Minn. Stat. § 574.31 (2026)
Limit Of Time To Bring Action
Edition and currency
Other sources
Courts have cited this section in 20 opinions since 1944.
Subdivision 1.Claims on performance bonds.
In the event of a claim by the public body on a performance bond, no action shall be maintained later than permitted under the statute of limitations applicable to the claim. Nothing in this subdivision may be construed to otherwise affect the common law or equitable rights of performance bond sureties, principals, or public bodies that are obligees.
Subd. 2.Claims on payment bonds.
(a) In the event of a claim on a payment bond by a person furnishing labor and materials, no action shall be maintained on the payment bond unless, within 120 days after completion, delivery, or provision by the person of its last item of labor and materials, for the public work, the person serves written notice of claim under the payment bond personally or by certified mail upon the surety that issued the bond and the contractor on whose behalf the bond was issued at their addresses as stated in the bond specifying the nature and amount of the claim and the date the claimant furnished its last item of labor and materials for the public work. The addresses of the contractor and the surety listed on the bond must be addresses at which the companies are authorized to accept service of the notice of the claim. If an agent or attorney-in-fact is authorized to accept service of notice of the claim for the contractor or surety, that fact must be expressly stated in the bond along with the address of the agent or attorney-in-fact at which service of the notice of the claim can be made. For the purpose of this section, notice is sufficient if served personally or via certified mail to the addresses of the contractor and surety listed on the bond. The form of notice is sufficient if it is substantially as follows:
NOTICE OF CLAIM ON PAYMENT BOND FOR PUBLIC WORK
| TO: . | |||
| (Surety that issued payment bond) | |||
| and . | |||
| (The contractor on whose behalf the bond was issued) | |||
| NOTICE IS HEREBY GIVEN that the undersigned claimant | |||
| has a claim against the above-named surety for labor and materials | |||
| furnished by the undersigned for the public work described | |||
| as follows: . | |||
| . | |||
| (Description of the public work) | |||
| The labor and materials were furnished under a contract | |||
| or agreement with | |||
| . | |||
| (Name and address of contractor or supplier requesting labor and materials from the claimant) | |||
| The nature of the labor and materials furnished is as follows: | |||
| . | |||
| The amount of the claim is: . | |||
| The date the claimant last furnished labor and materials to this public work is the ...... day of ......................., ............ | |||
| Claimant seeks payment of the claim according to the law. | |||
| . | ||||
| Claimant | ||||
| . | ||||
| Address | ||||
| . | ||||
| STATE OF . | ||||
| ss. | ||||
| COUNTY OF . | ||||
| ......................... being duly sworn on oath says that ....... | ||||
| is ......................... of the claimant named above and has | ||||
| knowledge of the claim and that the claim is correct, and no | ||||
| part of the claim has been paid. | ||||
| . | ||||
| Signed and sworn to before me | ||||
| on . | , | |||
| by . | (Notary Seal) | |||
| . | ||||
| Notary Public | ||||
(b) If the contractor providing the payment bond fails to comply with the filing requirements of section 574.28 by failing to state both its address and the address of the surety providing the bond, then a claimant under the bond need not provide either the surety or the contractor written notice of its claim under paragraph (a).
(c) An action to enforce a claim against the surety under the bond must be commenced within one year from the date of completion, delivery, or provision by the claimant of its last item of labor and materials for the public work stated in its notice of claim. If no notice of claim was required because the contractor providing the bond failed to comply with the requirements of section 574.28, then any action under the bond must be commenced within one year from the actual date of completion, delivery, or provision by the claimant of its last item of labor and materials for the public work. Any other person having a cause of action on a payment bond may be admitted, on motion, as a party to the action, and the court shall determine the rights of all parties. If the amount realized on the bond is insufficient to discharge all the claims in full, the amount must be prorated among the parties.
(d) The claimant can extend the time within which to bring an action to enforce a claim under the bond to beyond that specified in paragraph (c) either by: (1) written stipulation between the claimant and surety stating the extended deadline and executed by both parties before the expiration of one year from the actual date of completion, delivery, or provision by the claimant of its last item of labor and materials for the public work; or (2) written notice extending by one year the deadline specified in paragraph (c) sent by the claimant to the surety via certified mail 90 days before the expiration of the deadline specified in paragraph (c), which notice is not objected to in a return written notice sent by the surety to the claimant via certified mail within 30 days after the surety's receipt of claimant's notice. If a claimant's payment is not yet contractually due within one year from the actual date of completion, delivery, or provision by the claimant of its last item of labor and materials, the court shall continue and not dismiss the action until the payment is due.
- Where it cites § 574.31
- “The principal dispute in this case is whether a subcontractor gave proper notice of a payment-bond claim under Minn. Stat. § 574.31 , subd. 2(a) (2012).”
- Later courts cite it for
- “on the actions of the party against whom waiver was sought or its agents.” · 2 citing courts
- Where it cites § 574.31
- “Integrity argues that this date should control for the purposes of § 574.31 — a position which the trial court correctly rejected.”
- The case’s holding
- A public body may not retroactively backdate the date of contract acceptance to shorten the statutory notice period for claimants against a performance bond.
- Where it cites § 574.31
- “The sole issue on appeal is whether Spetz & Berg was required to comply strictly with the notice of claim requirements of Minn. Stat. § 574.31 (1929) as a condition precedent to the maintenance of its action against Balboa.”
- Where it cites § 574.31
- “Here, Mon-Ray and Erickson did not protect their rights because, for reasons not apparent from the record, they did not timely submit all of their payment-bond claims under Minn.Stat. § 574.31, subd. 2(a) (2002). See ServiceMaster, 544 N.”
- Later courts cite it for
- “to establish a claim for unjust enrichment, the claimant must show that another party knowingly received something of value to which he was not entitled and that the circumstances are such that it would be unjust for that person to retain the benefit.” · 4 citing courts
- Where it cites § 574.31
- “Is Green Electric estopped from maintaining an action for failing to take steps to protect itself under Minn.Stat. § 574.31? 4. Is Green Electric required to show AMM was insolvent at the time of the default before recovering against the MAC? ANALYSIS On appeal from summary…”
- Where it cites § 574.31
- “Safety Signs sent the notice to Niles-Wiese’s primary business address rather than the address listed on the payment bond, as required by Minn.Stat. § 574.31, subd. 2(a). Despite this failure to comply with the statute, both Niles-Wiese and Westfield acknowledged receipt of the…”
- Summary
- No passage or summary on file for this case yet.
- Where it cites § 574.31
- “Paul Fire & Marine on a payment bond for debts arising from the default of CNICO’s assured, (2) CNICO’s payment bond is subject to the limitation period in Minn.Stat. § 574.31 rather than the limitation contained in the bond, (3) St.”
- Where it cites § 574.31
- “Section 574.31 provides in part: “No action shall be maintained on any such bond unless within 90 days after the completion of the contract and acceptance thereof by the proper public authorities, the claimant shall file a written notice specifying the nature and amount of his…”
- Later courts cite it for
- “the general rule is that if a condition precedent prevents the accrual of a right, performance of the condition precedent may not be waived by a defendant to an action.” · 2 citing courts
- Where it cites § 574.31
- “United Fire denied both claims, stating that Kraemer failed to comply with Minn. Stat. § 574.31 , subd. 2(a) (1998), which requires bond claim notices to be served within 120 days after the last delivery of materials.”
- Where it cites § 574.31
- “Paul Fire & Marine moved to dismiss Spartan’s claim on the ground that Spartan had failed to comply with the notice requirements of Minn. Stat. § 574.31 (1984). The trial court ordered judgment dismissing Spartan’s action for failure to provide timely notice of its claim, and…”
- Where it cites § 574.31
- “I Minn.Stat. § 574.31 (1982) provides: No action shall be maintained on any such bond unless within 90 days after the completion of the contract and acceptance thereof by the proper public authorities, the claimant shall file a written notice * * * in the office of the auditor…”
- Where it cites § 574.31
- “And absent the requisite notice of claim by the subcontractor itself under § 574.31, the city would have no obligation to the subcontractor for which the surety is required to respond.”
- Where it cites § 574.31
- “1941, § 574.31 (Mason St. 1940 Supp. § 9705). The precise question here is whether this notice was filed within the time limited by that statute.”
- Where it cites § 574.31
- “We are of the opinion that the trial court was correct in determining that plaintiffs’ notices of claims under the various contracts were filed within the limitations provided in § 574.31, and in granting summary judgment on that basis.”
- Where it cites § 574.31
- “The trial court, interpreting the meaning of “acceptance” in Minn.Stat. § 574.31 (1982), found that respondent Maxson was entitled to summary judgment.”
- Where it cites § 574.31
- “Section 574.31 provides in part: “No action shall be maintained on any such bond unless within 90 days after the completion of the contract and acceptance thereof by the proper public authorities, the claimant shall file *16 a written notice specifying the nature and amount of…”
- Where it cites § 574.31
- “Minn. Stat. § 574.31 , subd. 2 (2012). Fieseler Masonry’s ability to make a claim under the payment bond was an adequate remedy that Fieseler Masonry opted not to pursue.”
- Where it cites § 574.31
- “Thorson commenced its action within the limitation period provided in the bond, but not within the statutory limitation period provided in Minn.Stat. § 574.31 (1998). The District Court 2 denied FCIC’s motion for summary judgment, concluding that Minn.”
- Where it cites § 574.31
- “Section 574.31 provides in part: "No action shall be maintained on any such bond unless within 90 days after the completion of the contract and acceptance thereof by the proper public authorities, the claimant shall file a written notice specifying the nature and amount of his…”
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
One bar per 2 years. Tallest: 4 cases in 1984–1985. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.
Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.
Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.
Edition shown: text as last checked Sept. 2026 (this copy records no edition or section history). Syfert holds no earlier or later version of this section.