Texas Codes homeSearch Texas
Tex. CodesUtilities CodeTitle 2. Public Utility Regulatory ActSubtitle B. Electric UtilitiesChapter 37. Certificates of Convenience and Necessity

Tex. Util. Code § 37.056 (2026)

Grant Or Denial Of Certificate

Edition and currency
laws through the 89th Legislature (2025). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTlaws through the 89th Legislature (2025) cited 2003–2025 19citing cases
At a glance

Courts have cited this section in 19 opinions since 2003, 4 of them in the last five years. The most litigated part is subsection (e) (3 cases).

Sec. 37.056. GRANT OR DENIAL OF CERTIFICATE. (a) The commission may approve an application and grant a certificate only if the commission finds that the certificate is necessary for the service, accommodation, convenience, or safety of the public.

(b) The commission may:

(1) grant the certificate as requested;

(2) grant the certificate for the construction of a portion of the requested system, facility, or extension or the partial exercise of the requested right or privilege; or

(3) refuse to grant the certificate.

(c) The commission shall grant each certificate on a nondiscriminatory basis after considering:

(1) the adequacy of existing service;

(2) the need for additional service;

(3) the effect of granting the certificate on the recipient of the certificate and any electric utility serving the proximate area; and

(4) other factors, such as:

(A) community values;

(B) recreational and park areas;

(C) historical and aesthetic values;

(D) environmental integrity;

(E) the probable improvement of service or lowering of cost to consumers in the area if the certificate is granted, including any potential economic or reliability benefits associated with dual fuel and fuel storage capabilities in areas outside the ERCOT power region; and

(F) the need for extending transmission service where existing or projected electrical loads will be underserved, including where:

(i) the existing transmission service is unreasonably remote;

(ii) the available capacity is unreasonably limited at transmission or distribution voltage level; or

(iii) the electrical load cannot be interconnected in a timely manner.

(c-1) In considering the need for additional service under Subsection (c)(2) for a reliability transmission project that serves the ERCOT power region or under Subsection (c)(4)(F), the commission must consider the historical load, forecasted load growth, and additional load currently seeking interconnection, including load for which the electric utility has yet to sign an interconnection agreement, as determined by the electric utility with the responsibility for serving the load.

(d) The commission by rule shall establish criteria, in addition to the criteria described by Subsection (c), for granting a certificate for a transmission project that serves the ERCOT power region and that is not necessary to meet state or federal reliability standards. The criteria must include a comparison of the estimated cost of the transmission project for consumers and the estimated congestion cost savings for consumers that may result from the transmission project, considering both current and future expected congestion levels and the transmission project's ability to reduce those congestion levels. The commission shall include with its decision on an application for a certificate to which this subsection applies findings on the criteria.

(e) A certificate to build, own, or operate a new transmission facility that directly interconnects with an existing electric utility facility or municipally owned utility facility may be granted only to the owner of that existing facility. If a new transmission facility will directly interconnect with facilities owned by different electric utilities or municipally owned utilities, each entity shall be certificated to build, own, or operate the new facility in separate and discrete equal parts unless they agree otherwise.

(f) Notwithstanding Subsection (e), if a new transmission line, whether single or double circuit, will create the first interconnection between a load-serving station and an existing transmission facility, the entity with a load-serving responsibility or an electric cooperative that has a member with a load-serving responsibility at the load-serving station shall be certificated to build, own, or operate the new transmission line and the load-serving station. The owner of the existing transmission facility shall be certificated to build, own, or operate the station or tap at the existing transmission facility to provide the interconnection, unless after a reasonable period of time the owner of the existing transmission facility is unwilling to build, and then the entity with the load-serving responsibility or an electric cooperative that has a member with a load-serving responsibility may be certificated to build the interconnection facility.

(g) Notwithstanding any other provision of this section, an electric utility or municipally owned utility that is authorized to build, own, or operate a new transmission facility under Subsection (e) or (f) may designate another electric utility that is currently certificated by the commission within the same electric power region, coordinating council, independent system operator, or power pool or a municipally owned utility to build, own, or operate a portion or all of such new transmission facility, subject to any requirements adopted by the commission by rule.

(h) The division of any required certification of facilities described in this section shall apply unless each entity agrees otherwise. Nothing in this section is intended to require a certificate for facilities that the commission has determined by rule do not require certification to build, own, or operate.

(i) Notwithstanding any other provision of this section, an electric cooperative may be certificated to build, own, or operate a new facility in place of any other electric cooperative if both cooperatives agree.

Acts 1997, 75th Leg., ch. 166, Sec. 1, eff. Sept. 1, 1997. Amended by Acts 2003, 78th Leg., ch. 295, Sec. 2, eff. June 18, 2003.

Amended by:

Acts 2011, 82nd Leg., R.S., Ch. 949 (H.B. 971), Sec. 2(a), eff. June 17, 2011.

Acts 2019, 86th Leg., R.S., Ch. 44 (S.B. 1938), Sec. 4, eff. May 16, 2019.

Acts 2021, 87th Leg., R.S., Ch. 198 (H.B. 1510), Sec. 3, eff. June 1, 2021.

Acts 2021, 87th Leg., R.S., Ch. 876 (S.B. 1281), Sec. 2, eff. September 1, 2021.

Acts 2023, 88th Leg., R.S., Ch. 410 (H.B. 1500), Sec. 12, eff. September 1, 2023.

Acts 2023, 88th Leg., R.S., Ch. 892 (H.B. 5066), Sec. 1, eff. June 13, 2023.

The 19 cases that cite Tex. Util. Code § 37.056 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENNextEra v. Lake, 48 F.4th 306 (5th Cir. 2022).
cites § 37.056 4×subsections: (e) 2× (f)cited by 15 cases
Where it cites § 37.056
“CODE § 37.056. The court concluded that the preference for incumbents was not discriminatory because it “applie[d] evenhandedly to all entities, regardless of whether they are Minnesota-based entities or based elsewhere.”
The case’s holding
A dismissal of a dormant commerce clause claim is reversed when the underlying legal sufficiency is established (reversing dismissal of dormant commerce clause claim).
Later courts cite it for
“limiting competition based on the existence or extent of a business's local foothold,” · 8 citing courts
2
GREENPub. Util. Comm'n v. Cities of Harlingen, 311 S.W.3d 610 (Tex. App.—Austin 2010).
cites § 37.056 2×cited by 24 cases
Where it cites § 37.056
“[9] Thus, we are convinced that the Commission's interpretation, that when a transfer occurs in which no new services are contemplated there is no need to comply with section 37.”
Later courts cite it for
“in the absence of some showing, either by legislative history or otherwise, that the intent of the legislature in adopting the amendment was to clarify rather than change the statute in question, the presumption is of change rather than clarification.” · 2 citing courts
3
GREENHammack v. Pub. Util. Com'n of Texas, 131 S.W.3d 713 (Tex. App.—Austin 2004).
cites § 37.056 1×cited by 95 cases
Where it cites § 37.056
“See Tex. Util. Code Ann. § 37.056 (West 1998) (hereinafter “PURA”).”
The case’s holding
A trial court may deny discovery requests based on a commission's assertion of privilege (affirming trial court’s denial of discovery request based on commission’s assertions of privilege).
Later courts cite it for
“specialized judgment, knowledge, and expertise” · 5 citing courts
4
GREENSw. Elec. Power Co. v. Pub. Util. Comm'n of Texas, 419 S.W.3d 414 (Tex. App.—Amarillo 2011).
cites § 37.056 4×subsections: (b)(2)cited by 4 cases
Where it cites § 37.056
“12 Tex. Util.Code Ann. § 37.056 (West 2007).”
5
GREENDunn v. Pub. Util. Com'n of Texas, 246 S.W.3d 788 (Tex. App.—Austin 2008).
cites § 37.056 1×subsections: (c)cited by 18 cases
Where it cites § 37.056
“Laws 713 , 787 (amended 2003) (current version at Tex. Util.Code Ann. § 37.056(c) (West 2007)).”
Later courts cite it for
“we will consider an administrative agency's decision to be arbitrary and capricious or an abuse of discretion if the agency reaches a completely unreasonable result after weighing the relevant factors established by the legislature.” · 3 citing courts
6
GREENNextEra v. D'Andrea, No. 20-50160 (5th Cir. Aug. 30, 2022).
cites § 37.056 3×subsections: (e) 2× (f)cited by 0 cases
Where it cites § 37.056
“Those lines that carry electricity through multiple states are classic instrumentalities of interstate commerce.”
cites § 37.056 1×subsections: (a)cited by 0 cases
Where it cites § 37.056
“, TEX. UTIL. CODE § 37.056(a), (c) (specifying required findings and criteria for granting or denying a certificate of convenience and necessity).”
Later courts cite it for
“acts arbitrarily or abuses its discretion if it fails to consider a mandatory factor, considers an irrelevant factor, considers appropriate factors but reaches a completely unreasonable result, or fails to follow its own regulations.” · 4 citing courts
8
NO FLAGDon Ross Malone v. Pub. Util. Comm'n of Texas Elec. TransmissionTexas, LLC, No. 03-11-00815-CV (Tex. App.—Austin Aug. 28, 2013).
cites § 37.056 3×subsections: (c) 2× (a)cited by 0 cases
Where it cites § 37.056
“4 Tex. Util. Code § 37.056(a). Ultimately, the 4 Section 37.”
9
GREENSw. Elec. Power Co. v. Pub. Util. Comm'n of Texas, No. 07-10-00108-CV (Tex. App.—Amarillo Nov. 4, 2011).
cites § 37.056 3×subsections: (b)(2)cited by 0 cases
Where it cites § 37.056
“12 TEX. UTIL. CODE ANN. § 37.056 (West 2007).”
10
NO FLAGEnergy Michigan, Inc. v. Michigan Pub. Serv. Comm'n, No. 2:20-cv-12521 (E.D. Mich. Feb. 24, 2023).
cites § 37.056 1×subsections: (e)cited by 0 casesunknown
Where it cites § 37.056
“Util. Code § 37.056(e)). In deciding whether the complaint plausibly pleaded a dormant Commerce Clause claim, the Fifth Circuit considered at length whether and when Tracy shields electric utilities from Commerce Clause scrutiny.”
cites § 37.056 1×cited by 0 cases
Where it cites § 37.056
“See Tex. Util. Code Ann. § 37.056 (West 1998) (hereinafter “PURA”).”
cites § 37.056 1×cited by 0 cases
Where it cites § 37.056
“See Tex. Util. Code Ann. § 37.056 (West 1998) (hereinafter "PURA").”
cites § 37.056 1×cited by 0 cases
Where it cites § 37.056
“See Tex. Util. Code Ann. § 37.056 (West 1998) (hereinafter "PURA").”
14
GREENJim Dunn v. Pub. Util. Comm'n of Texas & Oncor Elec. Delivery Co., No. 03-06-00699-CV (Tex. App.—Austin Feb. 7, 2008).
cites § 37.056 1×cited by 0 cases
Where it cites § 37.056
“Laws 713 , 787 (amended 2003) (current version at Tex. Util. Code Ann. § 37.056 (c) (West 2007)).”
15
GREENJim Dunn v. Pub. Util. Comm'n of Texas & Oncor Elec. Delivery Co., No. 03-06-00699-CV (Tex. App.—Austin Feb. 7, 2008).
cites § 37.056 1×cited by 0 cases
Where it cites § 37.056
“Laws 713 , 787 (amended 2003) (current version at Tex. Util. Code Ann. § 37.056 (c) (West 2007)).”
cites § 37.056 1×cited by 0 cases
Where it cites § 37.056
“9 Thus, we are convinced that the Commission’s interpretation, that when a transfer occurs in which no new services are contemplated there is no need to comply with section 37.”
cites § 37.056 1×cited by 0 cases
Where it cites § 37.056
“(9) Thus, we are convinced that the Commission's interpretation, that when a transfer occurs in which no new services are contemplated there is no need to comply with section 37.”
18
NO FLAGJessie F. McMaster, Jr. v. Pub. Util. Comm'n of Texas, No. 03-11-00571-CV, 2012 Tex. App. LEXIS 7502 (Tex. App.—Austin Aug. 31, 2012).
cites § 37.056 1×cited by 0 cases
Where it cites § 37.056
“" See Tex. Util. Code Ann. § 37.056 (a); see also id.”
19
NO FLAGJessie F. McMaster, Jr. v. Pub. Util. Comm'n of Texas, No. 03-11-00571-CV (Tex. App.—Austin Aug. 31, 2012).
cites § 37.056 1×cited by 0 cases
Where it cites § 37.056
“” See Tex. Util. Code Ann. § 37.056 (a); see also id.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
200320142025

One bar per year. Tallest: 3 cases in 2008. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Tex. App.12Tex. App.—Austin35th Cir.2E.D. Mich.1Tex.1
By subsection
(a)2 cases
Save Our Springs All., Inc. v. Texas Comm'n on Env't Quality & the City of Dripping Springs, 713 S.W.3d 308 (Tex. 2025).“, TEX. UTIL. CODE § 37.056(a), (c) (specifying required findings and criteria for granting or denying a certificate of convenience and necessity).”
Don Ross Malone v. Pub. Util. Comm'n of Texas Elec. TransmissionTexas, LLC, No. 03-11-00815-CV (Tex. App.—Austin Aug. 28, 2013).“4 Tex. Util. Code § 37.056(a). Ultimately, the 4 Section 37.”
(b)(2)2 cases
Sw. Elec. Power Co. v. Pub. Util. Comm'n of Texas, 419 S.W.3d 414 (Tex. App.—Amarillo 2011).“12 Tex. Util.Code Ann. § 37.056 (West 2007).”
Sw. Elec. Power Co. v. Pub. Util. Comm'n of Texas, No. 07-10-00108-CV (Tex. App.—Amarillo Nov. 4, 2011).“12 TEX. UTIL. CODE ANN. § 37.056 (West 2007).”
(c)2 cases
Dunn v. Pub. Util. Com'n of Texas, 246 S.W.3d 788 (Tex. App.—Austin 2008).“Laws 713 , 787 (amended 2003) (current version at Tex. Util.Code Ann. § 37.056(c) (West 2007)).”
Don Ross Malone v. Pub. Util. Comm'n of Texas Elec. TransmissionTexas, LLC, No. 03-11-00815-CV (Tex. App.—Austin Aug. 28, 2013).
(e)3 cases
NextEra v. Lake, 48 F.4th 306 (5th Cir. 2022).“CODE § 37.056. The court concluded that the preference for incumbents was not discriminatory because it “applie[d] evenhandedly to all entities, regardless of whether they are Minnesota-based entities or based elsewhere.”
NextEra v. D'Andrea, No. 20-50160 (5th Cir. Aug. 30, 2022).“Those lines that carry electricity through multiple states are classic instrumentalities of interstate commerce.”
Energy Michigan, Inc. v. Michigan Pub. Serv. Comm'n, No. 2:20-cv-12521 (E.D. Mich. Feb. 24, 2023).“Util. Code § 37.056(e)). In deciding whether the complaint plausibly pleaded a dormant Commerce Clause claim, the Fifth Circuit considered at length whether and when Tracy shields electric utilities from Commerce Clause scrutiny.”
(f)2 cases
NextEra v. Lake, 48 F.4th 306 (5th Cir. 2022).
NextEra v. D'Andrea, No. 20-50160 (5th Cir. Aug. 30, 2022).
Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: laws through the 89th Legislature (2025). Syfert holds no earlier or later version of this section.

Texas Codes Home  |  Search Texas  |  Search cases for this section  |  syfert.com