Idaho Code § 45-407 (2026)

Claim of lien for work or labor. 

Edition and currency
text as last checked Oct. 2026 (this copy records no edition or section history). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTtext as last checked Oct. 2026 (this copy records no edition or section history) cited 1963–2007 4citing cases
At a glance

Courts have cited this section in 4 opinions since 1963. The most litigated part is subsection (4) (1 case).

Claim of lien for work or labor. 

Every person, within sixty (60) days after the close of the rendition of the services, or after the close of the work or labor mentioned in sections 45-401 and 45-402, Idaho Code, claiming the benefit hereof, must file for record with the county recorder of the county in which such saw logs, spars, piles, cordwood or other timber was cut, or in which such lumber was manufactured, or, if removed to another county, then in such county, a notice of claim containing a statement of his demand, and the amount thereof, after deducting, as near as possible, all just credits and offsets, with the name of the person by whom he was employed. The notice of claim shall state what such service, work or labor is reasonably worth; and it shall also contain a description of the property to be charged with the lien, sufficient for identification, with reasonable certainty, which notice of claim must be verified by the oath of himself, his agent or attorney, to the effect that the affiant believes the same to be true. Such notice of claim shall be substantially in the following form:

…. claimant, vs. ….
Notice is hereby given that …. of …. county, state of Idaho, claims a lien upon a …. of …. being about …. in quantity, which were cut in …. county, state of Idaho, are marked thus …., and are now lying in …. for labor performed upon and assistance rendered in …. said ….; that the name of the owner or reputed owner is ….; that …. employed said …. to perform such labor and render such assistance upon the following terms, to wit: The said …. agreed to pay the said …. for such labor and assistance ….; that said contract has been faithfully performed and fully complied with on the part of said …., who performed labor upon and assisted in …. said …. for the period of …. that said labor and assistance were so performed and rendered upon said …. between the …. day of …. and the …. day of …., and the rendition of said services was closed on the …. day of …. and …. days have not elapsed since that time; that the amount of claimant’s demand for said services is ….; that no part thereof has been paid except …., and there is now due and unpaid thereon, after deducting all just credits and offsets, the sum of …., in which amount he claims a lien upon said …..
State of Idaho, …. county, ss.
…., being first duly sworn, on oath says that he is …. named in the foregoing claim, has heard the same read and knows the contents thereof, and believes the same to be true …..
Subscribed and sworn to before me this …. day of …., …..
The 4 cases that cite Idaho Code § 45-407 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENChurch v. Roemer, 498 P.2d 1255 (Idaho 1972).
cites § 45-407 2×cited by 33 cases
Where it cites § 45-407
“Simplot Company, it did substantially comply with the provisions of I.C. § 45-407, as required by I.C. § 45-302 (set out in note 1, supra).”
The case’s holding
A farm laborer's lien becomes void as to any party not sued within six months after the lien is filed.
2
GREENIn re Rake, 363 B.R. 146 (Bankr. D. Idaho 2007).
cites § 45-407 1×subsections: (4)cited by 14 cases
Where it cites § 45-407
“, showing that Debtor was identified as the party signing the claim of lien), there is no verification by him in accord with this subsection.”
Later courts cite it for
“cannot simply claim that there is a theoretical chance of a surplus in the estate, but must show that such surplus is a reasonable possibility.” · 2 citing courts
3
GREENAshley Glass Co. v. Hoff, 850 P.2d 193 (Idaho 1993).
cites § 45-407 6×cited by 2 cases
Where it cites § 45-407
“The trial court in ruling for the defendants concluded that I.C. § 45-407 required “[t]he service of a true and correct copy of a claim of lien must be completed within twenty-four (24) hours of the filing of the lien.”
4
GREENTurnboo v. Keele, 383 P.2d 591 (Idaho 1963).
cites § 45-407 2×cited by 7 cases
Where it cites § 45-407
“These contentions are without merit since the statute (I.C. § 45-407) does not require that the notice contain such recitals.”
Later courts cite it for
“a party familiar with the locality to identify the premises intended to be described with reasonable certainty, to the exclusion of others.” · 3 citing courts

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
196319852007

One bar per year. Tallest: 1 case in 1963. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Idaho3Bankr. D. Idaho1
By subsection
(4)1 case
In re Rake, 363 B.R. 146 (Bankr. D. Idaho 2007).“, showing that Debtor was identified as the party signing the claim of lien), there is no verification by him in accord with this subsection.”
Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.