Vermont Statutes Annotated

Vt. Stat. Ann. tit. 09, § 4003 (2026)

Contractor’s and subcontractor’s payment obligations

✓ current as of May 2026
Find cases: SyfertCases citing this section VT-LEGlegislature.vermont.gov JustiaTitle on Justia CornellLII Search CasesGoogle Scholar
(Cite as: 9 V.S.A. § 4003)
Notes of Decisions
Cited in 2 cases, 2005–2019 · leading case: Fletcher Hill, Inc. v. Crosbie, 872 A.2d 292 (Vt. 2005).
Fletcher Hill, Inc. v. Crosbie, 872 A.2d 292 (Vt. 2005). “See also 9 V.S.A. § 4003(d) (setting interest rate for late payments owed by contractor to subcontractor at the 12% annual rate established by 12 V.”
J & K Tile Co., 211 VT 179 (Vt. 2019). “” It further found that the general contractor cured the violation in its January 27 letter, which agreed that J & K Tile Co.”
Vt. Stat. Ann. tit. 09, § 4003(d): 2 cases
Fletcher Hill, Inc. v. Crosbie, 872 A.2d 292 (Vt. 2005). “See also 9 V.S.A. § 4003(d) (setting interest rate for late payments owed by contractor to subcontractor at the 12% annual rate established by 12 V.”
J & K Tile Co., 211 VT 179 (Vt. 2019). “” It further found that the general contractor cured the violation in its January 27 letter, which agreed that J & K Tile Co.”