Rate schedules for interim energy charges or periodic rate adjustment

Edition and currency
laws through the 2026 session (checked Sept. 2026). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTlaws through the 2026 session (checked Sept. 2026) cited 2010–2021 13citing cases

  386.266.  Rate schedules for interim energy charges or periodic rate adjustment — application for approval, procedure — adjustment mechanisms — rulemaking authority — task force to be appointed — surveillance monitoring, requirements. — 1.  Subject to the requirements of this section, any electrical corporation may make an application to the commission to approve rate schedules authorizing an interim energy charge, or periodic rate adjustments outside of general rate proceedings to reflect increases and decreases in its prudently incurred fuel and purchased-power costs, including transportation.  The commission may, in accordance with existing law, include in such rate schedules features designed to provide the electrical corporation with incentives to improve the efficiency and cost-effectiveness of its fuel and purchased-power procurement activities.

  2.  Subject to the requirements of this section, any electrical, gas, or water corporation may make an application to the commission to approve rate schedules authorizing periodic rate adjustments outside of general rate proceedings to reflect increases and decreases in its prudently incurred costs, whether capital or expense, to comply with any federal, state, or local environmental law, regulation, or rule.  Any rate adjustment made under such rate schedules shall not exceed an annual amount equal to two and one-half percent of the electrical, gas, or water corporation's Missouri gross jurisdictional revenues, excluding gross receipts tax, sales tax and other similar pass-through taxes not included in tariffed rates, for regulated services as established in the utility's most recent general rate case or complaint proceeding.  In addition to the rate adjustment, the electrical, gas, or water corporation shall be permitted to collect any applicable gross receipts tax, sales tax, or other similar pass-through taxes, and such taxes shall not be counted against the two and one-half percent rate adjustment cap.  Any costs not recovered as a result of the annual two and one-half percent limitation on rate adjustments may be deferred, at a carrying cost each month equal to the utilities net of tax cost of capital, for recovery in a subsequent year or in the corporation's next general rate case or complaint proceeding.

  *3.  Subject to the requirements of this section, any gas or electrical corporation may make an application to the commission to approve rate schedules authorizing periodic rate adjustments outside of general rate proceedings to adjust rates of customers in eligible customer classes to account for the impact on utility revenues of increases or decreases in residential and commercial customer usage due to variations in either weather, conservation, or both.  For purposes of this section:  for electrical corporations, "eligible customer classes" means the residential class and classes that are not demand metered; and for gas corporations, "eligible customer classes" means the residential class and the smallest general service class.  As used in this subsection, "revenues" means the revenues recovered through base rates, and does not include revenues collected through a rate adjustment mechanism authorized by this section or any other provisions of law.  This subsection shall apply to electrical corporations beginning January 1, 2019, and shall expire for electrical corporations on January 1, 2029.  An electrical corporation may make a one-time application to the commission under this subsection if such corporation has provided notice to the commission under subsection 5 of section 393.1400, provided the corporation shall not concurrently utilize electric rate adjustments under this subsection and the deferrals set forth in subsection 5 of section 393.1400.

  4.  Subject to the requirements of this section, a water corporation with more than eight thousand Missouri retail customers may make an application to the commission to approve rate schedules authorizing periodic rate adjustments outside of general rate proceedings to ensure revenues billed by such water corporation for regulated services equal the revenue requirement for regulated services as established in the water corporation's most recent general rate proceeding or complaint proceeding, excluding any other commission-approved surcharges and gross receipts tax, sales tax, and other similar pass-through taxes not included in tariffed rates, due to any revenue variation resulting from increases or decreases in residential, commercial, public authority, and sale for resale usage.

  5.  The commission shall have the power to approve, modify, or reject adjustment mechanisms submitted under subsections 1 to 4 of this section only after providing the opportunity for a full hearing in a general rate proceeding, including a general rate proceeding initiated by complaint.  The commission may approve such rate schedules after considering all relevant factors which may affect the costs or overall rates and charges of the corporation, provided that it finds that the adjustment mechanism set forth in the schedules:

  (1)  Is reasonably designed to provide the utility with a sufficient opportunity to earn a fair return on equity;

  (2)  Includes provisions for an annual true-up which shall accurately and appropriately remedy any over- or under-collections, including interest at the utility's short-term borrowing rate, through subsequent rate adjustments or refunds;

  (3)  In the case of an adjustment mechanism submitted under subsections 1 and 2 of this section, includes provisions requiring that the utility file a general rate case with the effective date of new rates to be no later than four years after the effective date of the commission order implementing the adjustment mechanism.  However, with respect to each mechanism, the four-year period shall not include any periods in which the utility is prohibited from collecting any charges under the adjustment mechanism, or any period for which charges collected under the adjustment mechanism must be fully refunded.  In the event a court determines that the adjustment mechanism is unlawful and all moneys collected thereunder are fully refunded, the utility shall be relieved of any obligation under that adjustment mechanism to file a rate case;

  (4)  In the case of an adjustment mechanism submitted under subsection 1 or 2 of this section, includes provisions for prudence reviews of the costs subject to the adjustment mechanism no less frequently than at eighteen-month intervals, and shall require refund of any imprudently incurred costs plus interest at the utility's short-term borrowing rate.

  6.  Once such an adjustment mechanism is approved by the commission under this section, it shall remain in effect until such time as the commission authorizes the modification, extension, or discontinuance of the mechanism in a general rate case or complaint proceeding.

  7.  Any amounts charged under any adjustment mechanism approved by the commission under this section shall be separately disclosed on each customer bill.

  8.  The commission may take into account any change in business risk to the corporation resulting from implementation of the adjustment mechanism in setting the corporation's allowed return in any rate proceeding, in addition to any other changes in business risk experienced by the corporation.

  9.  In the event the commission lawfully approves an incentive- or performance-based plan, such plan shall be binding on the commission for the entire term of the plan.  This subsection shall not be construed to authorize or prohibit any incentive- or performance-based plan.

  10.  Prior to August 28, 2005, for subsections 1 to 3 of this section, and upon August 28, 2018, for subsection 4 of this section, the commission shall have the authority to promulgate rules under the provisions of chapter 536 as it deems necessary, to govern the structure, content and operation of such rate adjustments, and the procedure for the submission, frequency, examination, hearing and approval of such rate adjustments.  Any electrical, gas, or water corporation may apply for any adjustment mechanism under this section whether or not the commission has promulgated any such rules.

  11.  Nothing contained in this section shall be construed as affecting any existing adjustment mechanism, rate schedule, tariff, incentive plan, or other ratemaking mechanism currently approved and in effect.

  12.  Each of the provisions of this section is severable. In the event any provision or subsection of this section is deemed unlawful, all remaining provisions shall remain in effect.

  13.  The provisions of subsections 1 to 3 of this section shall take effect on January 1, 2006, and the commission shall have previously promulgated rules to implement the application process for any rate adjustment mechanism under subsections 1 to 3 of this section prior to the commission issuing an order for any such rate adjustment.

  14.  The public service commission shall appoint a task force, consisting of all interested parties, to study and make recommendations on the cost recovery and implementation of conservation and weatherization programs for electrical and gas corporations.

  **15.  (1)  Each public utility operating under a mechanism proposed and approved under subsection 3 of this section shall quarterly file a surveillance monitoring, consisting of five parts.  Each part, except the rate-base quantifications report, shall contain information for the last twelve-month period and the last quarter data for total company electric operations and Missouri jurisdictional operations.  Rate-base quantifications shall contain only information for the ending date of the period being reported.

  (2)  Part one of the surveillance monitoring report shall be the rate-base quantifications report.  The quantification of rate-base items in part one shall be consistent with the methods or procedures used in the most recent rate proceeding unless otherwise specified.  The report shall consist of specific rate-base quantifications of:

  (a)  Plant in service;

  (b)  Reserve for depreciation;

  (c)  Materials and supplies;

  (d)  Cash working capital;

  (e)  Fuel inventory, if applicable;

  (f)  Prepayments;

  (g)  Other regulatory assets;

  (h)  Customer advances;

  (i)  Customer deposits;

  (j)  Accumulated deferred income taxes;

  (k)  Any other item included in the electrical corporation's rate base in its most recent rate proceeding;

  (l)  Net operating income from part three; and

  (m)  Calculation of the overall return on rate base.

  (3)  Part two of the surveillance monitoring report shall be the capitalization quantifications report, which shall consist of specific capitalization quantifications of:

  (a)  Common stock equity (net);

  (b)  Preferred stock, par or stated value outstanding;

  (c)  Long-term debt, including current maturities;

  (d)  Short-term debt; and

  (e)  Weighted cost of capital, including component costs.

  (4)  Part three of the surveillance monitoring report shall be the income statement, which shall consist of an income statement containing specific quantification of:

  (a)  Operating revenues to include sales to industrial, commercial, and residential customers, sales for resale, and other components of total operating revenues;

  (b)  Operating and maintenance expenses for fuel expense, production expenses, purchased power energy and capacity, if applicable;

  (c)  Transmission expenses;

  (d)  Distribution expenses;

  (e)  Customer accounts expenses;

  (f)  Customer service and information expenses;

  (g)  Sales expenses;

  (h)  Administrative and general expenses;

  (i)  Depreciation, amortization, and decommissioning expense;

  (j)  Taxes other than income taxes;

  (k)  Income taxes; and

  (l)  Quantification of heating degree and cooling degree days, actual and normal.

  (5)  Part four of the surveillance monitoring report shall be the jurisdictional allocation factor report, which shall consist of a listing of jurisdictional allocation factors for the rate base, capitalization quantification reports, and income statement.

  (6)  Part five of the surveillance monitoring report shall be the financial data notes, which shall consist of notes to financial data including, but not limited to:

  (a)  Out of period adjustments;

  (b)  Specific quantification of material variances between actual and budget financial performance;

  (c)  Material variances between current twelve-month period and prior twelve-month period revenue;

  (d)  Expense level of items ordered by the commission to be tracked under the order establishing the rate adjustment mechanism;

  (e)  Budgeted capital projects; and

  (f)  Events that materially affect debt or equity surveillance components.

  (7)  This subsection shall expire on January 1, 2029.

­­--------

(L. 2005 S.B. 179, A.L. 2018 S.B. 564 merged with S.B. 705, A.L. 2022 S.B. 745)

*Subsection 3 expires 1-01-29 for electrical corporations.

**Subsection 15 expires 1-01-29.

CROSS REFERENCE:

Nonseverability clause, 393.1675

The 13 cases that cite Mo. Rev. Stat. § 386.266 most heavily, weighted by court and treatment. RelevanceNewestTreatment
cites § 386.266 54×cited by 11 cases
Where it cites § 386.266
“During the 2005 legislative session, the Missouri legislature passed Senate Bill 179, later codified at section 386.266. Section 386.266 authorizes the PSC to establish an environmental cost recovery mechanism (“ECRM”) 4 to reflect increases and decreases in a utility’s…”
The case’s holding
A public service commission possesses only those powers expressly conferred by statute or those clearly implied as necessary to carry out its specifically granted authority.
Later courts cite it for
“because the commission is purely a creature of statute, its powers are limited to those conferred by statute either expressly, or by clear implication as necessary to carry out the powers specifically granted.” · 3 citing courts
2
GREENState ex rel. Union Elec. Co. v. Pub. Serv. Comm'n, 399 S.W.3d 467 (Mo. Ct. App. 2013).
cites § 386.266 18×cited by 16 cases
Where it cites § 386.266
“The tariff sheets proposed the implementation of a fuel adjustment clause, as authorized by section 386.266. 1 A fuel adjustment clause permits electric utilities to adjust base rates periodically outside a general rate proceeding “to reflect increases and decreases in an…”
Later courts cite it for
“however, this rule of statutory construction is tempered by the overriding rule that construction of a statute should avoid unreasonable or absurd results.” · 2 citing courts
3
GREENState ex rel. Praxair, Inc. v. Pub. Serv. Comm'n, 328 S.W.3d 329 (Mo. Ct. App. 2010).
cites § 386.266 6×cited by 18 cases
Where it cites § 386.266
“) Section 386.266 did not become law until January 1, 2006, which is well after the IEC was entered into by the parties and approved by the Commission in 2005.”
Later courts cite it for
“intervening events make a decision unnecessary!, and it is impossible for this court to grant effectual relief'; that is, when "the question presented for decision seeks a judgment upon some matter which, if the judgment was rendered, would not have any practical effect upon any then existing controversy.” · 1 citing court
4
GREENState ex rel. AG Processing, Inc. v. Pub. Serv. Comm'n, 311 S.W.3d 361 (Mo. Ct. App. 2010).
cites § 386.266 6×cited by 9 cases
Where it cites § 386.266
“140(11), RSMo 2000, the Commission concludes that the Revised Tariff Sheets are consistent with the Report and Order, as clarified by the First Tariff Order and Second Tariff Order, Section 386.266 RSMo, and Commission Rule 4 CSR 240-20.”
cites § 386.266 8×cited by 5 cases
Where it cites § 386.266
“So, while it is possible that other factors could cause AmerenUE to earn a greater than approved ROE and/or fuel purchases might be made that ultimately prove imprudent, such events would then be subject to scrutiny by the Commission in AmerenUE’s next rate case.”
cites § 386.266 4×cited by 13 cases
Where it cites § 386.266
“In addition, KCPL asked the PSC to adopt a fuel adjustment clause under section 386.266 and to use an accounting deferral mechanism for certain items of expenditure.”
cites § 386.266 2×cited by 15 cases
Where it cites § 386.266
“2011) (approving electric utility’s use of fuel adjustment clause, which permitted automatic adjustment for actual fuel costs without a full rate hearing, pursuant to legislature's 2005 enactment of section 386.266). . 4 CSR 240-40.015 is the general affiliate transaction rule,…”
Later courts cite it for
“the psc's order has a presumption of validity, and the burden of proof is on the appellant to prove that the order is unlawful or unreasonable.” · 2 citing courts
8
GREENState ex rel. AG Processing v. Pub. Serv. Comm'n, 340 S.W.3d 146 (Mo. Ct. App. 2011).
cites § 386.266 3×cited by 4 cases
Where it cites § 386.266
“As part of its May 17, 2007 Report and Order resolving that rate case, the Commission authorized KCP & L to implement a Fuel Adjustment Clause pursuant to § 386.266, 2 and the Commission’s implementing regulation, 4 C.”
9
GREENPraxair, Inc. v. Pub. Serv. Comm'n, 346 S.W.3d 377 (Mo. Ct. App. 2011).
cites § 386.266 4×cited by 1 case
Where it cites § 386.266
“The Commission, in response, first points out that section 386.266 did not become effective until January 1, 2006.”
10
GREENOff. of Pub. Couns. v. Pub. Serv. Comm'n, 422 S.W.3d 358 (Mo. Ct. App. 2013).
cites § 386.266 2×cited by 2 cases
Where it cites § 386.266
“Consumers also argue that the legislature could not have intended that the MISO transmission charges at issue be recoverable through the FAC because these types of charges did not exist when section 386.266 was passed in 2005. By its language, the statute does not impose such a…”
cites § 386.266 1×cited by 0 cases
Where it cites § 386.266
“banc 1979) (“UCCM”) (citations omitted), superseded on other grounds by § 386.266. In other words, the PSC must determine a rate that is just and reasonable using a utility’s past expenses only as a way to estimate the utility’s future costs (and fair return); not to allow a…”
Later courts cite it for
“point is multifarious in that it asserts the psc's decision regarding relocation expenses was error for two separate and distinct reasons.” · 2 citing courts
cites § 386.266 1×cited by 0 cases
Where it cites § 386.266
“3d at 685 (construing § 386.266). The court observed that that cost recovery mechanism "reduce[d] the expense of the regulatory process by decreasing both the magnitude and frequency of rate cases.”
13
NO FLAGPub. Serv. Comm'n v. Off. of Pub. Couns., 417 S.W.3d 815 (Mo. Ct. App. 2014).
cites § 386.266 1×cited by 0 cases
Where it cites § 386.266
“3d at 685 (construing § 386.266). The court observed that that cost recovery mechanism "reduce[d] the expense of the regulatory *822 process by decreasing both the magnitude and frequency of rate cases.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
201020152021

One bar per year. Tallest: 4 cases in 2011. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Mo. Ct. App.11Mo.2
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: laws through the 2026 session (checked Sept. 2026). Syfert holds no earlier or later version of this section.

Missouri Revised Statutes Home  |  Search Missouri  |  Search cases for this section  |  syfert.com