Revised Code of Washington homeSearch Washington
Wash. Rev. CodeTitle 39Chapter 39.12

Wash. Rev. Code § 39.12.065 (2025)

Investigation of complaints—Notice of violation—Hearing—Exception—Remedies—Penalties—Waiver or reduction

Edition and currency
laws through the 2025 session: 2026 session laws are not yet included. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTlaws through the 2025 session: 2026 session laws are not yet included cited 1987–2026 19citing cases
At a glance

Courts have cited this section in 19 opinions since 1987, 3 of them in the last five years. The most litigated part is subsection (1) (11 cases).

The 19 cases that cite Wash. Rev. Code § 39.12.065 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENSilverstreak, Inc. v. STATE DEPT. OF LABOR, 154 P.3d 891 (Wash. 2007).
cites § 39.12.065 2×subsections: (1)cited by 97 cases
Where it cites § 39.12.065
“See RCW 39.12.065. ¶ 57 The truck drivers in this case were workers upon a public works project who participated in the incorporation of fill material into the third runway embankment.”
The case’s holding
Equitable estoppel prevents a party from taking a position inconsistent with a previous one if a party has justifiably and in good faith relied on that position to its detriment.
Later courts cite it for
“equitable estoppel prevents a party from taking a position inconsistent with a previous one where inequitable consequences would result to a party who has justifiably and in good faith relied.” · 4 citing courts
2
GREENSilverstreak, Inc. v. Dep't of Labor & Indus., 159 Wash. 2d 868 (2007).
cites § 39.12.065 2×subsections: (1)cited by 96 cases
Where it cites § 39.12.065
“See RCW 39.12.065. ¶56 The truck drivers in this case were workers upon a public works project who participated in the incorporation of fill material into the third runway embankment.”
3
GREENCom. v. Goodco Mech., Inc., 291 A.3d 378, 2023 PA Super 32 (Pa. Super. Ct. 2023).
cites § 39.12.065 2×cited by 17 cases
Where it cites § 39.12.065
“§ 2258; and Washington, Wash. Rev. Code § 39.12.065 . For New Mexico, they cite an administrative provision, N.”
4
GREENInt'l Com. Collectors, Inc. v. Mazel Co., 740 P.2d 363 (Wash. Ct. App. 1987).
cites § 39.12.065 4×subsections: (2) 2×cited by 11 cases
Where it cites § 39.12.065
“The Department of Labor and Industries brought suit on behalf of the laborers and obtained a judgment against Mazel for the wage discrepancy pursuant to RCW 39.12.065. 1 To clear up outstanding claims on the project so the retainage would be released, M.”
Later courts cite it for
“in private projects rather than the materialmen, laborers or contractors being relegated to actions against their employers or contractors, another remedy is provided by giving a lien to those entitled to one against the property itself-which means in effect against the owner of the property who, however, may not have contracted with any of the parties entitled to a lien.” · 1 citing court
5
GREENSuperior Asphalt & Concrete Co. v. Dep't of Labor & Indus., 49 P.3d 135 (Wash. Ct. App. 2002).
cites § 39.12.065 1×subsections: (1)cited by 45 cases
Where it cites § 39.12.065
“They appeal the superior court’s ruling affirming the director’s decision upholding the ALJ’s determination as to the drivers’ types of activity and their corresponding wage rates. ANALYSIS Standard of Review An appeal from an L&I notice of violation of the Prevailing Wage Act…”
The case’s holding
Truck drivers are entitled to prevailing wage compensation for their entire delivery cycle, including loading and driving time, if their delivery methods incorporate materials into a public works project.
Later courts cite it for
“in reviewing an administrative action, we sit in the same position as the trial court and apply the apa standards directly to the administrative record.” · 2 citing courts
6
GREENSuperior Asphalt & Concrete Co. v. L&I, 49 P.3d 135 (Wash. Ct. App. 2002).
cites § 39.12.065 1×subsections: (1)cited by 40 cases
Where it cites § 39.12.065
“They appeal the superior court's ruling affirming the director's decision upholding the ALJ's determination as to the drivers' types of activity and their corresponding wage rates.”
7
GREENSilverstreak, Inc. v. STATE, DEPT. OF L & I, 104 P.3d 699 (Wash. Ct. App. 2005).
cites § 39.12.065 2×subsections: (1) 2×cited by 6 cases
Where it cites § 39.12.065
“[5] Office of Director of Administrative Hearings for the Department of Labor & Industries Proposed Finding of Fact 5 of Director's Order, Administrative Record at 3342. [6] Office of Administrative Hearings for the Department of Labor & Industries Proposed Finding of Fact 5 of…”
Later courts cite it for
“while we acknowledge the remedial purposes of the prevailing wage statute and the liberal construction we must give such a statute, we cannot ignore the plain words of the regulation in effectuating the underlying purposes of the regulation.” · 2 citing courts
8
GREENSilverstreak, Inc. v. Dep't of Labor & Indus., 125 Wash. App. 202 (Wash. Ct. App. 2005).
cites § 39.12.065 2×subsections: (1) 2×cited by 6 cases
Where it cites § 39.12.065
“Hr’gs for the Dep’t of Labor & Indus. Proposed Finding of Fact 5 of Dir’s Order, Admin.”
9
NEUTRALD.W. Close Co. v. Dep't of Labor & Indus., 143 Wash. App. 118 (Wash. Ct. App. 2008).
cites § 39.12.065 3×subsections: (1) 3×cited by 29 cases
Where it cites § 39.12.065
“” RCW 39.12.065(1). “Interested party” is defined as “a contractor, subcontractor, an employee of a contractor or subcontractor, an organization whose members’ wages, benefits, and conditions of employment are affected by this chapter, and the director of labor and industries or…”
The case’s holding
Under prevailing wage regulations, an agency's interpretation of an ambiguous scope-of-work rule receives substantial weight, and the electronic technician scope does not cover conduit pulls longer than ten feet.
Later courts cite it for
“the appellate court may substitute its interpretation for that of the agency . . . but, we must 'accord substantial weight to the agency interpretation.” · 2 citing courts
10
NEUTRALDw Close Co. v. Dept. of Labor & Indus., 177 P.3d 143 (Wash. Ct. App. 2008).
cites § 39.12.065 3×subsections: (1) 3×cited by 26 cases
Where it cites § 39.12.065
“" RCW 39.12.065(1). "Interested party" is defined as "a contractor, subcontractor, an employee of a contractor or subcontractor, an organization whose members' wages, benefits, and conditions of employment are affected by this chapter, and the director of labor and industries or…”
11
GREENIronworkers Dist. Council v. Woodland Park Zoo Plan. & Dev., 942 P.2d 1054 (Wash. Ct. App. 1997).
cites § 39.12.065 2×subsections: (1) (2)cited by 6 cases
Where it cites § 39.12.065
“RCW 39.12.065(1). We are not convinced that an "interested party” has an independent right of action for unpaid prevailing wages.”
12
GREENHeller v. McClure & Sons, Inc., 963 P.2d 923 (Wash. Ct. App. 1998).
cites § 39.12.065 1×cited by 16 cases
Where it cites § 39.12.065
“2 RCW 39.12.065 states, in relevant part: “A complaint concerning nonpayment of the prevailing rate of wage shall be filed with the department of labor and industries no later than thirty days from the acceptance date of the public works project.”
The case’s holding
Mechanics are entitled to prevailing wages when their work is directly related to the prosecution of the contracted work and necessary for its completion.
Later courts cite it for
“to protect employees working on public projects from substandard wages and . . . to preserve local wages.” · 3 citing courts
13
GREENSupporters of the Ctr., Inc. v. Moore, 80 P.3d 618 (Wash. Ct. App. 2003).
cites § 39.12.065 1×cited by 6 cases
Where it cites § 39.12.065
“RCW 39.12.065, .050. In April 1999, Leone & Keeble, SOC, and L&I agreed that any alleged difference in pay owed to the workers would be placed in an account pending a final determination of the matter.”
14
NO FLAGPenhall Co. v. Dep't of Labor & Indus., No. 40453-6 (Wash. Ct. App. May 19, 2026).
cites § 39.12.065 27×subsections: (3) 10× (1)cited by 0 casesunpublished
Where it cites § 39.12.065
“065(3) (2009) set forth that upon the first strike for a prevailing wage violation, an employer is subject to a civil penalty in the amount “not less than one thousand dollars or an amount equal to twenty percent of the total prevailing wage 3 RCW 39.12.065 was amended in 2019,…”
15
NEUTRALIronworkers Dist. Council v. Univ. of Washington Bd. of Regents, 970 P.2d 351 (Wash. Ct. App. 1999).
cites § 39.12.065 3×subsections: (1)cited by 7 cases
Where it cites § 39.12.065
“18 The Council also fails to explain why it should not use the administrative remedy provided by RCW 39.12.065. To do so, the Council must show that an interested party is *742 unduly burdened by the administrative process provided by statute or that using those procedures would…”
Later courts cite it for
“an organization does not have standing to invoke the court's remedial powers on behalf of its members where . . . the organization seeks damages and yet alleges neither monetary injury to itself nor assignment of its members' damage claims.” · 2 citing courts
16
NEUTRALLockheed Shipbuilding Co. v. Dep't of Labor & Indus., 783 P.2d 1119 (Wash. Ct. App. 1989).
cites § 39.12.065 3×cited by 7 cases
Where it cites § 39.12.065
“Finally, since RCW 39.12.065 4 specifically provides for judicial review of prevailing wage enforcement actions, we conclude that the Legislature would have provided for judicial review in RCW 39.”
17
NO FLAGGlacier Nw., Inc. v. Wa State Dept. Of Labor & Indus., No. 85660-0 (Wash. Ct. App. Sept. 3, 2024).
cites § 39.12.065 3×cited by 0 cases
Where it cites § 39.12.065
“RCW 39.12.065. And it is this court’s ultimate responsibility to review the applicability of the PWA de novo.”
18
GREENSupporters of Ctr., Inc. v. Moore, 80 P.3d 618 (Wash. Ct. App. 2003).
cites § 39.12.065 1×cited by 1 case
Where it cites § 39.12.065
“RCW 39.12.065; RCW 39.12.050. In April 1999, Leone & Keeble, SOC, and L & I agreed that any alleged difference in pay owed to the workers would be placed in an account pending a final determination of the matter.”
19
NO FLAGMartin v. Johnson Controls Fire Prot. LP, No. 2:19-cv-00514 (W.D. Wash. Aug. 17, 2020).
cites § 39.12.065 2×cited by 0 casesunknown
Where it cites § 39.12.065
“3 Defendant also suggests that a superior alternative to resolving this matter is 4 through the complaint procedures of the Department of Labor & Industries pursuant to 5 RCW 39.12.065. Dkt. # 29 at 24. But as noted by Plaintiff (Dkt.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
198720062026

One bar per year. Tallest: 2 cases in 2002. 2026 is a partial year. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Wash. Ct. App.15Wash.2Pa. Super. Ct.1W.D. Wash.1
By subsection
(1)11 cases
Silverstreak, Inc. v. STATE DEPT. OF LABOR, 154 P.3d 891 (Wash. 2007).“See RCW 39.12.065. ¶ 57 The truck drivers in this case were workers upon a public works project who participated in the incorporation of fill material into the third runway embankment.”
Silverstreak, Inc. v. Dep't of Labor & Indus., 159 Wash. 2d 868 (2007).“See RCW 39.12.065. ¶56 The truck drivers in this case were workers upon a public works project who participated in the incorporation of fill material into the third runway embankment.”
Superior Asphalt & Concrete Co. v. Dep't of Labor & Indus., 49 P.3d 135 (Wash. Ct. App. 2002).“They appeal the superior court’s ruling affirming the director’s decision upholding the ALJ’s determination as to the drivers’ types of activity and their corresponding wage rates. ANALYSIS Standard of Review An appeal from an L&I notice of violation of the Prevailing Wage Act…”
Superior Asphalt & Concrete Co. v. L&I, 49 P.3d 135 (Wash. Ct. App. 2002).“They appeal the superior court's ruling affirming the director's decision upholding the ALJ's determination as to the drivers' types of activity and their corresponding wage rates.”
Silverstreak, Inc. v. STATE, DEPT. OF L & I, 104 P.3d 699 (Wash. Ct. App. 2005).“[5] Office of Director of Administrative Hearings for the Department of Labor & Industries Proposed Finding of Fact 5 of Director's Order, Administrative Record at 3342. [6] Office of Administrative Hearings for the Department of Labor & Industries Proposed Finding of Fact 5 of…”
Showing the top 5 of 11. More in the list view →
(2)2 cases
Int'l Com. Collectors, Inc. v. Mazel Co., 740 P.2d 363 (Wash. Ct. App. 1987).“The Department of Labor and Industries brought suit on behalf of the laborers and obtained a judgment against Mazel for the wage discrepancy pursuant to RCW 39.12.065. 1 To clear up outstanding claims on the project so the retainage would be released, M.”
Ironworkers Dist. Council v. Woodland Park Zoo Plan. & Dev., 942 P.2d 1054 (Wash. Ct. App. 1997).“RCW 39.12.065(1). We are not convinced that an "interested party” has an independent right of action for unpaid prevailing wages.”
(3)1 case
Penhall Co. v. Dep't of Labor & Indus., No. 40453-6 (Wash. Ct. App. May 19, 2026).“065(3) (2009) set forth that upon the first strike for a prevailing wage violation, an employer is subject to a civil penalty in the amount “not less than one thousand dollars or an amount equal to twenty percent of the total prevailing wage 3 RCW 39.12.065 was amended in 2019,…”
Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: laws through the 2025 session: 2026 session laws are not yet included. Syfert holds no earlier or later version of this section.

Revised Code of Washington Home  |  Search Washington  |  Search cases for this section  |  syfert.com