Skip to main content

Idaho Code § 6-2501 (2026)

Short title. 

Edition and currency
text as last checked Oct. 2026 (this copy records no edition or section history). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTtext as last checked Oct. 2026 (this copy records no edition or section history) ACTIVE · 2 IN 5Y cited 2011–2024 4citing cases
At a glance

Courts have cited this section in 4 opinions since 2011, 2 of them in the last five years.

Short title. 

This chapter shall be known and may be cited as the "Notice and Opportunity to Repair Act."

The 4 cases that cite Idaho Code § 6-2501 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENPerception Constr. Mgmt., Inc. v. Bell, 254 P.3d 1246 (Idaho 2011).
cites § 6-2501 4×cited by 9 cases
Where it cites § 6-2501
“The district court later granted PCM's motion for summary judgment, dismissing the Bells' counterclaims for construction defects and breach of contract because the Bells did not provide timely notice under the Notice and Opportunity to Repair Act (NORA), I.C. §§ 6-2501 to -2504.…”
Later courts cite it for
“a district court's improper exclusion of evidence will be overturned on appeal if it affects a party's substantial right.” · 2 citing courts
2
GREENDavison v. Debest Plumbing, Inc., 416 P.3d 943 (Idaho 2018).
cites § 6-2501 2×cited by 9 cases
Where it cites § 6-2501
“Later, the district court granted summary judgment in favor of DeBest on the negligence claim, finding that the Davisons had failed to comply with the requirements of the Notice and Opportunity to Repair Act (NORA), Idaho Code sections 6-2501 -2504. On appeal, the Davisons argue…”
3
GREENWalker v. Meyer, 511 P.3d 828 (Idaho 2021).
cites § 6-2501 1×cited by 2 cases
Where it cites § 6-2501
“Meyer argues the district court erred in concluding he was not a “construction professional” as defined by Idaho’s Notice and Opportunity to Repair Act (“NORA”), Idaho Code sections 6-2501–04, and asserts the case should have been dismissed because Walker failed to comply with…”
4
GREENMoyer v. Lasher Constr., Inc., 560 P.3d 1114 (Idaho 2024).
cites § 6-2501 2×cited by 5 cases
Where it cites § 6-2501
“On April 8, 2021, Homeowners’ attorney sent Lasher Construction a demand letter citing NORA, Idaho Code section 6-2501 et. seq., which detailed numerous defects with the home, most notably those caused by water leaks, and demanded prompt remediation.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
201120172024

One bar per year. Tallest: 1 case in 2011. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: text as last checked Oct. 2026 (this copy records no edition or section history). Syfert holds no earlier or later version of this section.