Illinois Compiled Statutes homeSearch Illinois
ILCSChapter 770Act 60

770 ILCS 60/24 (2026)

Written notice by subcontractor; service; when notice not necessary; form of notice

Edition and currency
laws through the 2026 session (checked Sept. 2026). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTlaws through the 2026 session (checked Sept. 2026) cited 1995–2024 56citing cases
At a glance

Courts have cited this section in 56 opinions since 1995, 1 of them in the last five years. The most litigated part is subsection (a) (17 cases).

(770 ILCS 60/24) (from Ch. 82, par. 24)
    Sec. 24. Written notice by subcontractor; service; when notice not necessary; form of notice.
    (a) Subcontractors, or parties furnishing labor, materials, fixtures, apparatus, machinery, or services, may at any time after making his or her contract with the contractor, and shall within 90 days after the completion thereof, or, if extra or additional work or material is delivered thereafter, within 90 days after the date of completion of such extra or additional work or final delivery of such extra or additional material, cause a written notice of his or her claim and the amount due or to become due thereunder, to be provided to the owner of record or the owner of record's agent or architect, or the superintendent having charge of the building or improvement and to the lending agency, if known, with the written notice to be sent by: (i) registered or certified mail, with return receipt requested; (ii) a nationally recognized delivery company with tracking service; or (iii) personal service. Notice shall be considered served at the time the written notice is placed with the delivery service or in the mail. The notice shall not be necessary when the sworn statement of the contractor or subcontractor provided for herein shall serve to give the owner notice of the amount due and to whom due, but where such statement is incorrect as to the amount, the subcontractor or material man named shall be protected to the extent of the amount named therein as due or to become due to him or her.
    The form of such notice may be as follows: To (name of owner): You are hereby notified that I have been employed by (the name of contractor) to (state here what was the contract or what was done, or to be done, or what the claim is for) under his or her contract with you, on your property at (here give substantial description of the property) and that there was due to me, or is to become due (as the case may be) therefor, the sum of $.....
    Dated at .... this .... day of ....., .....
(Signature).....
    (b) The serving of notice pursuant to subsection (a) of this Section shall not constitute an admission by the lien claimant that its status is that of subcontractor if it is later determined that the party with whom the lien claimant contracted was the owner or an agent of the owner.
(Source: P.A. 103-827, eff. 1-1-25.)

    
The 20 cases that cite 770 ILCS 60/24 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENCordeck Sales, Inc. v. Constr. Sys., Inc., 887 N.E.2d 474 (Ill. App. Ct. 1st Dist. 2008).
cites § 770 ILCS 60/24 5×cited by 58 cases
Where it cites § 770 ILCS 60/24
“Next, First Midwest contends that the trial court erred in awarding summary judgment in favor of ALL because ALL failed to properly perfect its lien claim.”
The case’s holding
A mechanic's lien is not invalidated by an overstatement of the amount due unless there is evidence of an intent to defraud.
Later courts cite it for
“even under a constructive fraud theory, a lien claim will not be invalidated simply because the claim contains an overstatement. rather, in most cases, 'the intent to defraud is shown by executed documents that on their face overstate the amount due in combination with some other evidence of record from which intent could be inferred.” · 6 citing courts
2
GREENRothers Constr., Inc. v. Centurion Indus., Inc., 786 N.E.2d 644 (Ill. App. Ct. 4th Dist. 2003).
cites § 770 ILCS 60/24 16×cited by 4 cases
Where it cites § 770 ILCS 60/24
“The trial court found plaintiff failed to perfect its mechanics lien pursuant to section 24 of the Mechanics Lien Act (Act) (770 ILCS 60/24 (West 2000)). Plaintiff appeals, contending (1) the trial court erred in dismissing its mechanics lien foreclosure complaint on the grounds…”
Later courts cite it for
“in derogation of common law and must be strictly construed.” · 2 citing courts
3
GREENWeather-Tite, Inc. v. Univ. of St. Francis, 909 N.E.2d 830 (Ill. 2009).
cites § 770 ILCS 60/24 2×cited by 93 cases
Where it cites § 770 ILCS 60/24
“See 770 ILCS 60/24 (West 2004). Section 24 does not, however, require a subcontractor to serve notice of its claim on the owner “when the sworn statement of the contractor or subcontractor provided for herein shall serve to give notice of the amount due and to whom due.”
The case’s holding
An owner must retain sufficient funds to pay a subcontractor listed on a general contractor's sworn statement under the Mechanics Lien Act.
Later courts cite it for
“we review appeals from summary judgment rulings de novo” · 8 citing courts
4
GREENSeasons-4, Inc. v. Hertz Corp., 788 N.E.2d 179 (Ill. App. Ct. 1st Dist. 2003).
cites § 770 ILCS 60/24 6×cited by 9 cases
Where it cites § 770 ILCS 60/24
“Hertz filed a motion to dismiss the amended complaint pursuant to section 2 — 619 of the Illinois Code of Civil Procedure (Code) (735 ILCS 5/2 — 619 (West 1998)) based on plaintiff’s failure to timely serve it with written notice of its mechanic’s lien claim pursuant to section…”
Later courts cite it for
“when construing a statute, we may consider 'the reason and necessity for the statute and the evils it was intended to remedy.” · 4 citing courts
cites § 770 ILCS 60/24 7×subsections: (a) 3×cited by 7 cases
Where it cites § 770 ILCS 60/24
“) On June 19, 2001, Pope executed a Notice of Claim of Subcontractor, 770 ILCS 60/24 which was delivered to AES.”
6
GREENCyclonaire Corp. v. ISG Riverdale, Inc., 882 N.E.2d 684 (Ill. App. Ct. 1st Dist. 2007).
cites § 770 ILCS 60/24 4×subsections: (a) 4×cited by 17 cases
Where it cites § 770 ILCS 60/24
“770 ILCS 60/24(a) (West 2006). The trial court found that plaintiff’s notice of lien was sent outside the 90-day written notice period and found that any services performed and replacement parts provided by plaintiff during the 90-day period preceding the notice of plaintiffs…”
7
GREENCrawford Supply Co. v. Schwartz, 919 N.E.2d 5 (Ill. App. Ct. 1st Dist. 2009).
cites § 770 ILCS 60/24 4×subsections: (a) 4×cited by 11 cases
Where it cites § 770 ILCS 60/24
“The trial court denied the Schwartzes’ motion to dismiss, finding that plaintiffs written notice pursuant to section 24(a) of the Act (770 ILCS 60/24(a) (West 2006)) “constituted substantial compliance with the notice requirements under section[s] 5(b)(ii) and 5(b)(iii).”
8
GREENPetroline Co. v. Advanced Env't Contractors, Inc., 711 N.E.2d 1146 (Ill. App. Ct. 1st Dist. 1999).
cites § 770 ILCS 60/24 4×cited by 21 cases
Where it cites § 770 ILCS 60/24
“It provided 90 days’ notice to the owners under section 24 of the Mechanics Lien Act (770 ILCS 60/24 (West 1996)), but did not provide such notice to the mortgagee (whose interest was recorded).”
The case’s holding
Failure to give a mortgagee the statutory 90-day mechanic's lien notice renders the lien unenforceable against the lender only; the owner who received proper notice remains bound.
Later courts cite it for
“the paramount objective in construing a statute is to give effect to the intent of the legislature.” · 2 citing courts
9
GREENParkway Bank & Trust Co. v. Meseljevic, 940 N.E.2d 215 (Ill. App. Ct. 1st Dist. 2010).
cites § 770 ILCS 60/24 2×subsections: (a) 2×cited by 27 cases
Where it cites § 770 ILCS 60/24
“It asserted the lien was defective because (a) it was a subcontractor’s claim for lien and Beta had not provided Parkway with the 90-day notice required of subcontractors under section 24(a) of the Mechanics Lien Act (770 ILCS 60/24(a) (West 2008)); and (b) the property…”
The case’s holding
A subcontractor fails to enforce a mechanic's lien against a known lender if it does not provide the required statutory notice.
Later courts cite it for
“however, once the contractor or subcontractor has strictly complied with the requirements and the lien has properly attached, then the act should be liberally construed to accomplish its remedial purpose.” · 2 citing courts
10
GREENBricks, Inc. v. C & F Developers, Inc., 836 N.E.2d 743 (Ill. App. Ct. 1st Dist. 2005).
cites § 770 ILCS 60/24 3×cited by 9 cases
Where it cites § 770 ILCS 60/24
“actors, or party furnishing labor or materials, may at any time after making his or her contract with the contractor, and shall within 90 days after the completion thereof, or, if extra additional work or material is delivered thereafter, within 90 days after the date of…”
The case’s holding
A secondary subcontractor's mechanics lien recovery is limited to the amount owed to its immediate contractor at the time the lien notice is served.
Later courts cite it for
“in addition to protecting the rights of those furnishing labor and materials, the act also seeks to protect owners from the potential claims of subcontractors.” · 4 citing courts
cites § 770 ILCS 60/24 4×subsections: (a)cited by 32 cases
Where it cites § 770 ILCS 60/24
“See 770 ILCS 60/24 (West 2008). ¶ 88 Since the parties apply the same legal analysis and arguments to both sections 7 and 24, we examine both provisions together in deciding whether plaintiffs’ lien claims are enforceable on their face.”
The case’s holding
Full payment of a mortgage is a necessary but not sufficient condition that obligates a mortgagee to release the mortgage under the Act.
Later courts cite it for
“while the plain language of section 2 of the act does indicate that full payment is a necessary condition before a mortgagee is obligated to release a mortgage, it does not suggest that full payment, by itself, is a sufficient condition to release a mortgage.” · 4 citing courts
12
GREENStruebing Constr. Co. v. Golub-Lake Shore Place Corp., 666 N.E.2d 846 (Ill. App. Ct. 1st Dist. 1996).
cites § 770 ILCS 60/24 3×cited by 13 cases
Where it cites § 770 ILCS 60/24
“The circuit court arrived at the figure based on the sum of wrongful payments made by the private owner, after it received notice of the second-tier subcontractor’s claim pursuant to section 24 of the Mechanics Lien Act (Act) (770 ILCS 60/24 (West 1992)). The defendants contend…”
Later courts cite it for
“in violation of struebing's rights and interests as a subcontractor and thus were wrongful.” · 2 citing courts
13
GREENNorth Shore Cmty. Bank & Trust Co. v. Sheffield Wellington, LLC, 2014 IL App (1st) 123784, 20 N.E.3d 104.
cites § 770 ILCS 60/24 3×subsections: (a)cited by 6 casesunpublished
Where it cites § 770 ILCS 60/24
“See 770 ILCS 60/24 (West 2008). ¶ 88 Since the parties apply the same legal analysis and arguments to both sections 7 and 24, we examine both provisions together in deciding whether plaintiffs’ lien claims are enforceable on their face.”
14
GREENMerchants Env't Indus., Inc. v. SLT Realty Ltd. P'ship, 731 N.E.2d 394 (Ill. App. Ct. 1st Dist. 2000).
cites § 770 ILCS 60/24 2×cited by 23 cases
Where it cites § 770 ILCS 60/24
“Iron Mike’s also alleged that MEI’s notice of mechanic’s lien, dated November 6, 1997, was filed more than 90 days after the completion date and was thus untimely under section 24 of the Mechanics Lien Act (770 ILCS 60/24 (West 1992)). In support of its allegation that the lien…”
The case’s holding
A mechanic's lien claim is unenforceable against a third-party purchaser if it fails to include a completion date to allow verification of the filing deadline.
Later courts cite it for
“raise a genuine issue of material fact as to whether there was such reliance.” · 4 citing courts
15
GREENGateway Concrete Forming Sys., Inc. v. Dynaprop XVIII: State Street LLC, 826 N.E.2d 1051 (Ill. App. Ct. 1st Dist. 2005).
cites § 770 ILCS 60/24 2×cited by 10 cases
Where it cites § 770 ILCS 60/24
“770 ILCS 60/24 (West 2002). On March 10, 2004, defendants prepared a notice and demand for plaintiff to file suit to enforce its lien pursuant to section 34 of the Act.”
Later courts cite it for
“permit a lien upon premises where a property owner received a benefit from improvements to his property or realized an increase in property value because of a contractor's labor and materials.” · 2 citing courts
16
GREENWeydert Homes, Inc. v. Kammes, 917 N.E.2d 64 (Ill. App. Ct. 2d Dist. 2009).
cites § 770 ILCS 60/24 1×cited by 28 cases
Where it cites § 770 ILCS 60/24
“See 770 ILCS 60/24 (West 2006). Plaintiff reasons that the purpose of section 5 was met because Kammes had notice of any subcontractors’ claims.”
The case’s holding
Quantum meruit serves as an equitable remedy to provide restitution for unjust enrichment and may be pleaded as an alternative claim when a contract is unenforceable.
Later courts cite it for
“quantum meruit is used as an equitable remedy to provide restitution for unjust enrichment .” · 3 citing courts
17
GREENLazar Bros. Trucking v. a & B Excavating, Inc., 365 Ill. App. 3d 559 (Ill. App. Ct. 1st Dist. 2006).
cites § 770 ILCS 60/24 2×cited by 8 cases
Where it cites § 770 ILCS 60/24
“770 ILCS 60/24 (West 2004). Even timely notice may not protect the subcontractor, if the owner made proper payments to the contractor prior to receiving notice of the subcontractor’s claim.”
18
GREENNw. Millwork Co. v. Komperda, 788 N.E.2d 399 (Ill. App. Ct. 2d Dist. 2003).
cites § 770 ILCS 60/24 1×cited by 16 cases
Where it cites § 770 ILCS 60/24
“" 770 ILCS 60/24 (West 2000). Serving the 90-day notice is a condition precedent to a mechanic's lien claim.”
The case’s holding
Reversing a dismissal, the court held that a construction manager's failure to furnish a sworn contractor's statement under the Mechanics Lien Act does not bar its lien or contract claim against owners.
Later courts cite it for
“if the owner pays the contractor before receiving the sworn statement, the owner may be compelled to pay subcontractors even if he or she has paid the contractor in full.” · 1 citing court
19
GREENSeason Comfort Corp. v. Ben A. Borenstein Co., 655 N.E.2d 1065 (Ill. App. Ct. 1st Dist. 1995).
cites § 770 ILCS 60/24 1×cited by 35 cases
Where it cites § 770 ILCS 60/24
“Moreover, if a secondary subcontractor chooses not to rely on the subcontractor or the general contractor to provide written timely notice of its lien to the owner, the Act provides that the secondary subcontractor can provide written notice directly to the owner.”
The case’s holding
A party cannot plead one cause of action in a complaint and receive judgment based on a different cause of action.
Later courts cite it for
“a party cannot plead one cause of action in its complaint and receive judgment on the basis of a different cause of action.” · 5 citing courts
20
GREENCentury Road Builders, Inc. v. City of Palos Heights, 670 N.E.2d 836 (Ill. App. Ct. 1st Dist. 1996).
cites § 770 ILCS 60/24 1×cited by 27 cases
Where it cites § 770 ILCS 60/24
“The court also found that Century’s complaints were legally unsound, as its notices of lien were served after the expiration of the 90-day period provided in section 24 of the Mechanics Lien Act (Act) (770 ILCS 60/24 (West 1992)), and because Century pursued alleged lien rights…”
The case’s holding
A trial court must hold an evidentiary hearing before imposing sanctions based on a pleading filed for an improper purpose.
Later courts cite it for
“an evidentiary hearing should always be held when a sanction award is based upon a pleading filed for an improper purpose, rather than one which is merely unreasonable based on an objective standard.” · 4 citing courts

Show all 56 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
199520092024

One bar per year. Tallest: 6 cases in 2003. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Ill. App. Ct.52Bankr. N.D. Ill.2Ill.1N.D. Ill.1
By subsection
(a)17 cases
Cyclonaire Corp. v. ISG Riverdale, Inc., 882 N.E.2d 684 (Ill. App. Ct. 1st Dist. 2007).“770 ILCS 60/24(a) (West 2006). The trial court found that plaintiff’s notice of lien was sent outside the 90-day written notice period and found that any services performed and replacement parts provided by plaintiff during the 90-day period preceding the notice of plaintiffs…”
Crawford Supply Co. v. Schwartz, 919 N.E.2d 5 (Ill. App. Ct. 1st Dist. 2009).“The trial court denied the Schwartzes’ motion to dismiss, finding that plaintiffs written notice pursuant to section 24(a) of the Act (770 ILCS 60/24(a) (West 2006)) “constituted substantial compliance with the notice requirements under section[s] 5(b)(ii) and 5(b)(iii).”
Parkway Bank & Trust Co. v. Meseljevic, 940 N.E.2d 215 (Ill. App. Ct. 1st Dist. 2010).“It asserted the lien was defective because (a) it was a subcontractor’s claim for lien and Beta had not provided Parkway with the 90-day notice required of subcontractors under section 24(a) of the Mechanics Lien Act (770 ILCS 60/24(a) (West 2008)); and (b) the property…”
Raymond Prof'l Grp., Inc. v. William A. Pope Co. (In re Raymond Prof'l Grp., Inc.), 408 B.R. 711 (Bankr. N.D. Ill. 2009).“) On June 19, 2001, Pope executed a Notice of Claim of Subcontractor, 770 ILCS 60/24 which was delivered to AES.”
North Shore Cmty. Bank & Trust Co. v. Sheffield Wellington, LLC, 2014 IL App (1st) 123784, 20 N.E.3d 104.“See 770 ILCS 60/24 (West 2008). ¶ 88 Since the parties apply the same legal analysis and arguments to both sections 7 and 24, we examine both provisions together in deciding whether plaintiffs’ lien claims are enforceable on their face.”
Showing the top 5 of 17. More in the list view →

Show all 56 citing cases (list view) →

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: laws through the 2026 session (checked Sept. 2026). Syfert holds no earlier or later version of this section.