U.S.C. homeSearch U.S. Code
U.S. CodeTitle 42Chapter 103— Comprehensive Environmental Response, Compensation, And LiabilitySubchapter I— Hazardous Substances Releases, Liability, Compensation

42 U.S.C. § 9616 (2026)

Schedules

Edition and currency
U.S. Code current through Pub. L. 119-102 (OLRC release point). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTU.S. Code current through Pub. L. 119-102 (OLRC release point) cited 1989–2021 8citing cases
At a glance

Courts have cited this section in 8 opinions since 1989, 1 of them in the last five years.

(a) Assessment and listing of facilitiesIt shall be a goal of this chapter that, to the maximum extent practicable—(1) not later than January 1, 1988, the President shall complete preliminary assessments of all facilities that are contained (as of October 17, 1986) on the Comprehensive Environmental Response, Compensation, and Liability Information System (CERCLIS) including in each assessment a statement as to whether a site inspection is necessary and by whom it should be carried out; and(2) not later than January 1, 1989, the President shall assure the completion of site inspections at all facilities for which the President has stated a site inspection is necessary pursuant to paragraph (1).(b) Evaluation

Within 4 years after October 17, 1986, each facility listed (as of October 17, 1986) in the CERCLIS shall be evaluated if the President determines that such evaluation is warranted on the basis of a site inspection or preliminary assessment. The evaluation shall be in accordance with the criteria established in section 9605 of this title under the National Contingency Plan for determining priorities among release for inclusion on the National Priorities List. In the case of a facility listed in the CERCLIS after October 17, 1986, the facility shall be evaluated within 4 years after the date of such listing if the President determines that such evaluation is warranted on the basis of a site inspection or preliminary assessment.

(c) Explanations

If any of the goals established by subsection (a) or (b) are not achieved, the President shall publish an explanation of why such action could not be completed by the specified date.

(d) Commencement of RI/FSThe President shall assure that remedial investigations and feasibility studies (RI/FS) are commenced for facilities listed on the National Priorities List, in addition to those commenced prior to October 17, 1986, in accordance with the following schedule:(1) not fewer than 275 by the date 36 months after October 17, 1986, and(2) if the requirement of paragraph (1) is not met, not fewer than an additional 175 by the date 4 years after October 17, 1986, an additional 200 by the date 5 years after October 17, 1986, and a total of 650 by the date 5 years after October 17, 1986.(e) Commencement of remedial actionThe President shall assure that substantial and continuous physical on-site remedial action commences at facilities on the National Priorities List, in addition to those facilities on which remedial action has commenced prior to October 17, 1986, at a rate not fewer than:(1) 175 facilities during the first 36-month period after October 17, 1986; and(2) 200 additional facilities during the following 24 months after such 36-month period.(Pub. L. 96–510, title I, § 116, as added Pub. L. 99–499, title I, § 116, Oct. 17, 1986, 100 Stat. 1653.)Editorial NotesReferences in Text

This chapter, referred to in subsec. (a), was in the original “this Act”, meaning Pub. L. 96–510, Dec. 11, 1980, 94 Stat. 2767, known as the Comprehensive Environmental Response, Compensation, and Liability Act of 1980, which is classified principally to this chapter. For complete classification of this Act to the Code, see Short Title note set out under section 9601 of this title and Tables.

The 8 cases that cite 42 U.S.C. § 9616 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENFrey v. Env't Prot. Agency, 751 F.3d 461 (7th Cir. 2014).
cites § 9616 2×cited by 15 cases
Where it cites § 9616
“See 42 U.S.C. § 9616 (requiring commencement of RI/FS for pre-1986 National Priorities List sites); 40 C.”
Later courts cite it for
“information a judge has gleaned from prior judicial proceedings is not considered extrajudi- cial and simply does not require recusal.” · 2 citing courts
2
GREENIn re Nat'l Gypsum Co., 139 B.R. 397 (N.D. Tex. 1992).
cites § 9616 1×cited by 89 cases
Where it cites § 9616
“See 42 U.S.C. § 9616 . Congress has further required that the relevant government agency move diligently with remedial investigation and feasibility studies for the purpose of assessing and responding to natural resource damages.”
The case’s holding
A claim exists if the relationship between the debtor and creditor contains all elements necessary to give rise to a legal obligation under non-bankruptcy law before the petition date.
Later courts cite it for
“a claim exists only if before the filing of the bankruptcy petition, the relationship between the debtor and the creditor contained all. of the elements necessary to give rise to a legal obligation - 'a fight to payment' - under the relevant non-bankruptcy law.” · 10 citing courts
3
GREENUnited States v. M. Genzale Plating, Inc., 723 F. Supp. 877 (E.D.N.Y. 1989).
cites § 9616 2×cited by 9 cases
Where it cites § 9616
“After a site has been formally included on the NPL, CERCLA and regulations promulgated pursuant to the act provide for certain steps to be taken in order to restore NPL sites to acceptable environmental standards.”
Later courts cite it for
“vague assertions of unfairness on the part of the government, without more, cannot be molded into constitutional violations” · 4 citing courts
4
GREENUnited States v. Nicolet, Inc., 712 F. Supp. 1193 (E.D. Pa. 1989).
cites § 9616 1×cited by 28 cases
Where it cites § 9616
“Subsequently, the United States, pursuant to Section 116(d) of CERCLA, 42 U.S.C. § 9616 (d), conducted a remedial investigation/feasibility study for the site, and published a Record of Decision for the site on September 30, 1988.”
Later courts cite it for
“before a secured creditor ... may be held liable, it must, at a minimum, participate in the day-to-day operational aspects of the site. here, the creditor ... merely foreclosed on the property after all operations had ceased and thereafter took prudent and routine steps to secure the property against further depreciation.” · 2 citing courts
5
GREENUnited States v. Akzo Coatings of Am., Inc., 719 F. Supp. 571 (E.D. Mich. 1989).
cites § 9616 1×cited by 9 cases
Where it cites § 9616
“42 U.S.C. § 9616 (d). In June, 1987, the MDNR concluded the RI/FS for the Rose Township site, which the state agency conducted pursuant to a cooperative agreement with the EPA.”
Later courts cite it for
“the potential dangers of dust and ash exposure that are associated with soil incineration.” · 2 citing courts
6
GREENJach v. Am. Univ., 245 F. Supp. 2d 110 (D.D.C. 2003).
cites § 9616 1×cited by 4 cases
Where it cites § 9616
“) Pursuant to its responsibilities under CERCLA, 42 U.S.C. § 9616 , the Corps is proceeding at this time with cleanup activities in Spring Valley, including removal actions and the selection of a final remedy.”
7
NEUTRALFrey v. United States Env't Prot. Agency, 937 F. Supp. 2d 964 (S.D. Ind. 2013).
cites § 9616 1×cited by 1 case
Where it cites § 9616
“” 42 U.S.C. § 9616 (d). CERCLA does not define nor describe what should be included in an RI/FS.”
8
NO FLAGEnv't Def. Fund v. U.S. Env't Prot. Agency, 515 F. Supp. 3d 1135 (D. Mont. 2021).
cites § 9616 1×cited by 0 casesunknown
Where it cites § 9616
“§§ 6912 (a)(1), 6979; Comprehensive Environmental Response, Compensation, and Liability Act (“CERCLA”), 42 U.S.C. §§ 9616 , 9660; EPCRA, 42 U.S.C.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
198920052021

One bar per year. Tallest: 3 cases in 1989. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
7th Cir.1D.D.C.1S.D. Ind.1E.D. Mich.1D. Mont.1E.D.N.Y1E.D. Pa.1N.D. Tex.1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments
(Pub. L. 96–510, title I, § 116, as added Pub. L. 99–499, title I, § 116, Oct. 17, 1986, 100 Stat. 1653.)
Versions

Edition shown: U.S. Code current through Pub. L. 119-102 (OLRC release point). Syfert holds no earlier or later version of this section.

U.S.C. Home  |  Search U.S. Code  |  Search cases for this section  |  syfert.com