Foreclosure of lien; procedure; parties
✓ current as of July 2026
Find cases:
SyfertCases citing this section
WI-LEGdocs.legis.wisconsin.gov
JustiaChapter on Justia
CornellLII Search
CasesGoogle Scholar
779.09779.09 Foreclosure of lien; procedure; parties. In the foreclosure of liens mentioned in s. 779.01, ch. 846 shall control as far as applicable unless otherwise provided in this subchapter. All persons having filed claims for liens under s. 779.01 may join as plaintiffs, and if any do not join they may be made defendants. All persons having liens subsequent to such lien may be joined as defendants. If any person who is a proper party is not a party to the action the person may, at any time before judgment, be made a defendant, and any person who after the commencement of the action obtains a lien or becomes a purchaser may, at any time before judgment, be made a defendant.
779.09 HistoryHistory: 1973 c. 189 s. 20; Sup. Ct. Order, 67 Wis. 2d 585, 775 (1975); 1975 c. 218; 1979 c. 32 ss. 57, 92 (9); Stats. 1979 s. 779.09.
779.09 AnnotationSection 840.10 (1) (a) imposes the requirement of recording a lis pendens on the plaintiff who files a complaint and on a defendant seeking relief on a counterclaim or a cross-complaint, which contains a legal description of the real estate. A defendant construction lien claimant is not a plaintiff, and no cross-claim is necessary in order for a defendant construction lien claimant to obtain a determination of the amount due it and an order for sale in a lien foreclosure action. There is no logical rationale for imposing the requirements of s. 840.10 (1) (a) on a defendant construction lien claimant because it unnecessarily files a cross-claim seeking relief it is entitled to under ss. 779.09 to 779.11. Carolina Builders Corp. v. Dietzman, 2007 WI App 201, 304 Wis. 2d 773, 739 N.W.2d 53, 06-3180.
Notes of Decisions
Cited in 3
cases, 2002–2015 · leading case: Carolina Builders Corp. v. Dietzman, 2007 WI App 201 (Wis. Ct. App. 2007).
Carolina Builders Corp. v. Dietzman, 2007 WI App 201 (Wis. Ct. App. 2007). “" Wis. Stat. § 779.09 . 13 The appellants also attempt to distinguish First Wis.”
Am. Wood Dryers, Inc. v. Bombardier Capital, Inc., 305 F. Supp. 2d 966 (W.D. Wis. 2002). “2000); see Wis. Stat. § 779.09 . A properly perfected construction lien has priority over an unperfected security interest.”
In re Segebrecht, 536 B.R. 810 (Bankr. E.D. Wis. 2015). “(1) has so filed its claim for hen upon a lot it may foreclose the same by action in the circuit court having jurisdiction thereof, and §§ 779.09, 779.10, 779.11, 779.12 and 779.”
Annotations are extracted automatically from the opinions in the
Syfert caselaw corpus and ranked by authority, recency, and
treatment. Dots show Syfertize treatment of the citing case itself.