Wash. Rev. Code § 19.28.131 (2025)
Specialty electrical contractor license—Written warning, penalty—Violations of RCW 19.28.010 through 19.28.141 and 19.28.311 through 19.28.361—Schedule of penalties—Appeal
Edition and currency
Other sources
Courts have cited this section in 4 opinions since 2012, 1 of them in the last five years.
Notes:
- Where it cites § 19.28.131
- “Because his interest is solely an economic one, RCW 19.28.131’s monetary prerequisite to an appeal does not violate his due process rights.”
- Later courts cite it for
- “an essential principle of due process is the right to notice and a meaningful opportunity to be heard.” · 1 citing court
- Where it cites § 19.28.131
- “131, that L&I procedure violated due process, and that L&I was estopped from denying his appeal.”
- Where it cites § 19.28.131
- “261(6) precludes the Department from citing MTC.”
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
One bar per year. Tallest: 2 cases in 2012. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.
Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.
Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.
Edition shown: laws through the 2025 session: 2026 session laws are not yet included. Syfert holds no earlier or later version of this section.