15 U.S.C. § 3371 (2026)

Authorization of certain sales and transportation

Edition and currency
U.S. Code current through Pub. L. 119-102 (OLRC release point). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTU.S. Code current through Pub. L. 119-102 (OLRC release point) cited 1981–2025 36citing cases
At a glance

Courts have cited this section in 36 opinions since 1981, 2 of them in the last five years. The most litigated part is subsection (a)(2) (1 case).

(a) Commission approval of transportation(1) Interstate pipelines(A) In general The Commission may, by rule or order, authorize any interstate pipeline to transport natural gas on behalf of—(i) any intrastate pipeline; and(ii) any local distribution company.(B) Just and reasonable rates

The rates and charges of any interstate pipeline with respect to any transportation authorized under subparagraph (A) shall be just and reasonable (within the meaning of the Natural Gas Act [15 U.S.C. 717 et seq.]).

(2) Intrastate pipelines(A) In generalThe Commission may, by rule or order, authorize any intrastate pipeline to transport natural gas on behalf of—(i) any interstate pipeline; and(ii) any local distribution company served by any interstate pipeline.(B) Rates and charges(i) Maximum fair and equitable price

The rates and charges of any intrastate pipeline with respect to any transportation authorized under subparagraph (A), including any amount computed in accordance with the rule prescribed under clause (ii), shall be fair and equitable and may not exceed an amount which is reasonably comparable to the rates and charges which interstate pipelines would be permitted to charge for providing similar transportation service.

(ii) Commission ruleThe Commission shall, by rule, establish the method for calculating an amount necessary to—(I) reasonably compensate any intrastate pipeline for expenses incurred by the pipeline and associated with the providing of any gathering, treatment, processing, transportation, delivery, or similar service provided by such pipeline in connection with any transportation of natural gas authorized under subparagraph (A); and(II) provide an opportunity for such pipeline to earn a reasonable profit on such services.
(b) Commission approval of sales(1) In generalThe Commission may, by rule or order, authorize any intrastate pipeline to sell natural gas to—(A) any interstate pipeline; and(B) any local distribution company served by any interstate pipeline.(2) Rates and charges(A) Maximum fair and equitable priceThe rates and charges of any intrastate pipeline with respect to any sale of natural gas authorized under paragraph (1) shall be fair and equitable and may not exceed the sum of—(i) such intrastate pipeline’s weighted average acquisition cost of natural gas;(ii) an amount, computed in accordance with the rule prescribed under subparagraph (B); and(iii) any adjustment permitted under subparagraph (C).(B) Commission ruleThe Commission shall, by rule, establish the method for calculating an amount necessary to—(i) reasonably compensate any intrastate pipeline for expenses incurred by the pipeline and associated with the providing of any gathering, treatment, processing, transportation, or delivery service provided by such pipeline in connection with any sale of natural gas authorized under paragraph (1); and(ii) provide an opportunity for such pipeline to earn a reasonable profit on such services.(C) Adjustment(i) ApplicationThis subparagraph shall apply in any case in which, in order to deliver any volume of natural gas pursuant to any sale authorized under paragraph (1), any intrastate pipeline acquires quantities of natural gas under any existing contract, if—(I) such intrastate pipeline acquires any volume of natural gas under such contract in excess of that which such pipeline would otherwise have acquired; and(II) the price paid for such additional volume of natural gas acquired under such contract is greater than such pipeline’s weighted average acquisition cost of natural gas, computed without regard to the acquisition of such additional volume of natural gas.(ii) Commission adjustment

In any case to which this subparagraph applies, the Commission shall permit an adjustment to the maximum fair and equitable price provided under subparagraph (A) to increase the revenue to the intrastate pipeline under such sale by an amount determined by the Commission to be adequate to offset the additional cost incurred by such pipeline due to any increase in such pipeline’s weighted average acquisition cost of natural gas.

(3) Limitation(A) Two-year duration

No authorization of any sale (or any extension thereof) under paragraph (1) may be for a period exceeding two years.

(B) Extension

Any authorization of any sale under paragraph (1), and any extension of any such authorization under this subparagraph, may be extended by the Commission if such extension satisfies the requirements of this subsection.

(4) Adequacy of service to intrastate customers

Any sale authorized under paragraph (1) shall be subject to interruption to the extent that natural gas subject to such sale is required to enable the intrastate pipeline involved to provide adequate service to such pipeline’s customers at the time of such sale.

(5) Procedural requirements(A) AffidavitAny application for authorization of any sale under paragraph (1) shall be accompanied by an affidavit filed by the intrastate pipeline involved and setting forth—(i) the identity of the interstate pipeline or local distribution company involved;(ii) each point of delivery of the natural gas from the intrastate pipeline;(iii) the estimated total and daily volumes of natural gas subject to such sale;(iv) the price or prices of such volumes; and(v) such other information as the Commission may, by rule, require.(B) Verification of compliance

Any application for authorization of any sale under paragraph (1) shall be accompanied by a statement by the intrastate pipeline involved verifying by oath or affirmation that such sale, if authorized, would comply with all requirements applicable to such sale under this subsection and all terms and conditions established, by rule or order, by the Commission and applicable to such sale.

(6) Termination of sales(A) HearingUpon complaint of any interested person, or upon the Commission’s own motion, the Commission shall, after affording an opportunity for oral presentation of views and arguments, terminate any sale authorized under paragraph (1) if the Commission determines—(i) such termination is required to enable the intrastate pipeline involved to provide adequate service to the customers of such pipeline at the time of such sale;(ii) such sale involves the sale of natural gas acquired by the intrastate pipeline involved solely or primarily for the purpose of resale of such natural gas pursuant to a sale authorized under paragraph (1);(iii) such sale violates any requirement of this subsection or any term or condition established, by rule or order, by the Commission and applicable to such sale; or(iv) such sale circumvents or violates any provision of this chapter.(B) Suspension pending hearing

Prior to any hearing or determination required under subparagraph (A), upon complaint of any interested person or upon the Commission’s own motion, the Commission may suspend any sale authorized under paragraph (1) if the Commission finds that it is likely that the determinations described in subparagraph (A) will be made following the hearing required under subparagraph (A).

(C) Determination

The determination of whether any interruption of any sale authorized under paragraph (1) is required under subparagraph (A)(i) shall be made by the Commission without regard to the character of the use of natural gas by any customer of the intrastate pipeline involved.

(D) State intervention

Any interested State may intervene as a matter of right in any proceeding before the Commission relating to any determination under this section.

(7) Disapproval of applicationThe Commission shall disapprove any application for authorization of any sale under paragraph (1) if the Commission determines—(A) such sale would impair the ability of the intrastate pipeline involved to provide adequate service to its customers at the time of such sale (without regard to the character of the use of natural gas by such customer);(B) such sale would involve the sale of natural gas acquired by the intrastate pipeline involved solely or primarily for the purpose of resale of such natural gas pursuant to a sale authorized under paragraph (1);(C) such sale would violate any requirement of this subsection or any term or condition established, by rule or order, by the Commission and applicable to such sale; or(D) such sale would circumvent or violate any provision of this chapter.
(c) Terms and conditions

Any authorization granted under this section shall be under such terms and conditions as the Commission may prescribe.

(Pub. L. 95–621, title III, § 311, Nov. 9, 1978, 92 Stat. 3388.)Editorial NotesReferences in Text

The Natural Gas Act, referred to in subsec. (a)(1)(B), is act June 21, 1938, ch. 556, 52 Stat. 821, which is classified generally to chapter 15B (§ 717 et seq.) of this title. For complete classification of this act to the Code, see section 717w of this title and Tables.

The 20 cases that cite 15 U.S.C. § 3371 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENAnr Pipeline Co. v. Fed. Energy Regulatory Comm'n, 71 F.3d 897 (D.C. Cir. 1995).
cites § 3371 4×cited by 50 cases
Where it cites § 3371
“” 15 U.S.C. § 3371 (a)(2)(A), (B)(i). Thereafter, in Order No.”
The case’s holding
An agency must provide a reasoned explanation when treating similar situations differently or departing from established precedent to avoid being arbitrary and capricious.
Later courts cite it for
“where an agency departs from established precedent without a reasoned explanation, its decision will be vacated as arbitrary and capricious.” · 13 citing courts
cites § 3371 2×cited by 98 cases
Where it cites § 3371
“…since it granted FERC jurisdiction over the intrastate market for the first time. See the Act's §§ 311 and 312, 15 U. S. C. §§ 3371 and 3372. Appellees argue, however, that §§ 601(a)(1)(B)(i) and (ii), 15 U. S. C. §§ 3431 (a)(1)(B)(i) and (ii), stripped FERC of…”
The case’s holding
A federal decision to forgo regulation in a specific area may imply an authoritative determination that the area is best left unregulated and carries preemptive force (federal preemption).
Later courts cite it for
“the aim of federal regulation remains to assure adequate supplies of natural gas at fair prices.” · 5 citing courts
3
GREENCity of Clarksville v. Fed. Energy Regulatory Comm'n, 888 F.3d 477 (D.C. Cir. 2018).
cites § 3371 1×cited by 32 cases
Where it cites § 3371
“FERC also declared that should Clarksville desire to transport natural gas in interstate commerce in the same manner as an intrastate pipeline may under section 311 of the Natural Gas Policy Act ("NGPA"), 15 U.S.C. § 3371 , it would be required to obtain a different certificate…”
Later courts cite it for
“in addressing a question of statutory interpretation, we begin with the text.” · 8 citing courts
4
GREENTenneco, Inc. ex rel. Tennessee Gas Pipeline Co. v. Sutton, 530 F. Supp. 411 (M.D. La. 1981).
cites § 3371 6×cited by 7 cases
Where it cites § 3371
“44 Sales authorized under 15 U.S.C. § 3371 (b) are limited to a period of two years and are subject to interruption by the seller or termination by FERC.”
cites § 3371 1×cited by 75 cases
Where it cites § 3371
“But where Congress has exercised its authority under the Commerce Clause to regulate intrastate shipments of gas, 15 U.S.C. § 3371 (a) & (b), we may presume the commerce is under regulation by Congress.”
The case’s holding
An arbitration provision remains enforceable under the Federal Arbitration Act if it is not invalid separately from the underlying contract.
Later courts cite it for
“invalid separately from the entire contract” · 2 citing courts
cites § 3371 1×cited by 39 cases
Where it cites § 3371
“As we are led to understand, Rate Schedule T-6 embodied Northwest’s transportation rate for services rendered pursuant to section 311 of the Natural Gas Policy Act of 1978, 15 U.S.C. § 3371 (1982). Northwest describes its T-6 rate in the following way: “Northwest filed its Rate…”
The case’s holding
A party must raise a request for retroactive rate relief before the Commission to satisfy the statutory requirement for exhaustion of administrative remedies.
Later courts cite it for
“is to afford the commission an opportunity to bring its knowledge and expertise to bear on an issue before it is presented to a generalist court.” · 5 citing courts
cites § 3371 1×cited by 34 cases
Where it cites § 3371
“3(c) of the regulations provides automatic authorization for the construction of facilities to be used for the transportation of natural gas pursuant to section 311 of the Natural Gas Policy Act of 1978, 15 U.S.C. § 3371 (1988). See 18 C.F.R. § 284 .”
The case’s holding
An agency must provide a factual basis for its predictions of regulatory avoidance to justify using the good cause exception to notice and comment requirements.
Later courts cite it for
“provided little factual basis for its belief that pipelines would seek to avoid the future rule by rushing new construction and replacements with attendant damage to the environment.” · 3 citing courts
cites § 3371 1×cited by 6 cases
Where it cites § 3371
“15 U.S.C. § 3371 (a)(2). Such authorized transportation is exempt from "the jurisdiction of the Commission" under the Natural Gas Act.”
Later courts cite it for
“does not require the aggregation of federal and non-federal actions.” · 2 citing courts
9
NO FLAGCity of Chanute v. Williams Nat. Gas Co., 955 F.2d 641 (10th Cir. 1992).
cites § 3371 2×cited by 52 cases
Where it cites § 3371
“Williams initiated this interim open-access program pursuant to § 311 of the Natural Gas Policy Act, 15 U.S.C. § 3371 (1978). . Williams had take-or-pay provisions in its contracts with natural gas suppliers.”
10
GREENUnited Gas Pipe Line Co. v. Fed. Energy Regulatory Comm'n, 707 F.2d 1507 (D.C. Cir. 1983).
cites § 3371 1×cited by 19 cases
Later courts cite it for
“must show that the agency acted arbitrarily by failing to give 'meaningful consideration' to the application.” · 2 citing courts
11
REDLone Star Gas Co. v. R.R. Comm'n of Texas, 798 S.W.2d 888 (Tex. App.—Austin 1990).
cites § 3371 2×subsections: (a)(2)cited by 6 cases
Reversed by Railroad Com'n of Texas v. Lone Star Gas Co. (1992): the Texas Supreme Court's own opinion in this case.
Later courts cite it for
“the spot market price of gas is much lower than the long-term contract price.” · 1 citing court
12
GREENLaclede Gas Co. v. Fed. Energy Regulatory Comm'n, 670 F.2d 38 (5th Cir. 1982).
cites § 3371 1×cited by 13 cases
Where it cites § 3371
“Specifically, Laclede refers to United’s purchase of expensive gas under §§311 and 312 of the Natural Gas Policy Act, 15 U.S.C. §§ 3371 , 3372 (Supp. II 1978).”
Later courts cite it for
“an integral part of the manner in which rates are charged” · 2 citing courts
13
NO FLAGCity of Chanute v. Williams Nat. Gas Co., 31 F.3d 1041 (10th Cir. 1994).
cites § 3371 1×cited by 101 cases
Where it cites § 3371
“2 While awaiting FERC approval, Williams initiated a temporary open access program to transport third-party gas for the cities pursuant to § 311 of the Natural Gas Policy Act, 15 U.S.C. § 3371 (1978). The cities began to negotiate and enter into agreements for gas from…”
14
GREENMustang Energy Corp. v. Fed. Energy Regulatory Comm'n, 859 F.2d 1447 (10th Cir. 1988).
cites § 3371 2×cited by 4 cases
Where it cites § 3371
“15 U.S.C. § 3371 (a)(2). At issue here is FERC’s determination of “fair and equitable” rates for transportation service under the NGPA.”
Later courts cite it for
“unnecessarily shifts most of the risk of underutilization ... to the intrastate pipeline.” · 2 citing courts
15
NEUTRALAm. Gas Ass'n v. Fed. Energy Regulatory Comm'n, 888 F.2d 136 (D.C. Cir. 1989).
cites § 3371 2×cited by 29 cases
Where it cites § 3371
“They argue further that § 311 of the Natural Gas Policy Act, 15 U.S.C. § 3371 , does not provide authority for the crediting mechanism because conditioning works against the purpose of that statute to promote reliance upon market forces in pricing gas.”
16
GREENLaclede Gas Co. v. Fed. Energy Regulatory Comm'n, 722 F.2d 272 (5th Cir. 1984).
cites § 3371 1×cited by 8 cases
Where it cites § 3371
“THORNBERRY, Circuit Judge: The question presented in this case is whether United Gas Pipe Line Company (“United”) may “roll-in” to all of its sales the cost of natural gas purchased under Sections 311(b) and 312 (“Sections 311 and 312”) of the Natural Gas Policy Act of 1978…”
Later courts cite it for
“an agency must either conform to its prior precedent or explain its reasoning for departure from that precedent.” · 2 citing courts
17
GREENCity of Chanute, Kan. v. Williams Nat. Gas Co., 678 F. Supp. 1517 (D. Kan. 1988).
cites § 3371 1×cited by 8 cases
Where it cites § 3371
“§ 717f, or (2) actually provides transportation under § 311 of the NGPA, 15 U.S.C. § 3371 . It further provides that if a pipeline holds itself out as a transporter of gas for others, the pipeline’s LDC customers then have an opportunity to convert their existing contract demand…”
Later courts cite it for
“established procedures for the renegotiation of low, old, pre-ngpa gas prices and the release of gas covered by such pre-ngpa gas purchase contracts.” · 2 citing courts
18
GREENETC Mktg., Ltd. v. Harris Cnty. Appraisal Dist., 476 S.W.3d 501 (Tex. App.—Houston [1st Dist.] 2015).
cites § 3371 1×cited by 4 cases
Where it cites § 3371
“§ 717 ; 15 U.S.C. § 3371 (Natural Gas Policy Act of 1978, § 311).”
Later courts cite it for
“etc marketing had offices and employees in harris county and elsewhere in the state of texas.” · 2 citing courts
cites § 3371 6×cited by 3 cases
Where it cites § 3371
“…pursuant to § 7 of the NGA, 15 U.S.C. § 717f (1982), or (2) actually provides transportation under § 311 of the NGPA, 15 U.S.C. § 3371 (1982). See 18 C.F.R. §§ 284.8 (b), 284.9(b). 3 Several pipelines and others attack these conditions as beyond the scope of the Commission’s…”
Later courts cite it for
“agencies do not need to conduct experiments in order to rely on the prediction that an unsupported stone will fall, nor need they do so for predictions that competition will normally lead to lower prices.” · 6 citing courts
cites § 3371 1×cited by 3 cases
Where it cites § 3371
“15 U.S.C. § 3371 (1982) (“Section 311”). The firm shippers continued to pay 100 percent of Ozark’s fixed costs, and thus the interrupti-ble shippers paid only the commodity rate.”

Show all 36 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
198120032025

One bar per year. Tallest: 4 cases in 1988. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
D.C. Cir.2210th Cir.45th Cir.3Tex. App.29th Cir.1D. Idaho1D. Kan.1M.D. La.1

The 8 courts with the most citing cases, of 9 courts in all.

By subsection
(a)(2)1 case
Lone Star Gas Co. v. R.R. Comm'n of Texas, 798 S.W.2d 888 (Tex. App.—Austin 1990).

Show all 36 citing cases (list view) →

Enactment and amendments
(Pub. L. 95–621, title III, § 311, Nov. 9, 1978, 92 Stat. 3388.)