted in an application for a permit as defined in s. 163.3169. 2. The review and precertification of completeness of the application and all related documents, including site engineering plans or site plans or their functional equivalent, or plats, and their compliance with all relevant existing land development regulations.
(c) If an applicant chooses to use the development preapplication consultation services program, the county, upon receipt of the proposed development application, shall confirm receipt, verify completeness, and issue a written notification to the applicant indicating that all required information has been submitted, or specify in writing with particularity any deficiencies in the application, within 5 business days. If the application is deficient, the applicant has 30 days to address the deficiencies by submitting the required additional information. If the county fails to issue the written notification within 5 business days, the application is deemed complete by operation of law without conditions, and the county must process the application as required in paragraph (d).
(d)1. Upon receipt of the applicant’s completed application, the county must process the application for final action and must approve, approve with conditions, or deny the application within 45 days after submission of a complete application, except the county may not review again those plans specified in subparagraph (b)2.
2. If the county fails to take final action to approve, approve with conditions, or deny the application within 45 days, the applicant shall notify the county in writing. If the county fails to respond within 10 days, the application is deemed approved by operation of law without conditions, and the applicant is entitled to proceed with the proposed activity or development as though the county had granted unconditional approval. Approval pursuant to this subparagraph may not be construed to relieve the applicant of the obligation to comply with all other applicable federal, state, and local laws, regulations, and ordinances.
(2) If an applicant for a development permit or development order is not eligible, does not request, or elects not to use the county’s development preapplication consulting services program pursuant to subsection (1), all of the following requirements shall apply:(a) A county shall specify in writing the minimum information that must be submitted in an application for a zoning approval, rezoning approval, subdivision approval, certification, special exception, or variance. A county shall make the minimum information available for inspection and copying at the location where the county receives applications for development permits and orders, provide the information to the applicant at a preapplication meeting, or post the information on the county’s website.
(b)1. Within 5 business days after receiving an application for approval of a development permit or development order, a county shall confirm receipt of the application using contact information provided by the applicant. Within 30 days after receiving an application for approval of a development permit or development order, a county must review the application for completeness and issue a written notification to the applicant indicating that all required information is submitted or specify in writing with particularity any areas that are deficient. If the application is deficient, the applicant has 30 days to address the deficiencies by submitting the required additional information.
2. For applications that do not require final action through a quasi-judicial hearing or a public hearing, the county must approve, approve with conditions, or deny the application for a development permit or development order within 120 days after the county has deemed the application complete.
3. For applications that require final action through a quasi-judicial hearing or a public hearing, the county must approve, approve with conditions, or deny the application for a development permit or development order within 180 days after the county has deemed the application complete.
4. Both parties may agree in writing or in a public meeting or hearing to an extension of time, particularly in the event of a force majeure or other extraordinary circumstance. An approval, approval with conditions, or denial of the application for a development permit or development order must include written findings supporting the county’s decision.
The timeframes contained in this paragraph do not apply in an area of critical state concern, as designated in s. 380.0552. The timeframes contained in this paragraph restart if an applicant makes a substantive change to the application. As used in this paragraph, the term “substantive change” means an applicant-initiated change of 15 percent or more in the proposed density, intensity, or square footage of a parcel.
(c)1. When reviewing an application for a development permit or development order that is certified by a professional listed in s. 403.0877, a county may not request additional information from the applicant more than three times, unless the applicant waives the limitation in writing. 2. If a county makes a request for additional information and the applicant submits the required additional information within 30 days after receiving the request, the county must review the application for completeness and issue a letter indicating that all required information has been submitted or specify with particularity any areas that are deficient within 30 days after receiving the additional information.
3. If a county makes a second request for additional information and the applicant submits the required additional information within 30 days after receiving the request, the county must review the application for completeness and issue a letter indicating that all required information has been submitted or specify with particularity any areas that are deficient within 10 days after receiving the additional information.
4. Before a third request for additional information, the applicant must be offered a meeting to attempt to resolve outstanding issues. If a county makes a third request for additional information and the applicant submits the required additional information within 30 days after receiving the request, the county must deem the application complete within 10 days after receiving the additional information or proceed to process the application for approval or denial unless the applicant waived the county’s limitation in writing as described in subparagraph 1.
5. Except as provided in subsection (4), if the applicant believes the request for additional information is not authorized by ordinance, rule, statute, or other legal authority, the county, at the applicant’s request, shall proceed to process the application for approval or denial.
(d) A county must issue a refund to an applicant equal to:1. Ten percent of the application fee if the county fails to issue written notification of completeness or written specification of areas of deficiency within 30 days after receiving the application.
2. Ten percent of the application fee if the county fails to issue a written notification of completeness or written specification of areas of deficiency within 30 days after receiving the additional information pursuant to subparagraph (c)2.
3. Twenty percent of the application fee if the county fails to issue a written notification of completeness or written specification of areas of deficiency within 10 days after receiving the additional information pursuant to subparagraph (c)3.
4. Fifty percent of the application fee if the county fails to approve, approves with conditions, or denies the application within 30 days after conclusion of the 120-day timeframe specified in subparagraph (b)2. or the 180-day timeframe specified in subparagraph (b)3.
5. One hundred percent of the application fee if the county fails to approve, approves with conditions, or denies an application 31 days or more after conclusion of the 120-day timeframe specified in subparagraph (b)2. or the 180-day timeframe specified in subparagraph (b)3.
A county is not required to issue a refund if the applicant and the county agree to an extension of time, the delay is caused by the applicant, or the delay is attributable to a force majeure or other extraordinary circumstance.
(e) When a county denies an application for a development permit or development order, the county shall give written notice to the applicant. The notice must include a citation to the applicable portions of an ordinance, rule, statute, or other legal authority for the denial of the permit or order.