Tex. Prop. Code § 53.023 (2026)
Payment Secured By Lien
Edition and currency
Other sources
Courts have cited this section in 8 opinions since 2013, 4 of them in the last five years. The most litigated part is subsection (1) (2 cases).
Sec. 53.023. PAYMENT SECURED BY LIEN. The lien secures payment for:
(1) the labor done or material furnished for the construction, repair, design, survey, or demolition; or
(2) the specially fabricated material, even if the material has not been delivered or incorporated into the construction or repair, less its fair salvage value.
Acts 1983, 68th Leg., p. 3536, ch. 576, Sec. 1, eff. Jan. 1, 1984. Amended by Acts 1995, 74th Leg., ch. 851, Sec. 2, eff. Sept. 1, 1995.
Amended by:
Acts 2021, 87th Leg., R.S., Ch. 690 (H.B. 2237), Sec. 6, eff. January 1, 2022.
- Where it cites § 53.023
- “” Tex. Prop. Code Ann. § 53.023 . As to the post-release liens, there is no contention that the builder “d[id] labor.”
- The case’s holding
- A lien release discharging a specific lien does not waive the underlying debt or the right to file new liens for subsequent expenses or on different property tracts.
- Later courts cite it for
- “demonstrating that no genuine issues of material fact exist and that he is entitled to judgment as a matter of law.” · 2 citing courts
- Where it cites § 53.023
- “See Tex. Prop.Code Ann. § 53.021 (providing lien for labor furnished); Tex.”
- Where it cites § 53.023
- “the labor done or material furnished for the construction or repair” under Texas law (quoting Tex. Prop. Code Ann. § 53.023 )). 6The relevant statute now reads, “[E]xcept that no property of the taxpayer is exempt from payment of the tax.”
- Later courts cite it for
- “we review questions of statutory interpretation for correction of errors at law.” · 2 citing courts
- Where it cites § 53.023
- “See TEX. PROP. CODE §§ 53.023, 56.002. The trial court found: Had ERT limited the lien to secure payment for authorized items (i.”
- Later courts cite it for
- “if there is more than a scintilla of evidence to support a finding, it must be upheld.” · 2 citing courts
- Summary
- No passage or summary on file for this case yet.
- Where it cites § 53.023
- “See TEX. PROP. CODE § 53.023(1) (mechanic’s or materialman’s lien secures payment for “labor done or material furnished for the construction”).”
- Where it cites § 53.023
- “See TEX. PROP. CODE ANN. § 53.023 (1) (providing for a lien to secure payment for “the labor done or material furnished for the construction, repair, design, survey, or demolition.”
- Where it cites § 53.023
- “TEX. PROP. CODE § 53.023(1). Section 53.021 does not require that the material furnished “should actually enter into the construction of the improvement.”
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
One bar per year. Tallest: 2 cases in 2023. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.
(1)2 cases
Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.