Or. Rev. Stat. § 543.610 (2026)
Acquisition of project by state or municipality
Edition and currency
Other sources
Courts have cited this section in 9 opinions since 1982, 1 of them in the last five years. The most litigated part is subsection (1) (5 cases).
543.610 Acquisition of project by state or municipality. (1) Upon not less than two years’ notice in writing the state, or any municipality thereof, shall have the right at any time to take over and thereafter to maintain and operate any project constructed under a license pursuant to ORS 543.010 to 543.610, upon payment of just compensation, including such reasonable damages, if any, to valuable, serviceable and dependent property of the holder of the license, not taken over, as may be caused by the severance therefrom of the property taken, and shall assume all contracts entered into by the licensee which are required to have and do have the express approval of the Water Resources Commission. If the sum to be paid cannot be agreed upon by the holder of the license and the municipality or the state, as the case may be, it shall be determined in a proceeding in equity instituted by the state or municipality, as the case may be, in the circuit court of the county in which the major part of the project is located.
(2) There is also expressly reserved to the state, and any municipality thereof, the right to take over all or any part of any project by condemnation proceedings as may be provided by the laws of Oregon or the charter of any such municipality. [Amended by 1983 c.799 §8]
543.620 [Repealed by 1995 c.229 §9]
POWER GENERATION BY DISTRICTS
- Where it cites § 543.610
- “Emerald People's Utility District (Emerald) filed this action under ORS 543.610 (1981) to take over the hydroelectric project of defendant Pacific Power & Light (PP & L).”
- The case’s holding
- The omission of a specific term in one statute that is included in a related statute implies a deliberate legislative intent to exclude that term from the related statute.
- Where it cites § 543.610
- “Emerald People’s Utility District (Emerald) filed this action pursuant to former ORS 543.610 for a judicial determination of the price to be paid for hydroelectric dams, located outside the district, that Emerald proposed to take over from Pacific Power & Light (PP&L) under the…”
- Where it cites § 543.610
- “Emerald People's Utility District (Emerald) filed this action pursuant to former ORS 543.610 for a judicial determination of the price to be paid for hydroelectric dams, located outside the district, that Emerald proposed to take over from Pacific Power & Light (PP & L) under…”
- Where it cites § 543.610
- “Emerald People’s Utility District (Emerald) filed this action under ORS 543.610 (1981) to take over the hydroelectric project of defendant Pacific Power & Light (PP&L).”
- Where it cites § 543.610
- “2d 552 . Thus, in deciding whether PUDs are "municipalities" within the meaning of a particular statute, this court examines the specific statutory context at issue.”
- Later courts cite it for
- “provide authority for the people of a city to determine the organization, and to define the powers, of their local government without first having to obtain authorization from the state legislature.” · 2 citing courts
- Where it cites § 543.610
- “” 2 Plaintiffs made an earlier effort to acquire some of defendant’s facilities pursuant to ORS 543.610. The Supreme Court held in Emerald PUD v.”
- Where it cites § 543.610
- “Alfalfa Solar I, LLC “(1) The Public Utility Commission shall establish minimum criteria that a cogeneration facility or small power production facility must meet to qualify as a qual- ifying facility under ORS 543.610, 757.005 and 758.505 to 758.555.”
- Later courts cite it for
- “it is not our role to add limitations that the legislature itself did not include.” · 3 citing courts
- Where it cites § 543.610
- “In Emerald PUD , for example, this court concluded that PUDs do not qualify as *644 “municipalities” within the meaning of ORS 543.610 because the legislature had enacted that statute together with Oregon Laws 1931, chapter 279, 11 which distinguished between municipalities and…”
- Where it cites § 543.610
- “” On August 7, 1981, EPUD’s president, Richard Eymann, sent a letter to PPL, which read in its entirety: “This letter serves as the notice required by ORS 543.610 that the Emerald People’s Utility District will take over and thereafter maintain and operate a portion of the…”
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
One bar per year. Tallest: 2 cases in 1985. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.
(1)5 cases
(2)2 cases
Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.
Edition shown: laws through the 2025 session (checked Sept. 2026). Syfert holds no earlier or later version of this section.