Mich. Comp. Laws § 570.1116 (2026)

Claim of lien; vacation and discharge; bond; penal sum; filing; notification of lien claimant; objection to sufficiency of surety; appearance by surety; approval of bond; certificate; recordation; discharge of claim of lien and notice of lis pendens; action by obligee; court order or other relief.

Edition and currency
laws through the 2026 session (checked Aug. 2026). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTlaws through the 2026 session (checked Aug. 2026) ACTIVE · 3 IN 5Y cited 2003–2024 5citing cases
At a glance

Courts have cited this section in 5 opinions since 2003, 3 of them in the last five years. The most litigated part is subsection (1) (3 cases).

CONSTRUCTION LIEN ACT


Act 497 of 1980


570.1116 Claim of lien; vacation and discharge; bond; penal sum; filing; notification of lien claimant; objection to sufficiency of surety; appearance by surety; approval of bond; certificate; recordation; discharge of claim of lien and notice of lis pendens; action by obligee; court order or other relief.

Sec. 116.

    (1)  The claim of lien of a contractor, subcontractor, supplier, or laborer may at any time be vacated and discharged if a bond, with the lien claimant as obligee, is filed with the county clerk for the county in which the property covered by the lien is located and a copy is given to the obligee lien claimant. The bond shall be in the penal sum of twice the amount for which the lien is claimed and shall be conditioned on the payment of any sum for which the obligee in the bond may obtain judgment on the claim for which the claim of lien was filed. The bond may be either a cash bond executed by a principal, or a surety bond executed by a principal and a surety company authorized to do business in this state.

    (2) Within 10 days after receiving the bond, the county clerk shall notify each lien claimant that a bond has been filed and indicate the amount of the bond and the name of the surety on the bond. The lien claimants shall have 10 days after being notified of the bond within which to file an objection to the sufficiency of the surety on the bond, in which case the county clerk shall not approve the bond until the surety has appeared before the county clerk and answered under oath those questions asked by or on behalf of the lien claimant touching on the surety's financial responsibility. If an objection to the surety is not filed within the 10 days after being notified of the bond or if the county clerk approves the bond after the questioning of the surety, the county clerk shall at once give to the principal and the obligee named in the bond a certificate that a good and sufficient bond has been filed in accordance with this act. The certificate shall state the names of the obligor and obligee, the amount of the bond, and the description of the property covered by the claim of lien being discharged. Upon the recording of the certificate in the office of the register of deeds where the claim of lien was recorded, the claim of lien of the obligee lien claimant named in the claim of lien shall be discharged. If because of the pendency of proceedings to enforce the claim of lien, a notice of lis pendens has been recorded, the recording of the certificate shall also operate as a discharge of the notice of lis pendens. The obligee may make any obligor on the bond a party to an action to enforce a claim under the bond, and a judgment may be recovered in the action against all or any of the obligors.

    (3) In an action brought in connection with the claim of the obligee, the court may do 1 or more of the following:

    (a) Order the amount of the bond to be reduced.

    (b) Order other or additional surety to be provided.

    (c) Grant any other relief the court considers to be equitable.

History: 1980, Act 497, Eff. Jan. 1, 1982

The 5 cases that cite Mich. Comp. Laws § 570.1116 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENE R Zeiler Excavating, Inc v. Valenti Trobec Chandler Inc, 717 N.W.2d 370 (Mich. Ct. App. 2006).
cites § 570.1116 17×subsections: (1) 2× (3) 2× (3)(c)cited by 15 cases
Where it cites § 570.1116
“1117(1), governs an action to enforce a surety bond pursuant to MCL 570.1116. Because the one-year period of limitations under MCL 570.”
2
NO FLAGKeith Gipfert v. Hartford Fire Ins. Co., No. 365748 (Mich. Ct. App. Nov. 12, 2024).
cites § 570.1116 12×subsections: (1) 7× (2) 4×cited by 0 casesunpublished
Where it cites § 570.1116
“Gypsum’s first amended complaint states that its claim against CBC and Hartford was a claim on the bond, which CBC and Hartford filed pursuant to MCL 570.1116. MCL 570.1116(1) provides: “The obligee may make any obligor on the bond a party to an action to enforce a claim under…”
3
NO FLAGStand. Elec. Co. v. Markee Elec. Inc, No. 359028 (Mich. Ct. App. Dec. 22, 2022).
cites § 570.1116 8×subsections: (1) 5× (2) 3×cited by 0 casesunpublished
Where it cites § 570.1116
“In general, “[p]roceedings for the enforcement of a construction lien and the foreclosure of any interests subject to the construction lien shall not be brought later than 1 year after the date the claim of lien was recorded.” MCL 570.”
4
NEUTRALSteelcon, Inc. v. Bennett & Wright Grp., Inc., 257 F. Supp. 2d 895 (E.D. Mich. 2003).
cites § 570.1116 2×cited by 1 case
Where it cites § 570.1116
“J; Mich. Comp. Laws Ann. § 570.1116 . On December 20, 2000, Steelcon filed suit in Wayne County Circuit Court against Blue Circle and B & W for breach *897 of contract and seeking to foreclose their construction lien.”
5
NO FLAGComau LLC v. Bayview Elec. Co., No. 2:20-cv-12865, 2021 WL 1037728 (E.D. Mich. Mar. 17, 2021).
cites § 570.1116 1×cited by 0 casesunknown
Where it cites § 570.1116
“§ 570.1116. Bayview replaced its lien claim its state court complaint with a claim against the bond, which is a contractual rather than equitable claim.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
200320132024

One bar per year. Tallest: 1 case in 2003. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Mich. Ct. App.3E.D. Mich.2
By subsection
(1)3 cases
E R Zeiler Excavating, Inc v. Valenti Trobec Chandler Inc, 717 N.W.2d 370 (Mich. Ct. App. 2006).“1117(1), governs an action to enforce a surety bond pursuant to MCL 570.1116. Because the one-year period of limitations under MCL 570.”
Keith Gipfert v. Hartford Fire Ins. Co., No. 365748 (Mich. Ct. App. Nov. 12, 2024).“Gypsum’s first amended complaint states that its claim against CBC and Hartford was a claim on the bond, which CBC and Hartford filed pursuant to MCL 570.1116. MCL 570.1116(1) provides: “The obligee may make any obligor on the bond a party to an action to enforce a claim under…”
Stand. Elec. Co. v. Markee Elec. Inc, No. 359028 (Mich. Ct. App. Dec. 22, 2022).“In general, “[p]roceedings for the enforcement of a construction lien and the foreclosure of any interests subject to the construction lien shall not be brought later than 1 year after the date the claim of lien was recorded.” MCL 570.”
(2)2 cases
Keith Gipfert v. Hartford Fire Ins. Co., No. 365748 (Mich. Ct. App. Nov. 12, 2024).
Stand. Elec. Co. v. Markee Elec. Inc, No. 359028 (Mich. Ct. App. Dec. 22, 2022).
(3)1 case
E R Zeiler Excavating, Inc v. Valenti Trobec Chandler Inc, 717 N.W.2d 370 (Mich. Ct. App. 2006).
(3)(c)1 case
E R Zeiler Excavating, Inc v. Valenti Trobec Chandler Inc, 717 N.W.2d 370 (Mich. Ct. App. 2006).
Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: laws through the 2026 session (checked Aug. 2026). Syfert holds no earlier or later version of this section.

Michigan Compiled Laws Home  |  Search Michigan  |  Search cases for this section  |  syfert.com