Oregon Revised Statutes homeSearch Oregon
Or. Rev. Stat.Oregon Revised Statutes

Or. Rev. Stat. § 225.270 (2026)

Use of surplus revenue

Edition and currency
laws through the 2025 session (checked Sept. 2026). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTlaws through the 2025 session (checked Sept. 2026) cited 1972–1981 2citing cases
At a glance

Courts have cited this section in 2 opinions since 1972.

      225.270 Use of surplus revenue. When any city which owns or operates a municipal electric power plant or system or distributing system, has paid principal and interest to date on all indebtedness incurred in connection therewith, and has created and accumulated an adequate depreciation and replacement reserve in the judgment of the officer having control of such plant or system, the city shall, for the purpose of reducing general property taxes within such city, pay to itself not less than three percent of the annual gross operating revenue of such plant or system, or a volumetric charge based upon the amounts of electricity delivered, transmitted or distributed to retail electricity consumers regardless of the source. The volumetric charge shall not be less than the equivalent of three percent of the gross operating revenues of the municipality utility in 1999. The city shall adjust a volumetric charge to end users such that charges established for different customer classes bear the same approximate relationship as the gross revenues per kilowatt hour paid by the classes in 1999. [Amended by 1999 c.865 §32]

The 2 cases that cite Or. Rev. Stat. § 225.270 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENPorter v. Tiffany, 502 P.2d 1385 (Or. Ct. App. 1972).
cites § 225.270 2×cited by 14 cases
Where it cites § 225.270
“ued in connection with operation of any such plant or system, and also in payment for alterations, improvements, additions or extensions and for redemption and retirement of outstanding bonds, together with interest thereon, and shall be expended only in connection with and for…”
2
GREENNicoll v. City of Eugene, 628 P.2d 1213 (Or. Ct. App. 1981).
cites § 225.270 1×cited by 5 cases
Where it cites § 225.270
“ued in connection with operation of any such plant or system, and also in payment for alterations, improvements, additions or extensions and for redemption and retirement of outstanding bonds, together with interest thereon, and shall be expended only in connection with and for…”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: laws through the 2025 session (checked Sept. 2026). Syfert holds no earlier or later version of this section.

Oregon Revised Statutes Home  |  Search Oregon  |  Search cases for this section  |  syfert.com