Or. Rev. Stat. § 469.320 (2026)

Site certificate required; exceptions

Edition and currency
laws through the 2025 session (checked Sept. 2026). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTlaws through the 2025 session (checked Sept. 2026) ACTIVE · 5 IN 5Y cited 1979–2025 12citing cases
At a glance

Courts have cited this section in 12 opinions since 1979, 5 of them in the last five years. The most litigated part is subsection (1) (8 cases).

      469.320 Site certificate required; exceptions. (1) Except as provided in subsections (2) and (5) of this section, no facility shall be constructed or expanded unless a site certificate has been issued for the site thereof in the manner provided in ORS 469.300 to 469.563, 469.590 to 469.619, 469.930 and 469.992. No facility shall be constructed or operated except in conformity with the requirements of ORS 469.300 to 469.563, 469.590 to 469.619, 469.930 and 469.992.

      (2) A site certificate is not required for:

      (a) An energy facility for which no site certificate has been issued that, on August 2, 1993, had operable electric generating equipment for a modification that uses the same fuel type and increases electric generating capacity, if:

      (A) The site is not enlarged; and

      (B) The ability of the energy facility to use fuel for electricity production under peak steady state operating conditions is not more than 200 million Btu per hour greater than it was on August 2, 1993, or the energy facility expansion is called for in the short-term plan of action of an energy resource plan that has been acknowledged by the Public Utility Commission of Oregon.

      (b) Construction or expansion of any interstate natural gas pipeline or associated underground natural gas storage facility authorized by and subject to the continuing regulation of the Federal Energy Regulatory Commission or successor agency.

      (c) An energy facility, except coal and nuclear power plants, if the energy facility:

      (A) Sequentially produces electrical energy and useful thermal energy from the same fuel source; and

      (B) Under average annual operating conditions, has a nominal electric generating capacity:

      (i) Of less than 50 megawatts and the fuel chargeable to power heat rate value is not greater than 6,000 Btu per kilowatt hour;

      (ii) Of 50 megawatts or more and the fuel chargeable to power heat rate value is not greater than 5,500 Btu per kilowatt hour; or

      (iii) Specified by the Energy Facility Siting Council by rule based on the council’s determination relating to emissions of the energy facility.

      (d) Temporary storage, at the site of a nuclear-fueled thermal power plant for which a site certificate has been issued by the State of Oregon, of radioactive waste from the plant.

      (e) An energy facility as defined in ORS 469.300 (12)(a)(G), if the plant also produces a secondary fuel used on site for the production of heat or electricity, if the output of the primary fuel is less than six billion Btu of heat a day.

      (f) An energy facility as defined in ORS 469.300 (12)(a)(G), if the facility:

      (A) Exclusively uses biomass, including but not limited to grain, whey, potatoes, oilseeds, waste vegetable oil or cellulosic biomass, as the source of material for conversion to a liquid fuel;

      (B) Has received local land use approval under the applicable acknowledged comprehensive plan and land use regulations of the affected local government and the facility complies with any statewide planning goals or rules of the Land Conservation and Development Commission that are directly applicable to the facility;

      (C) Requires no new electric transmission lines or gas or petroleum product pipelines that would require a site certificate under subsection (1) of this section;

      (D) Produces synthetic fuel, at least 90 percent of which is used in an industrial or refueling facility located within one mile of the facility or is transported from the facility by rail or barge; and

      (E) Emits less than 118 pounds of carbon dioxide per million Btu from fossil fuel used for conversion energy.

      (g) A standby generation facility, if the facility complies with all of the following:

      (A) The facility has received local land use approval under the applicable acknowledged comprehensive plan and land use regulations of the affected local government and the facility complies with all statewide planning goals and applicable rules of the Land Conservation and Development Commission;

      (B) The standby generators have been approved by the Department of Environmental Quality as having complied with all applicable air and water quality requirements. For an applicant that proposes to provide the physical facilities for the installation of standby generators, the requirement of this subparagraph may be met by agreeing to require such a term in the lease contract for the facility; and

      (C) The standby generators are:

      (i) Electrically incapable of being interconnected to the transmission grid. For an applicant that proposes to provide the physical facilities for the installation of standby generators under this sub-subparagraph, the requirement of this sub-subparagraph may be met by agreeing to require such a term in the lease contract for the facility; or

      (ii) Electrically capable of being interconnected to the grid but are dispatched to the grid by a local transmission and distribution grid operator or balancing authority to support grid reliability, are operated consistent with 40 C.F.R. 63.6640(f), as in effect on March 27, 2024, and are exclusively using renewable fuels, including renewable diesel, renewable natural gas or renewable hydrogen, if such fuels are available and if their use does not violate the warranty or certification of the generator.

      (3) The Energy Facility Siting Council may review and, if necessary, revise the fuel chargeable to power heat rate value set forth in subsection (2)(c)(B) of this section. In making its determination, the council shall ensure that the fuel chargeable to power heat rate value for facilities set forth in subsection (2)(c)(B) of this section remains significantly lower than the fuel chargeable to power heat rate value for the best available, commercially viable thermal power plant technology at the time of the revision.

      (4)(a)(A) Any person who proposes to construct or enlarge an energy facility and who claims an exemption under subsection (2)(a), (c) or (f) of this section from the requirement to obtain a site certificate shall request the Energy Facility Siting Council to determine whether the proposed facility qualifies for the claimed exemption.

      (B) The council may not require a person who operates or proposes to construct or enlarge an energy facility to request that the council determine whether the proposed facility qualifies for exemption under subsection (2)(g) of this section.

      (b) The council shall make its determination within 60 days after the request for exemption is filed. An appeal from the council’s determination on a request for exemption shall be made under ORS 469.403, except that the scope of review by the Supreme Court shall be the same as a review by a circuit court under ORS 183.484. The record on review by the Supreme Court shall be the record established in the council proceeding on the exemption.

      (5) Notwithstanding subsection (1) of this section, a separate site certificate shall not be required for:

      (a) Transmission lines, battery energy storage systems, storage facilities, pipelines or similar related or supporting facilities, if such related or supporting facilities are addressed in and are subject to a site certificate for another energy facility;

      (b) Expansion within the site or within the energy generation area of a facility for which a site certificate has been issued, if the existing site certificate has been amended to authorize expansion; or

      (c) Expansion, either within the site or outside the site, of an existing council certified surface facility related to an underground gas storage reservoir, if the existing site certificate is amended to authorize expansion.

      (6) If the substantial loss of the steam host causes a facility exempt under subsection (2)(c) of this section to substantially fail to meet the exemption requirements under subsection (2)(c) of this section, the electric generating facility shall cease to operate one year after the substantial loss of the steam host unless an application for a site certificate has been filed in accordance with the provisions of ORS 469.300 to 469.563.

      (7) As used in this section:

      (a) “Standby generation facility” means an electric power generating facility, including standby generators and the physical structures necessary to install and connect standby generators, that provides temporary electric power:

      (A) In the event of a power outage and that is electrically incapable of being interconnected with the transmission grid; or

      (B) Consistent with 40 C.F.R. 63.6640(f), as in effect on March 27, 2024.

      (b) “Total energy output” means the sum of useful thermal energy output and useful electrical energy output.

      (c) “Useful thermal energy” means the verifiable thermal energy used in any viable industrial or commercial process, heating or cooling application.

      (8)(a) If the developer of a facility elects, or the governing body of the local government after consulting with the developer elects, to defer regulatory authority to the Energy Facility Siting Council, the developer of a facility shall obtain a site certificate, in the manner provided in ORS 469.300 to 469.563, 469.590 to 469.619, 469.930 and 469.992, for a facility that, notwithstanding the definition of “energy facility” in ORS 469.300, is:

      (A) An electric power generating plant with an average electric generating capacity of less than 100 megawatts produced from wind energy at a single energy facility or within a single energy generation area;

      (B) An associated transmission line;

      (C) A battery energy storage system; or

      (D) A solar photovoltaic power generation facility that is not an energy facility as defined in ORS 469.300 (12)(a)(D).

      (b) An election by a developer or a local government under this subsection is final.

      (c) An election by a local government under this subsection is not a land use decision as defined in ORS 197.015.

      (d) A local government may not make an election under this subsection after a permit application has been submitted under ORS 215.416 or 227.175. [Formerly 453.325; 1977 c.86 §1; 1979 c.730 §8; 1982 s.s.1 c.6 §1; 1987 c.200 §5; 1991 c.480 §5; 1993 c.569 §4; 1995 c.505 §7; 1999 c.365 §6; 1999 c.385 §1; 2001 c.134 §§3,4; 2001 c.683 §§7,8; 2003 c.186 §§76,77; 2005 c.768 §§1,2; 2007 c.739 §33; 2009 c.751 §7; 2019 c.650 §2; 2021 c.109 §1; 2024 c.25 §2; 2024 c.51 §9; 2025 c.162 §2]

The 12 cases that cite Or. Rev. Stat. § 469.320 most heavily, weighted by court and treatment. RelevanceNewestTreatment
cites § 469.320 8×subsections: (2)(c) 7× (2)cited by 178 cases
Where it cites § 469.320
“ORS 469.320(2) (c) exempts cogeneration facilities with a fuel chargeable to power heat rate of not greater than 6000 BTU per kilowatt hour from the site certificate process in its entirety.”
The case’s holding
A reviewing court defers to an agency's interpretation of its own administrative rule if the interpretation is plausible and not inconsistent with the rule's wording, context, or other law.
Later courts cite it for
“inconsistent with the wording of the rule itself, or with the rule's context, or with any other source of law.” · 33 citing courts
cites § 469.320 2×subsections: (1)cited by 9 cases
Where it cites § 469.320
“The statute instead notes that, "[e]xcept as otherwise provided in ORS 469.320 and this section, the review by the Supreme Court shall be the same as the review by the Court of Appeals described in ORS 183.”
The case’s holding
A rule adopted in substantial compliance with the agency's statutory rulemaking notice procedures is adopted in compliance with applicable rulemaking procedures, and the required measurement statement must be retrievable.
Later courts cite it for
“a rule adopted in substantial compliance with ors 183.335 is a rule adopted in 'compliance with applicable rulemaking procedures” · 2 citing courts
3
GREENStop B2H Coalition v. Dept. of Energy, 525 P.3d 864 (Or. 2023).
cites § 469.320 1×cited by 15 cases
Where it cites § 469.320
“of Energy “energy facility”); ORS 469.320 (site certificate require- ment).”
The case’s holding
Courts construing a statute seek to discern the intent of the legislature that enacted it, and agency action is reviewable where it is directed at identifiable regulated conduct.
Later courts cite it for
“modification of the one-mile requirement applied only to the site certificate for this specific proposed transmission line” · 3 citing courts
cites § 469.320 2×subsections: (1)cited by 3 cases
Where it cites § 469.320
“ORS 469.320 generally prohibits construction of a waste disposal facility unless EFSC issues a site certificate.”
5
REDWyers v. Dressler, 601 P.2d 1268 (Or. Ct. App. 1979).
cites § 469.320 1×cited by 14 cases
Overruled by Mendieta v. State, Division of State Lands on other grounds: 2 citing opinions limit it to other grounds.
Where it cites § 469.320
“) Plaintiffs read this section in conjunction with ORS 469.320, which states, " * * * no energy facility shall be constructed or *806 expanded unless a site certificate has been issued for the site thereof * * and with ORS 469.”
Later courts cite it for
“an agency which is vested with discretion by statute may limit its own discretion in its regulations.” · 1 citing court
cites § 469.320 1×subsections: (1)cited by 12 cases
Where it cites § 469.320
“1 See ORS 469.320(1) and ORS 469.300(10)(b), (14), (17)(a) and (24).”
Later courts cite it for
“analysis of the specific statutory scheme under which an agency operates and the nature of the rule that the agency wishes to adopt.” · 4 citing courts
cites § 469.320 2×subsections: (1) 2×cited by 3 cases
Where it cites § 469.320
“See ORS 469.320(1) (“[N]o facility shall be constructed or expanded unless a site certificate has been issued for the site.”
Later courts cite it for
“the council oversees the development of large energy facilities in oregon, including electric power generating plants, high-voltage transmission lines, gas pipelines, and radioactive waste disposal sites, among other projects.” · 2 citing courts
cites § 469.320 1×subsections: (1)cited by 14 cases
Where it cites § 469.320
“ORS 469.320(1). 2 Applications for site certificates must be made to EFSC.”
9
GREENGilbert /March v. Dept. of Energy, 566 P.3d 627 (Or. 2025).
cites § 469.320 3×subsections: (5) (5)(b)cited by 0 cases
Where it cites § 469.320
“Under that system, a party who seeks to build an “energy facility” must obtain authority—known as a “site certificate”—from EFSC before it can proceed.”
10
NO FLAGForelaws on Bd. v. Energy Facility Siting Council, 811 P.2d 636 (Or. 1991).
cites § 469.320 3×subsections: (1)cited by 0 cases
Where it cites § 469.320
“6 Procedures for approving, rejecting and issuing site certificate applications are set forth in ORS 469.320 to ORS 469.400. Normally, the parties in such cases are EFSC, the applicant and other intervening persons permitted to become a party “in support of or in opposition to…”
11
GREENUmatilla Cnty. v. Dept. of Energy, 547 P.3d 804 (Or. 2024).
cites § 469.320 1×subsections: (1)cited by 0 cases
Where it cites § 469.320
“See ORS 469.320(1) (“[N]o facility shall be constructed or expanded unless a site certificate has been 2 Those standards are adopted as DOE regulations.”
12
GREENUmatilla Cnty. v. Dept. of Energy, 547 P.3d 804 (Or. 2024).
cites § 469.320 1×subsections: (1)cited by 0 cases
Where it cites § 469.320
“See ORS 469.320(1) (“[N]o facility shall be constructed or expanded unless a site certificate has been 2 Those standards are adopted as DOE regulations.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
197920022025

One bar per year. Tallest: 2 cases in 2024. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Or.11Or. Ct. App.1
By subsection
(1)8 cases
Friends of the Columbia Gorge v. Energy Facility Siting Council, 446 P.3d 53 (Or. 2019).“The statute instead notes that, "[e]xcept as otherwise provided in ORS 469.320 and this section, the review by the Supreme Court shall be the same as the review by the Court of Appeals described in ORS 183.”
Forelaws on Bd. v. Energy Facility Siting Council, 760 P.2d 212 (Or. 1988).“1 See ORS 469.320(1) and ORS 469.300(10)(b), (14), (17)(a) and (24).”
Fremont Lumber Co. v. Energy Facility Siting Council, 16 P.3d 1147 (Or. 2001).“ORS 469.320 generally prohibits construction of a waste disposal facility unless EFSC issues a site certificate.”
Friends of Columbia Gorge v. Energy Fac. Siting Coun., 486 P.3d 787 (Or. 2021).“See ORS 469.320(1) (“[N]o facility shall be constructed or expanded unless a site certificate has been issued for the site.”
Teledyne Wah Chang Albany v. Energy Facility Siting Council, 692 P.2d 86 (Or. 1985).“ORS 469.320(1). 2 Applications for site certificates must be made to EFSC.”
Showing the top 5 of 8. More in the list view →
(2)1 case
Don't Waste Oregon Comm. v. Energy Facility Siting Council, 881 P.2d 119 (Or. 1994).“ORS 469.320(2) (c) exempts cogeneration facilities with a fuel chargeable to power heat rate of not greater than 6000 BTU per kilowatt hour from the site certificate process in its entirety.”
(2)(c)1 case
(5)1 case
Gilbert /March v. Dept. of Energy, 566 P.3d 627 (Or. 2025).“Under that system, a party who seeks to build an “energy facility” must obtain authority—known as a “site certificate”—from EFSC before it can proceed.”
(5)(b)1 case
Gilbert /March v. Dept. of Energy, 566 P.3d 627 (Or. 2025).
Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.