Mechanics’ liens, including those for additions, repairs, and betterments, shall attach to the building or improvement for which the material or labor was furnished or done, in preference to any prior lien, encumbrance, or mortgage upon the land upon which such building or improvement was erected or situated except as provided in sections 572.10 and 572.11. [R60, §1853, 1855; C73, §2139, 2141; C97, §3095; C24, 27, 31, 35, 39, §10289; C46, 50, 54, 58, 62, 66, 71, 73, 75, 77, 79, 81, §572.20] 2007 Acts, ch 83, §13 \n 572.21 Foreclosure of mechanic’s lien when lien on land. In the foreclosure of a mechanic’s lien when there is a superior lien, encumbrance, or mortgage upon the land the following regulations shall govern:

1. Lien on original and independent building or improvement. If such material was furnished or labor performed in the construction of an original and independent\n\nTue Dec 09 22:00:42 2025 Iowa Code 2026, Chapter 572 (38, 0) 9 MECHANIC’S LIEN, §572.23\n\nbuilding or improvement commenced after the attaching or execution of such superior lien, encumbrance, or mortgage, the court may, in its discretion, order such building or improvement to be sold separately under execution, and the purchaser may remove the same in such reasonable time as the court may fix. If the court shall find that such building or improvement should not be sold separately, it shall take an account of and ascertain the separate values of the land, and the building or improvement, and order the whole sold, and distribute the proceeds of such sale so as to secure to the superior lien, encumbrance, or mortgage priority upon the land, and to the mechanic’s lien priority upon the building or improvement.

2. Lien on existing building or improvement for repairs or additions. If the material furnished or labor performed was for additions, repairs, or betterments upon any building or improvement, the court shall take an accounting of the values before such material was furnished or labor performed, and the enhanced value caused by such additions, repairs, or betterments; and upon the sale of the premises, distribute the proceeds of such sale so as to secure to the superior mortgagee or lienholder priority upon the land and improvements as they existed prior to the attaching of the mechanic’s lien, and to the mechanic’s lienholder priority upon the enhanced value caused by such additions, repairs, or betterments. In case the premises do not sell for more than sufficient to pay off the superior mortgage or other superior lien, the proceeds shall be applied on the superior mortgage or other superior liens. [R60, §1853, 1855; C73, §2139, 2141; C97, §3095; C24, 27, 31, 35, 39, §10290; C46, 50, 54, 58, 62, 66, 71, 73, 75, 77, 79, 81, §572.21] 2007 Acts, ch 83, §14 \n

Notes of Decisions
Cited in 1 case, 1965–1965 · leading case: Gen. Mortg. Corp. of Iowa v. Campbell, 138 N.W.2d 416 (Iowa 1965).
Gen. Mortg. Corp. of Iowa v. Campbell, 138 N.W.2d 416 (Iowa 1965). “It is appellees’ contention the placement of the provisions relating to new construction in a separate sub-paragraph from the provisions dealing with additions and repairs has the effect of making the troublesome last sentence apply only to additions and repairs because it…”