Or. Rev. Stat. § 468A.710 (2026)
License required for asbestos abatement project
Edition and currency
Other sources
Courts have cited this section in 1 opinion since 2006.
468A.710 License required for asbestos abatement project. (1) Except as provided in ORS 468A.707 (1)(c) and (3), after the Environmental Quality Commission adopts rules under ORS 468A.707 and 468A.745, no contractor shall work on an asbestos abatement project unless the contractor holds a license issued by the Department of Environmental Quality under ORS 468A.720.
(2) A contractor carrying out an asbestos abatement project shall be responsible for the safe and proper handling and delivery of waste that includes asbestos-containing material to a landfill authorized to receive such waste. [Formerly 468.879]
- Where it cites § 468A.710
- “The statutory scheme attempts to accomplish that goal by (1) ensuring that persons who carry out asbestos abatement projects are properly licensed or certified, ORS 468A.710; ORS 468A.715(2), and (2) ensuring that persons who require others to carry out those projects hire or…”
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.
Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.
Edition shown: laws through the 2025 session (checked Sept. 2026). Syfert holds no earlier or later version of this section.