Skip to main content

Idaho Code § 54-5203 (2026)

Definitions. 

Edition and currency
text as last checked Oct. 2026 (this copy records no edition or section history). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTtext as last checked Oct. 2026 (this copy records no edition or section history) ACTIVE · 6 IN 5Y cited 2012–2025 8citing cases
At a glance

Courts have cited this section in 8 opinions since 2012, 6 of them in the last five years. The most litigated part is subsection (4)(a) (3 cases).

Definitions. 

As used in this chapter:

(1)  "Board" means the Idaho contractors board as created in section 54-5206, Idaho Code.
(2)  "Construction" means the performance of building, altering, repairing, adding to, subtracting from, improving, reconstructing, moving, excavating, wrecking or demolishing any building, highway, road, bridge, or other structure, project, development or improvement to real property, or to do any part thereof, including the erection of scaffolding or other structures or works in connection therewith.
(3)  "Contractor" means:
(a)  Any person who in any capacity undertakes, offers to undertake, purports to have the capacity to undertake, or submits a bid to, or does himself or by or through others, perform construction; or
(b)  A construction manager who performs construction management services.
(4)  "Department" means the department of self-governing agencies of the state of Idaho.
(5)  "Division administrator" means the chief administrative officer of the division of occupational and professional licenses.
(6)  "Person" means any individual, firm, partnership, limited liability company, limited liability partnership, corporation, trust, association or other entity or organization capable of conducting business, or any combination thereof acting as a unit.
The 7 cases that cite Idaho Code § 54-5203 most heavily, weighted by court and treatment. RelevanceNewestTreatment
cites § 54-5203 6×subsections: (6) 4× (4)(a) 2×cited by 49 cases
The case’s holding
A limited liability company must register independently under the contractor registration statute because a member's personal registration does not satisfy the entity's statutory obligation.
Later courts cite it for
“only where the language is ambiguous will this court look to rules of construction for guidance and consider the reasonableness of proposed interpretations.” · 2 citing courts
2
GREENAED, Inc. v. KDC Investments, LLC, 307 P.3d 176 (Idaho 2013).
cites § 54-5203 2×subsections: (4)(a) 2×cited by 63 cases
Where it cites § 54-5203
“Under the ICRA, a contractor includes “[a]ny person who in any capacity undertakes, offers to undertake, purports to have the capacity to undertake, or submits a bid to, or does himself or by or through others, perform construction____” I.C. § 54-5203(4)(a) (emphasis added).…”
The case’s holding
A breach of contract claim fails where the underlying contract is illegal and therefore void (summary judgment).
Later courts cite it for
“this court exercises de novo review of a grant of summary judgment and the 'standard of review is the same as the standard used by the trial court in ruling on the motion for summary judgment.” · 12 citing courts
3
GREENGenho v. Riverdale Hot Springs, LLC, 560 P.3d 1041 (Idaho 2024).
cites § 54-5203 2×subsections: (4)(a) 2×cited by 2 cases
Where it cites § 54-5203
“§ 54-5203(4)(a) (amended 2022)). Thus, the contract in AED was illegal from execution and could not be validated by later compliance with ICRA.”
Later courts cite it for
“issues of statutory interpretation are questions of law which this court reviews de novo.” · 2 citing courts
4
NO FLAGBest View Constr. & Dev., LLC, No. 20-00674 (Bankr. D. Idaho Apr. 15, 2022).
cites § 54-5203 6×
Where it cites § 54-5203
“(quoting Idaho Code § 54-5203 (4)(a)). The court further noted that the ICRA defines “person” as “any individual, .”
5
NO FLAGWard v. Bishop Constr., 582 P.3d 28 (Idaho 2025).
cites § 54-5203 4×subsections: (3) 2× (3)(a) 2×
Where it cites § 54-5203
“I.C. § 54-5203(3). While a broad reading of this definition could support Bishop’s argument below and on appeal that Ward was a contractor, subject to ICRA’s requirements, Bishop put on no proof about that subject at trial.”
6
NO FLAGPerron v. Martinez, No. 51474 (Idaho Ct. App. Mar. 5, 2025).
cites § 54-5203 2×subsections: (3)(b) 2×unpublished
Where it cites § 54-5203
“Under I.C. § 54-5203(3)(b), a contractor includes a construction manager who performs construction management services.”
7
NO FLAGNorth Haven Bus. Park, Inc. v. Balance Regenerative Med., PLLC, No. 51986 (Idaho Ct. App. June 18, 2025).
cites § 54-5203 2×subsections: (3)(b) 2×
Where it cites § 54-5203
“The question this Court must address is whether North Haven was acting as a construction manager at the time the lease was executed such that it was subject to the requirements of the ICRA.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
201220182025

One bar per year. Tallest: 3 cases in 2025. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Idaho5Idaho Ct. App.2Bankr. D. Idaho1
By subsection
(3)1 case
Ward v. Bishop Constr., 582 P.3d 28 (Idaho 2025).“I.C. § 54-5203(3). While a broad reading of this definition could support Bishop’s argument below and on appeal that Ward was a contractor, subject to ICRA’s requirements, Bishop put on no proof about that subject at trial.”
(3)(a)1 case
Ward v. Bishop Constr., 582 P.3d 28 (Idaho 2025).
(3)(b)2 cases
Perron v. Martinez, No. 51474 (Idaho Ct. App. Mar. 5, 2025).“Under I.C. § 54-5203(3)(b), a contractor includes a construction manager who performs construction management services.”
North Haven Bus. Park, Inc. v. Balance Regenerative Med., PLLC, No. 51986 (Idaho Ct. App. June 18, 2025).“The question this Court must address is whether North Haven was acting as a construction manager at the time the lease was executed such that it was subject to the requirements of the ICRA.”
(4)(a)3 cases
AED, Inc. v. KDC Investments, LLC, 307 P.3d 176 (Idaho 2013).“Under the ICRA, a contractor includes “[a]ny person who in any capacity undertakes, offers to undertake, purports to have the capacity to undertake, or submits a bid to, or does himself or by or through others, perform construction____” I.C. § 54-5203(4)(a) (emphasis added).…”
Genho v. Riverdale Hot Springs, LLC, 560 P.3d 1041 (Idaho 2024).“§ 54-5203(4)(a) (amended 2022)). Thus, the contract in AED was illegal from execution and could not be validated by later compliance with ICRA.”
(6)1 case
Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: text as last checked Oct. 2026 (this copy records no edition or section history). Syfert holds no earlier or later version of this section.