15 U.S.C. § 717n (2026)
Process coordination; hearings; rules of procedure
Edition and currency
Other sources
Courts have cited this section in 53 opinions since 1945, 9 of them in the last five years. The most litigated part is subsection (a) (11 cases).
The Commission shall act as the lead agency for the purposes of coordinating all applicable Federal authorizations and for the purposes of complying with the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.).
Each Federal and State agency considering an aspect of an application for Federal authorization shall cooperate with the Commission and comply with the deadlines established by the Commission.
If a Federal or State administrative agency does not complete a proceeding for an approval that is required for a Federal authorization in accordance with the schedule established by the Commission, the applicant may pursue remedies under section 717r(d) of this title.
Hearings under this chapter may be held before the Commission, any member or members thereof, or any representative of the Commission designated by it, and appropriate records thereof shall be kept. In any proceeding before it, the Commission in accordance with such rules and regulations as it may prescribe, may admit as a party any interested State, State commission, municipality or any representative of interested consumers or security holders, or any competitor of a party to such proceeding, or any other person whose participation in the proceeding may be in the public interest.
All hearings, investigations, and proceedings under this chapter shall be governed by rules of practice and procedure to be adopted by the Commission, and in the conduct thereof the technical rules of evidence need not be applied. No informality in any hearing, investigation, or proceeding or in the manner of taking testimony shall invalidate any order, decision, rule, or regulation issued under the authority of this chapter.
The National Environmental Policy Act of 1969, referred to in subsec. (b)(1), is Pub. L. 91–190,
The Coastal Zone Management Act of 1972, referred to in subsec. (d)(1), is title III of Pub. L. 89–454, as added by Pub. L. 92–583,
2005—Pub. L. 109–58 substituted “Process coordination; hearings; rules of procedure” for “Hearings; rules of procedure” in section catchline, added subsecs. (a) to (d), and redesignated former subsecs. (a) and (b) as (e) and (f), respectively.
- The case’s holding
- An agency need not address downstream environmental effects if the chain of events leading to those effects requires a critical intervening action by another agency.
- Later courts cite it for
- “cannot be considered a legally relevant cause of the effect for nepa purposes.” · 2 citing courts
- Where it cites § 717n
- “§ 717t-1; see also NGA § 15, 15 U.S.C. § 717n. Even assuming that Total is correct in its argument that it is entitled to de novo review of the penalty assessment in district court, no penalty can be said to have been “assessed” until the conclusion of all FERC proceedings.”
- Where it cites § 717n
- “" 15 U.S.C. § 717n. On October 13, 2017, FERC issued ACP a certificate of public convenience and necessity that authorized the construction and operation of the pipeline.”
- The case’s holding
- An agency decision is arbitrary and capricious if the agency fails to consider an important aspect of the problem or offers an explanation that runs counter to the evidence.
- Later courts cite it for
- “the causation element of standing does not require the challenged action to be the sole or even immediate cause of the injury.” · 14 citing courts
- Where it cites § 717n
- “15 U.S.C. § 717n(b)(1). The FERC docket serves as a central conduit and repository for information requests and responses and is the foundation for the consolidated record for petitions for review, such as this one, concerning water quality certifications under the Clean Water…”
- Later courts cite it for
- “we owe deference to the bia's interpretation of its own regulations, and the bia's interpretation will be 'controlling unless plainly errone- ous or inconsistent with the regulation.” · 2 citing courts
- Where it cites § 717n
- “FERC serves as the "lead agency," coordinating the needed governmental authorizations, see 15 U.S.C. § 717n(b), including the one central to this case, Virginia's state water-quality certification under the Clean Water Act ("CWA").”
- Later courts cite it for
- “a likelihood of ultimate relief” · 2 citing courts
- Where it cites § 717n
- “2018) (quoting 15 U.S.C. § 717n(a)(1), (2) ). As the lead agency, FERC is responsible for coordinating all applicable federal authorizations.”
- Later courts cite it for
- “will vacate agency action if it is not 'based on a consideration of the relevant factors' or where 'there has been a clear error of judgment.” · 3 citing courts
- The case’s holding
- State water quality certifications issued under the Clean Water Act are actions taken pursuant to federal law and are subject to judicial review under the Natural Gas Act.
- Later courts cite it for
- “mistakes that have no bearing on the substantive decision of an agency do not prejudice a party.” · 5 citing courts
- The case’s holding
- An agency is not required under NEPA to consider indirect environmental effects that fall under the regulatory authority of a different agency.
- Later courts cite it for
- “significant variation in output” · 2 citing courts
- Where it cites § 717n
- “at 689, codified at 15 U.S.C. § 717n(b)(l). It required FERC to promulgate regulations for NEPA compliance that require a pre-filing of LNG import terminal siting applications.”
- Later courts cite it for
- “courts consider whether the practical effects of an agency's decision make it a final agency action, regardless of how it is labeled.” · 5 citing courts
- Where it cites § 717n
- “Purported Un-Reviewability Based on § 717n PADEP’s theory of obstacle preemption rests on a different codified provision of the Natural Gas Act, 15 U.S.C. § 717n, which imposes an obligation on FERC to prepare an administrative record for “Federal authorization[s],” as that term…”
- The case’s holding
- The Natural Gas Act does not preempt state administrative review before a state board of Clean Water Act permits issued for interstate natural gas pipeline projects, so such state appeals may proceed.
- Later courts cite it for
- “an ehb disposition of such an administrative appeal would be within the 'pursuant to federal law' requirement and subject to review through a civil action in the third circuit, leaving no obstacle to that purpose of the nga.” · 4 citing courts
- Where it cites § 717n
- “15 U.S.C. § 717n(b). As a condition of FERC approval, the applicant is required to obtain any other state or federal licenses required by law.”
- The case’s holding
- A state agency's reasonable interpretation of its own water-dependency regulation that incorporates an alternatives analysis is not arbitrary or capricious.
- The case’s holding
- An agency action is arbitrary and capricious if the agency fails to articulate a rational connection between the facts found and the choice made.
- Later courts cite it for
- “we may hold unlawful and set aside a federal agency action for certain specified reasons, including whenever the challenged act is arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with the law.” · 5 citing courts
- Where it cites § 717n
- “Here, FERC was the “lead agency” for the purposes of complying with NEPA, see 15 U.S.C. § 717n(b)(1), and the Department acted as a “cooperating agency,” 40 C.”
- The case’s holding
- An agency need not quantify environmental effects that are too speculative to inform its decision, and it satisfies NEPA by reasonably explaining why more granular analysis would be speculative, unhelpful, or infeasible.
- Later courts cite it for
- “in determining what effects are 'reasonably foreseeable,' an agency must engage in 'reasonable forecasting and speculation,' with reasonable being the operative word.” · 2 citing courts
- Where it cites § 717n
- “See 15 U.S.C. § 717n(b). Because the pipeline project involves the discharge of fill and dredged materials into waterways and wetlands, Atlantic needed to obtain not only a certificate of public convenience and necessity from FERC, but also a Section 404 CWA authorization from…”
- Later courts cite it for
- “to survive review under the arbitrary and capricious standard, an agency decision must show that the agency examined 'the relevant data and articulated a satisfactory explanation for its action including a 'rational connection between the facts found and the choice made.” · 4 citing courts
- Where it cites § 717n
- “15 U.S.C. § 717n(b). Additionally, Congress provided for expedited judicial review of federal or state agency action or inaction that deprives a company building a FERC-certified natural gas facility of an authorization it requires to proceed with construction.”
- The case’s holding
- Under the Natural Gas Act, state air quality requirements saved by the Clean Air Act and incorporated into an approved state implementation plan are not preempted, even for federally certificated facilities.
- Later courts cite it for
- “congress intended to occupy the field to the exclusion of state law by establishing through the nga a comprehensive scheme of federal regulation of all wholesales of natural gas in interstate commerce.” · 5 citing courts
- Where it cites § 717n
- “Consequently, in my opinion, the petitioners aré not “parties aggrieved” Within the meaning of Section 19(b) of the Natural Gas Act, supra, and have no standing to maintain this petition.”
- The case’s holding
- Competitors threatened with financial loss through increased competition resulting from an administrative order are aggrieved parties entitled to judicial review under the Natural Gas Act.
- Where it cites § 717n
- “The Natural Gas Act requires state agencies to “comply with the deadlines established by the Commission,” 15 U.S.C. § 717n(b)(2), and if a state agency exceeds FERC’s deadline, the applicant could pursue remedies under section 19(d), id.”
- Where it cites § 717n
- “43 Although the pipeline at issue here is located entirely within New York and will deliver gas only to the Valley Energy Center, it will receive out-of-state gas from the Millennium mainline.”
- The case’s holding
- A federal court lacks jurisdiction to adjudicate the rights of consumers to a fund involving local rate adjustments when such regulation is a legislative function of the state.
- Where it cites § 717n
- “15 U.S.C. § 717n(a). The Act defines “municipality” as “a city, county, or other political subdivision or agency of a State,” 15 U.”
- The case’s holding
- A state may sue the federal government as parens patriae where Congress expressly confers party or review status on states, since the parens patriae bar is prudential, not constitutional.
Show all 53 citing cases (list view) →
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
One bar per 2 years. Tallest: 10 cases in 2016–2017. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.
The 8 courts with the most citing cases, of 16 courts in all.
(a)11 cases
(a)(1)3 cases
(b)6 cases
(b)(1)11 cases
(b)(2)1 case
(c)1 case
(d)1 case
(d)(2)1 case
(e)4 cases
Amendment years (notes): 2005
Edition shown: U.S. Code current through Pub. L. 119-102 (OLRC release point). Syfert holds no earlier or later version of this section.