liquidated damages clause (California) · Go Syfert
← California issues

liquidated damages clause in California

57 California opinions name it 3 courts 1960–2025 15 in the last five years

The cases below were cited by California courts in a sentence that names this issue. Sides come from how each citing opinion treated the case (Syfertize flag on that citation), so a case can appear on both: that is where the law is contested. A red or yellow chip is the case's own overall treatment.

Followed or applied (32)

CaseFollowedCited
Ridgley v. Topa Thrift & Loan Assn.green
cal · 1998 · cited in 20 California opinions naming this issue, 2002–2025
2 sentences

2025Other relevant considerations in the determination of whether the amount of liquidated damages is so high or so low as to be unreasonable include, but are not limited to, such matters as the relative equality of the bargaining power of the parties, whether the parties were represented by lawyers at the time the contract was made, the anticipation of the parties that proof of actual damages would be costly or inconvenient, the difficulty of proving causation and foreseeability, and whether the liquidated damages provision is included in a form contract.’” (El Centro Mall, LLC v. Payless ShoeSou

2022It also noted, “ ‘A liquidated damages clause will generally be considered unreasonable, and hence unenforceable under section 1671[, subdivision] (b), if it bears no reasonable relationship to the range of actual damages that the parties could have anticipated would flow from a breach.’ ” (Greentree, supra, 163 Cal.App.4th at p. 499 , quoting Ridgley v. Topa Thrift & Loan Assn. (1998) 17 Cal.4th 970, 977 (Ridgley).) The court then held the amount of the judgment entered pursuant to the stipulation “bears no reasonable relationship to the range of actual damages the parties could have anticipa

1220
McGuire v. More-Gas Invistment, LLCgreen
calctapp · 2013 · cited in 5 California opinions naming this issue, 2017–2024
2 sentences

2024(See McGuire, supra, 220 Cal.App.4th at p. 522 [“[A] provision in a contract that appears at first glance to be either a liquidated damages clause or an unenforceable penalty provision may instead merely be a provision that permissibly calls for alternative performance by the obligor”].) The cotenancy provision “clearly reserves to [JJD] the power to make a realistic and rational choice.” (Blank, supra, 11 Cal.3d at p. 971 .) JJD can choose to provide a higher level of service (i.e., a mall with anchor tenants or specified 10 JJD-HOV ELK GROVE, LLC v. JO-ANN STORES, LLC Opinion of the Court by

2022After surveying the law of liquidated damages and Civil Code section 1671, the court stated, “It is important to recognize . . . that a provision in a contract that appears at first glance to be either a liquidated damages clause or an unenforceable penalty provision may instead merely be a provision that permissibly calls for alternative performance by the obligor. ‘A contractual provision that merely provides an option of alternative performance of an obligation does not impose damages and is not subject to section 1671 limitations.’ [Citation.] Thus, notwithstanding the limitations on liqui

35
Greentree Financial Group, Inc. v. Execute Sports, Inc.green
calctapp · 2008 · cited in 10 California opinions naming this issue, 2014–2022
2 sentences

2022It also noted, “ ‘A liquidated damages clause will generally be considered unreasonable, and hence unenforceable under section 1671[, subdivision] (b), if it bears no reasonable relationship to the range of actual damages that the parties could have anticipated would flow from a breach.’ ” (Greentree, supra, 163 Cal.App.4th at p. 499 , quoting Ridgley v. Topa Thrift & Loan Assn. (1998) 17 Cal.4th 970, 977 (Ridgley).) The court then held the amount of the judgment entered pursuant to the stipulation “bears no reasonable relationship to the range of actual damages the parties could have anticipa

2021(See Greentree, supra, at p. 498 [addressing settlement of breach of contract claim based on contract for financial services]; Ridgley, supra, at p. 973 [addressing prepayment fee in loan contract]; see also Vitatech Internat., Inc. v. Sporn (2017) 16 Cal.App.5th 796, 800 [addressing settlement of breach of contract claim].) Finally, BPI contends if we decide, as we do, that Civil Code section 1671 does not apply, BPI would effectively be precluded from challenging the final CWPA, and thus the alleged liquidated damages clause, because the 60- day window to reinstate review had passed by the t

210
Harbor Island Holdings, L.L.C. v. Kimgreen
calctapp · 2003 · cited in 5 California opinions naming this issue, 2008–2020
2 sentences

2019The Stipulated Judgment Is an Unenforceable Penalty As noted above, under section 1671, subdivision (b), "a provision in a contract liquidating the damages for the breach of the contract is valid unless the party seeking to invalidate the provision establishes that the provision was unreasonable under the circumstances existing at the time the contract was made." A liquidated damages clause will generally be considered unreasonable, and hence unenforceable under section 1671 if it "bears no reasonable relationship to the range of actual damages that the parties could have anticipated would flo

2019The Stipulated Judgment Is an Unenforceable Penalty As noted above, under section 1671, subdivision (b), "a provision in a contract liquidating the damages for the breach of the contract is valid unless the party seeking to invalidate the provision establishes that the provision was unreasonable under the circumstances existing at the time the contract was made." A liquidated damages clause will generally be considered unreasonable, and hence unenforceable under section 1671 if it "bears no reasonable relationship to the range of actual damages that the parties could have anticipated would flo

25
Garrett v. Coast & Southern Federal Savings & Loan Ass'ngreen
cal · 1973 · cited in 4 California opinions naming this issue, 1979–2022
2 sentences

2022Sav. & Loan Assn. (1973) 9 Cal.3d 731, 738 [“The party seeking to rely on a liquidated damages clause bears the burden of proof”].) In 1977, the Legislature adopted without change a California Law Revision Commission (the Commission) recommendation that repealed section 1670 and amended section 1671.

2022If these amounts were not then paid, the parties agreed that interest at the higher rate would accrue.’ [Garrett, supra, 9 Cal.3d at p. 737 .] That is precisely the situation here. 3MB failed to pay the ‘balloon’ at maturity and default interest began to accrue.” (3MB, supra, 609 B.R. at pp. 848–849.) Further, FJM Capital’s position that the language of the Loan must govern the result is belied by the language in section 1671 that contains 8 As the 3MB court summarized Thompson: “[D]efault interest following note maturity has long been allowed in California without resort to a liquidated damag

24
Krechuniak v. Noorzoygreen
calctapp · 2017 · cited in 3 California opinions naming this issue, 2017–2025
2 sentences

2025Other relevant considerations in the determination of whether the amount of liquidated damages is so high or so low as to be unreasonable include, but are not limited to, such matters as the relative equality of the bargaining power of the parties, whether the parties were represented by lawyers at the time the contract was made, the anticipation of the parties that proof of actual damages would be costly or inconvenient, the difficulty of proving causation and foreseeability, and whether the liquidated damages provision is included in a form contract.’” (El Centro Mall, LLC v. Payless ShoeSou

2025Other relevant considerations in the determination of whether the amount of liquidated damages is so high or so low as to be unreasonable include, but are not limited to, such matters as the relative equality of the bargaining power of the parties, whether the parties were represented by lawyers at the time the contract was made, the anticipation of the parties that proof of actual damages would be costly or inconvenient, the difficulty of proving causation and foreseeability, and whether the liquidated damages provision is included in a form contract.’” (El Centro Mall, LLC v. Payless ShoeSou

23
Vitatech Int'l, Inc. v. Sporngreen
calctapp5d · 2017 · cited in 3 California opinions naming this issue, 2020–2021
2 sentences

2021(See Greentree, supra, at p. 498 [addressing settlement of breach of contract claim based on contract for financial services]; Ridgley, supra, at p. 973 [addressing prepayment fee in loan contract]; see also Vitatech Internat., Inc. v. Sporn (2017) 16 Cal.App.5th 796, 800 [addressing settlement of breach of contract claim].) Finally, BPI contends if we decide, as we do, that Civil Code section 1671 does not apply, BPI would effectively be precluded from challenging the final CWPA, and thus the alleged liquidated damages clause, because the 60- day window to reinstate review had passed by the t

2021(See Greentree, supra, at p. 498 [addressing settlement of breach of contract claim based on contract for financial services]; Ridgley, supra, at p. 973 [addressing prepayment fee in loan contract]; see also Vitatech Internat., Inc. v. Sporn (2017) 16 Cal.App.5th 796, 800 [addressing settlement of breach of contract claim].) Finally, BPI contends if we decide, as we do, that Civil Code section 1671 does not apply, BPI would effectively be precluded from challenging the final CWPA, and thus the alleged liquidated damages clause, because the 60- day window to reinstate review had passed by the t

23
Purcell v. Schweitzer CA4/1green
calctapp · 2014 · cited in 3 California opinions naming this issue, 2017–2020
2 sentences

2020Analysis of Relevant Case Law Section 1671, subdivision (b), provides that a liquidated damages clause “is valid unless the party seeking to invalidate the provision establishes that the provision 5 was unreasonable under the circumstances existing at the time the contract was made.” Under this subdivision, “a liquidated damages clause becomes an unenforceable penalty ‘if it bears no reasonable relationship to the range of actual damages that the parties could have anticipated would flow from a breach.’ [Citation.] ‘The amount set as liquidated damages “must represent the result of a reasonabl

2017The characteristic feature of a penalty is its lack of proportional relation to the damages which may actually flow from failure to perform under a contract.' " ( Ridgley , supra , 17 Cal.4th at p. 977 , 73 Cal.Rptr.2d 378 , 953 P.2d 484 .) "In short, '[a]n amount disproportionate to the anticipated damages is termed a "penalty." A contractual provision imposing a "penalty" is ineffective, and the wronged party can collect only the actual damages sustained.' " ( Ridgley , supra , 17 Cal.4th at p. 977 , 73 Cal.Rptr.2d 378 , 953 P.2d 484 ; see Purcell v. Schweitzer (2014) 224 Cal.App.4th 969 , 9

23
Weber, Lipshie & Co. v. Christiangreen
calctapp · 1997 · cited in 3 California opinions naming this issue, 2013–2017
2 sentences

2017The characteristic feature of a penalty is its lack of proportional relation to the damages which may actually flow from failure to perform under a contract.' " ( Ridgley , supra , 17 Cal.4th at p. 977 , 73 Cal.Rptr.2d 378 , 953 P.2d 484 .) "In short, '[a]n amount disproportionate to the anticipated damages is termed a "penalty." A contractual provision imposing a "penalty" is ineffective, and the wronged party can collect only the actual damages sustained.' " ( Ridgley , supra , 17 Cal.4th at p. 977 , 73 Cal.Rptr.2d 378 , 953 P.2d 484 ; see Purcell v. Schweitzer (2014) 224 Cal.App.4th 969 , 9

2017The characteristic feature of a penalty is its lack of proportional relation to the damages which may actually flow from failure to perform under a contract.' " ( Ridgley , supra , 17 Cal.4th at p. 977 , 73 Cal.Rptr.2d 378 , 953 P.2d 484 .) "In short, '[a]n amount disproportionate to the anticipated damages is termed a "penalty." A contractual provision imposing a "penalty" is ineffective, and the wronged party can collect only the actual damages sustained.' " ( Ridgley , supra , 17 Cal.4th at p. 977 , 73 Cal.Rptr.2d 378 , 953 P.2d 484 ; see Purcell v. Schweitzer (2014) 224 Cal.App.4th 969 , 9

23
Allen v. Smithgreen
calctapp · 2002 · cited in 3 California opinions naming this issue, 2006–2013
2 sentences

2013“To avoid uncertainty and litigation if a default occurs, the parties to a contract may use a liquidated damages clause to determine the measure of damages in advance. [Citation.] A liquidated damages clause is generally valid unless the party challenging it shows it was unreasonable under the circumstances existing at the time the parties entered into the contract. [Citations.] In the absence of a reasonable relationship between the liquidated damages and the actual damages the parties could have contemplated for breach, „a contractual clause purporting to predetermine damages “must be constr

2006(Allen v. Smith (2002) 94 Cal.App.4th 1270, 1278 [ 114 Cal.Rptr.2d 898 ].) Until 1978, former Civil Code section 1670 provided that a liquidated damages clause was void unless it complied with former Civil Code section 1671, which said; “The parties to a contract may agree therein upon an amount which shall be presumed to be the amount of damage sustained by a breach thereof, when, from the nature of the case, it would be impracticable or extremely difficult to fix the actual damage.” (See H.

23
Californians for Population Stabilization v. Hewlett-Packard Co.green
calctapp · 1997 · cited in 2 California opinions naming this issue, 2009–2009
2 sentences

2009All the circumstances existing at the time of the making of the contract are considered, including the relationship that the damages provided in the contract bear to the range of harm that reasonably could be anticipated at the time of the making of the contract.’ ” (Californians for Population Stabilization v. Hewlett-Packard Co. (1997) 58 Cal.App.4th 273, 288 [ 67 Cal.Rptr.2d 621 ].) Because Pavestone failed to satisfy its burden of establishing the 18 percent interest charge was an unreasonable estimate of the damages likely to be suffered by plaintiffs in the event of late payment, the tri

2009All the circumstances existing at the time of the making of the contract are considered, including the relationship that the damages provided in the contract bear to the range of harm that reasonably could be anticipated at the time of the making of the contract.’ ” (Californians for Population Stabilization v. Hewlett-Packard Co. (1997) 58 Cal.App.4th 273, 288 [ 67 Cal.Rptr.2d 621 ].) Because Pavestone failed to satisfy its burden of establishing the 18 percent interest charge was an unreasonable estimate of the damages likely to be suffered by plaintiffs in the event of late payment, the tri

22
Rice v. Schmidgreen
cal · 1941 · cited in 3 California opinions naming this issue, 2006–2024
2 sentences

2024(Rice v. Schmid (1941) 18 Cal.2d 382, 385 [the validity of a liquidated damages clause involves questions of fact specific to the particular contract at issue]; Johnson v. Greenelsh (2009) 47 Cal.4th 598, 603 [“ ‘ “[I]ssues not raised in the trial court cannot be raised for the first time on appeal.” ’ ”].) Vladimir next argues the doctrines of waiver, laches, and unclean hands bar reinstatement of the attorney fees award.

2006Rice, supra, 18 Cal.2d 382 , cited Dyer Bros, for the proposition that the validity of a liquidated damages clause turned in part on whether it represented “a reasonable endeavor by the parties to estimate fair compensation for the loss sustained.” (Id. at p. 386.) This statement was dicta and came as part of an *1034 acknowledgement that courts in other states had approved liquidated damages provisions in form contracts.

13
Morris v. Redwood Empire Bancorpgreen
calctapp · 2005 · cited in 3 California opinions naming this issue, 2014–2021
2 sentences

2014ANALYSIS “[A] provision in a contract liquidating the damages for the breach of the contract is valid unless the party seeking to invalidate the provision establishes that the provision was unreasonable under the circumstances existing at the time the contract was made.” (§ 1671, subd. (b), italics added.) However, a liquidated damages clause becomes an unenforceable penalty “if it bears no reasonable relationship to the range of actual damages that the parties could have anticipated would flow from a breach.” (Ridgley v. Topa Thrift & Loan Assn. (1998) 17 Cal.4th 970, 977 [ 73 Cal.Rptr.2d 378

2014ANALYSIS “[A] provision in a contract liquidating the damages for the breach of the contract is valid unless the party seeking to invalidate the provision establishes that the provision was unreasonable under the circumstances existing at the time the contract was made.” (§ 1671, subd. (b), italics added.) However, a liquidated damages clause becomes an unenforceable penalty “if it bears no reasonable relationship to the range of actual damages that the parties could have anticipated would flow from a breach.” (Ridgley v. Topa Thrift & Loan Assn. (1998) 17 Cal.4th 970, 977 [ 73 Cal.Rptr.2d 378

13
Blank v. Bordengreen
cal · 1974 · cited in 2 California opinions naming this issue, 2021–2024
2 sentences

2024(See McGuire, supra, 220 Cal.App.4th at p. 522 [“[A] provision in a contract that appears at first glance to be either a liquidated damages clause or an unenforceable penalty provision may instead merely be a provision that permissibly calls for alternative performance by the obligor”].) The cotenancy provision “clearly reserves to [JJD] the power to make a realistic and rational choice.” (Blank, supra, 11 Cal.3d at p. 971 .) JJD can choose to provide a higher level of service (i.e., a mall with anchor tenants or specified 10 JJD-HOV ELK GROVE, LLC v. JO-ANN STORES, LLC Opinion of the Court by

2021“To constitute a liquidated damage clause the conduct triggering the payment must in some manner breach the contract.” (Morris v. Redwood Empire Bancorp (2005) 128 Cal.App.4th 1305, 1315 ; see also McGuire v. More-Gas Investments, LLC (2013) 220 Cal.App.4th 512, 521 [“The term ‘liquidated damages’ is used to indicate an amount of compensation to be paid in the event of a 12 breach of contract”], italics added.) “A contractual provision that merely provides an option of alternative performance of an obligation does not impose damages and is not subject to [Civil Code] section 1671 limitations.”

12
Beasley v. Wells Fargo Bankgreen
calctapp · 1991 · cited in 2 California opinions naming this issue, 2007–2023
2 sentences

2007Gilbert Co. (1999) 69 Cal.App.4th 1155, 1182-1183 [ 82 Cal.Rptr.2d 162 ]) and he improperly testified the contract drafts contained no provision barring ticket sales without Stewart’s prior written approval, the deposited money did not belong to Stewart, the liquidated damages clause was not a fair and reasonable forfeiture (Beasley v. Wells Fargo Bank (1991) 235 Cal.App.3d 1383, 1393 [ 1 Cal.Rptr.2d 446 ] [the validity of liquidated damages clause is a question of law]), and the three grounds identified by Tyerman in the cancellation letter of January 15, 2002 were not legally valid grounds u

2007Gilbert Co. (1999) 69 Cal.App.4th 1155, 1182-1183 [ 82 Cal.Rptr.2d 162 ]) and he improperly testified the contract drafts contained no provision barring ticket sales without Stewart’s prior written approval, the deposited money did not belong to Stewart, the liquidated damages clause was not a fair and reasonable forfeiture (Beasley v. Wells Fargo Bank (1991) 235 Cal.App.3d 1383, 1393 [ 1 Cal.Rptr.2d 446 ] [the validity of liquidated damages clause is a question of law]), and the three grounds identified by Tyerman in the cancellation letter of January 15, 2002 were not legally valid grounds u

12
ABI, Inc. v. City of Los Angelesgreen
calctapp · 1984 · cited in 2 California opinions naming this issue, 2009–2021
2 sentences

2021(ABI, Inc. v. City of Los Angeles (1984) 153 Cal.App.3d 669, 685 .) Under California law, different standards for reviewing the legality of such a clause apply depending on whether the clause is in a consumer or a non-consumer contract.

2009(ABI, Inc. v. City of Los Angeles (1984) 153 Cal.App.3d 669, 685 [ 200 Cal.Rptr. 563 ].) Courts perform a “ ‘reasonable endeavor’ ” test to determine the validity of the liquidated damages provision measured at the time of contracting: “The amount set as liquidated damages ‘must represent the result of a reasonable endeavor by the parties to estimate a fair average compensation for any loss that may be sustained.’ ” (Ridgley v. Topa Thrift & Loan Assn. (1998) 17 Cal.4th 970, 977 [ 73 Cal.Rptr.2d 378 , 953 P.2d 484 ].) *64 In determining whether the liquidated damages provision is enforceable,

12
Better Food Markets, Inc. v. American District Telegraph Co.green
cal · 1953 · cited in 2 California opinions naming this issue, 1973–2006
2 sentences

2006As discussed ante, the reasonable endeavor test looks primarily to the intent of the parties, as determined by the purposes behind a liquidated damages clause and the relationship between the amount of liquidated damages and a fair estimate of the actual damages from a breach of the contract. ( Garrett, supra, 9 Cal.3d at pp. 738-740; Better Food, supra, 40 Cal.2d at p. 187 ; Rice, supra, 18 Cal.2d at pp. 386-387.) In the context of mass consumer transactions involving standardized form contracts, those standards are not necessarily undermined by nonnegotiated liquidated damages provisions.

1973Co., supra, 40 Cal.2d 179, 184, 185, 186 .) The party seeking to rely on a liquidated damages clause bears the burden of proof.

12
Armitage v. Deckergreen
calctapp · 1990 · cited in 1 California opinions naming this issue, 2024–2024
1 sentence

2024Proc., § 726, subd. (b)), the trial court adopted a measure of damages used in cases of tortious injury to real property, namely, “the reasonable cost of repair or restoration of the property to its original condition.” (6 Witkin, Summary of Cal. Law (11th ed. 2017) Torts, § 1913, p. 1365; see Armitage v. Decker (1990) 218 Cal.App.3d 887, 905 [one “measure of damages for tortious injury to property” is “cost of repair or restoration”].) As appellants point out, however, tort law does not govern, because the injured property, i.e., the golf course, belongs to them, not the Association; and they

11
Johnson v. Greenelshgreen
cal · 2009 · cited in 1 California opinions naming this issue, 2024–2024
1 sentence

2024(Rice v. Schmid (1941) 18 Cal.2d 382, 385 [the validity of a liquidated damages clause involves questions of fact specific to the particular contract at issue]; Johnson v. Greenelsh (2009) 47 Cal.4th 598, 603 [“ ‘ “[I]ssues not raised in the trial court cannot be raised for the first time on appeal.” ’ ”].) Vladimir next argues the doctrines of waiver, laches, and unclean hands bar reinstatement of the attorney fees award.

11
Moncharsh v. Heily & Blasegreen
cal · 1992 · cited in 1 California opinions naming this issue, 2023–2023
1 sentence

2023(Gueyffier); see Cable Connection, Inc. v. DIRECTV, Inc. (2008) 44 Cal.4th 1334 , 1360 . . . ), and California law does not permit a court to correct even what may appear to be obvious errors in such interpretation. ( Moncharsh, supra, 3 Cal.4th at pp. 6, 28 & 33.)” (VVA-TWO, supra, 48 Cal.App.5th at p. 1005.) Mehta and Gupta raise a related argument that the arbitrator’s award effectively “modified” the liquidated damages clause, in violation of the purchase agreement’s requirement that an arbitrator “shall not have the power to add to, modify, or change any of the provisions [of the agreemen

11
Cable Connection, Inc. v. DirecTV, Inc.green
cal · 2008 · cited in 1 California opinions naming this issue, 2023–2023
1 sentence

2023(Gueyffier); see Cable Connection, Inc. v. DIRECTV, Inc. (2008) 44 Cal.4th 1334 , 1360 . . . ), and California law does not permit a court to correct even what may appear to be obvious errors in such interpretation. ( Moncharsh, supra, 3 Cal.4th at pp. 6, 28 & 33.)” (VVA-TWO, supra, 48 Cal.App.5th at p. 1005.) Mehta and Gupta raise a related argument that the arbitrator’s award effectively “modified” the liquidated damages clause, in violation of the purchase agreement’s requirement that an arbitrator “shall not have the power to add to, modify, or change any of the provisions [of the agreemen

11
Harshad & Nasir Corp. v. Global Sign Sys., Inc.green
calctapp5d · 2017 · cited in 1 California opinions naming this issue, 2023–2023
1 sentence

2023(See Cal. Rules of Court, rule 8.204(a)(1)(C) [briefs must “[s]upport any reference to a matter in the record by a citation to the volume and page number of the record where the matter appears”]; Harshad & Nasir Corp. v. Global Sign Systems, Inc. (2017) 14 Cal.App.5th 523, 527, fn. 3 [“We are not required to scour the record in search of support for a party’s factual statements and may disregard such unsupported statements”].) In all, on this record, Dixon has not shown error on the conversion cause of action. 4 Dixon at one point relies on a liquidated damages clause from a purchase agreement

11
McCarthy v. Tallygreen
cal · 1956 · cited in 1 California opinions naming this issue, 2011–2011
11
People v. Orange County Charitable Servicesgreen
calctapp · 1999 · cited in 1 California opinions naming this issue, 2009–2009
11
Summers v. A. L. Gilbert Co.green
calctapp · 1999 · cited in 1 California opinions naming this issue, 2007–2007
11
HS PERLIN CO. INC. v. Morse Signal Devicesgreen
calctapp · 1989 · cited in 1 California opinions naming this issue, 2006–2006
11
Hong v. Somerset Associatesgreen
calctapp · 1984 · cited in 1 California opinions naming this issue, 2002–2002
11
Barbera v. Sokolgreen
calctapp · 1980 · cited in 1 California opinions naming this issue, 1984–1984
11
McClure v. Ceratigreen
calctapp · 1948 · cited in 1 California opinions naming this issue, 1984–1984
11
Clermont v. Secured Investment Corp.green
calctapp · 1972 · cited in 1 California opinions naming this issue, 1979–1979
11
Ralph C. Sutro Co. v. Paramount Plastering, Inc.green
calctapp · 1963 · cited in 1 California opinions naming this issue, 1974–1974
11
Atkinson v. Pacific Fire Extinguisher Co.green
cal · 1953 · cited in 1 California opinions naming this issue, 1967–1967
11

Distinguished, questioned or overruled (1)

CaseNegativeCited
Harbor Island Holdings, L.L.C. v. Kimgreen
calctapp · 2003 · cited in 5 California opinions naming this issue, 2008–2020
2 sentences

2019The Stipulated Judgment Is an Unenforceable Penalty As noted above, under section 1671, subdivision (b), "a provision in a contract liquidating the damages for the breach of the contract is valid unless the party seeking to invalidate the provision establishes that the provision was unreasonable under the circumstances existing at the time the contract was made." A liquidated damages clause will generally be considered unreasonable, and hence unenforceable under section 1671 if it "bears no reasonable relationship to the range of actual damages that the parties could have anticipated would flo

2019The Stipulated Judgment Is an Unenforceable Penalty As noted above, under section 1671, subdivision (b), "a provision in a contract liquidating the damages for the breach of the contract is valid unless the party seeking to invalidate the provision establishes that the provision was unreasonable under the circumstances existing at the time the contract was made." A liquidated damages clause will generally be considered unreasonable, and hence unenforceable under section 1671 if it "bears no reasonable relationship to the range of actual damages that the parties could have anticipated would flo

15

Also cited on this issue (33)

CaseCitedYears
Cellphone Termination Fee Cases green
calctapp · 2011
2 sentences

2021The decision held that “to establish the reasonable endeavor required, evidence must exist that the party seeking to impose liquidated damages ‘ “actually engaged in some form of analysis to determine what losses it would sustain from [a] breach, and that it made a genuine and non-pretextual effort to estimate a fair average compensation.” ’ ” (Cellphone Termination, supra, 193 Cal.App.4th at pp. 322–323, quoting Hitz v. First Interstate Bank (1995) 38 Cal.App.4th 274, 291 .) This court agreed with the consumer plaintiffs “that the reasonable endeavor test, to have any meaning, must necessaril

2018In re Cellphone Termination Fee Cases (2011) 193 Cal.App.4th 298, 322 .

32013–2021
El Centro Mall, LLC v. Payless ShoeSource, Inc. green
calctapp · 2009
2 sentences

2025DISCUSSION A. Applicable Law and Standard of Review “The objective of a liquidated damages clause is to ‘stipulate . . . a pre-estimate of damages in order that the [contracting] parties may know with reasonable certainty the extent of liability’ in the event of breach.” (El Centro Mall, LLC v. Payless ShoeSource, Inc. (2009) 174 Cal.App.4th 58, 63 ; see Graylee v. Castro (2020) 52 Cal.App.5th 1107 , 1114 [liquidated damages are a sum a contracting party agrees to pay for breach of a contractual obligation].) Civil Code section 16761 provides that “a provision in a contract to purchase and sel

2025Other relevant considerations in the determination of whether the amount of liquidated damages is so high or so low as to be unreasonable include, but are not limited to, such matters as the relative equality of the bargaining power of the parties, whether the parties were represented by lawyers at the time the contract was made, the anticipation of the parties that proof of actual damages would be costly or inconvenient, the difficulty of proving causation and foreseeability, and whether the liquidated damages provision is included in a form contract.’” (El Centro Mall, LLC v. Payless ShoeSou

22020–2025
Hitz v. First Interstate Bank green
calctapp · 1995
2 sentences

2021The decision held that “to establish the reasonable endeavor required, evidence must exist that the party seeking to impose liquidated damages ‘ “actually engaged in some form of analysis to determine what losses it would sustain from [a] breach, and that it made a genuine and non-pretextual effort to estimate a fair average compensation.” ’ ” (Cellphone Termination, supra, 193 Cal.App.4th at pp. 322–323, quoting Hitz v. First Interstate Bank (1995) 38 Cal.App.4th 274, 291 .) This court agreed with the consumer plaintiffs “that the reasonable endeavor test, to have any meaning, must necessaril

2011(Utility Consumers, supra, 135 Cal.App.4th at pp. 1029-1039.) The court concluded that “the reasonable endeavor test looks primarily to the intent of the parties, as determined by the purposes behind a liquidated damages clause and the relationship between the amount of liquidated damages and a fair estimate of the actual damages from a breach of the contract. [Citations.]” (Id. at p. 1038.) The Utility Consumers court was critical of what it viewed as the interpretation of Garrett, supra, 9 Cal.3d 731 in Hitz, supra, 38 Cal.App.4th at page 289 , “as focusing solely on the intent behind a liqu

22011–2021
Petrovich v. City of Arcadia green
cal · 1950
2 sentences

2018And Petrovich v. Arcadia (1950) 36 Cal.2d 78 , 84-85, 222 P.2d 231 simply refused to enforce a liquidated damages clause in a contract.

2018And Petrovich v. Arcadia (1950) 36 Cal.2d 78 , 84-85, 222 P.2d 231 simply refused to enforce a liquidated damages clause in a contract.

22018–2018
Oppenheimer v. Sunkist Growers green
calctapp · 1957
2 sentences

2018The only case Grill Concepts cites involving Labor Code section 203 is Oppenheimer v. Sunkist Growers, Inc. (1957) 153 Cal.App.2d Supp. 897 , 898-899, 315 P.2d 116 , which construed section 203 to preclude waiting time penalties from continuing to accrue once the last paycheck was delivered, even if that paycheck did not itself include the amount of the then-accrued waiting time penalties; it did not speak to the issue of equitable discretion.

2018The only case Grill Concepts cites involving Labor Code section 203 is Oppenheimer v. Sunkist Growers, Inc. (1957) 153 Cal.App.2d Supp. 897, 898-899 , which construed section 203 to preclude waiting time penalties from continuing to accrue once the last paycheck was delivered, even if that paycheck did not itself include the amount of the then-accrued waiting time 20 penalties; it did not speak to the issue of equitable discretion.

22018–2018
Utility Consumers' Action Network, Inc. v. AT&T Broadband of Southern Cal., Inc. green
calctapp · 2006
2 sentences

2013“To avoid uncertainty and litigation if a default occurs, the parties to a contract may use a liquidated damages clause to determine the measure of damages in advance. [Citation.] A liquidated damages clause is generally valid unless the party challenging it shows it was unreasonable under the circumstances existing at the time the parties entered into the contract. [Citations.] In the absence of a reasonable relationship between the liquidated damages and the actual damages the parties could have contemplated for breach, „a contractual clause purporting to predetermine damages “must be constr

2011(Utility Consumers, supra, 135 Cal.App.4th at pp. 1029-1039.) The court concluded that “the reasonable endeavor test looks primarily to the intent of the parties, as determined by the purposes behind a liquidated damages clause and the relationship between the amount of liquidated damages and a fair estimate of the actual damages from a breach of the contract. [Citations.]” (Id. at p. 1038.) The Utility Consumers court was critical of what it viewed as the interpretation of Garrett, supra, 9 Cal.3d 731 in Hitz, supra, 38 Cal.App.4th at page 289 , “as focusing solely on the intent behind a liqu

22011–2013
Dudley v. Department of Transportation green
calctapp · 2001
1 sentence

2023(Ryan v. Real Estate of the Pacific, Inc. (2019) 32 Cal.App.5th 637, 644 ; Dudley v. Department of Transportation (2001) 90 Cal.App.4th 255, 259 .) But as the O’Briens also correctly assert in their opening and reply briefs, the validity of a liquidated damages clause involves questions of fact specific to the particular contract at issue.

12023–2023
Ryan v. Real Estate of the Pac., Inc. green
calctapp5d · 2019
1 sentence

2023(Ryan v. Real Estate of the Pacific, Inc. (2019) 32 Cal.App.5th 637, 644 ; Dudley v. Department of Transportation (2001) 90 Cal.App.4th 255, 259 .) But as the O’Briens also correctly assert in their opening and reply briefs, the validity of a liquidated damages clause involves questions of fact specific to the particular contract at issue.

12023–2023
Howard J. White, Inc. v. Varian Associates green
calctapp · 1960
12022–2022
W. R. Grace & Co. v. Local Union 759, International Union of the United Rubber, Cork, Linoleum & Plastic Workers green
scotus · 1983
12022–2022
Del Monte Props. & Invs., Inc. v. Dolan green
· 2018
12020–2020
Therapy Services, Inc. v. Crystal City Nursing Center, Inc. green
va · 1990
12007–2007
Fernández v. District Court neutral
prsupreme · 1904
12006–2006
Lowe v. Massachusetts Mutual Life Insurance green
calctapp · 1976
12006–2006
Muldoon v. Lynch green
cal · 1885
12006–2006
People v. Central Pacific Railroad green
cal · 1888
12006–2006
Kendall v. Ernest Pestana, Inc. green
cal · 1985
12001–2001
P.S.G. Ltd. Partnership v. August Income/Growth Fund VII green
nm · 1993
12001–2001
Pacific Employers Insurance v. City of Berkeley green
calctapp · 1984
11999–1999
General Insurance v. Mammoth Vista Owners' Ass'n green
calctapp · 1985
11999–1999
Payne v. United California Bank green
calctapp · 1972
11997–1997
Farthing v. San Mateo Clinic green
calctapp · 1956
11991–1991
Abel Construction Co. v. School District neutral
neb · 1972
11984–1984
Abel Construction Co. v. School District of Seward green
neb · 1972
11984–1984
Mattei v. Hopper green
cal · 1958
11981–1981
Rodriguez v. Barnett green
cal · 1959
11981–1981
Brown v. Superior Court green
cal · 1949
11981–1981
Aetna Casualty & Surety Co. v. Board of Trustees green
calctapp · 1963
11979–1979
United States v. United Engineering & Contracting Co. green
scotus · 1914
11979–1979
Gogo v. Los Angeles County Flood Control District green
calctapp · 1941
11979–1979
Wright v. Rodgers green
cal · 1926
11976–1976
Shell v. Schmidt green
calctapp · 1954
11974–1974
Webster v. Garrette green
calctapp · 1935
11960–1960

Statutes the citing opinions construe

CA § Cal. Civil Code § 1671 (23) CA § Cal. Civil Code § 1670 (6) CA § Cal. Civil Code § 3287 (3)

Counted by distinct opinions that both name this issue and are annotated to the section; sections every opinion cites regardless of issue are not filtered here, so read the counts against the total above.

Where else courts name it

NY 113 (1868–2026) IL 73 (1971–2025) TX 70 (1942–2026) CA 57 (1960–2025) OH 41 (1982–2025) MA 37 (1959–2026) FL 37 (1962–2025) CT 36 (1964–2022) IN 35 (1976–2026) MO 30 (1966–2021) PA 26 (1966–2025) GA 21 (1978–2026) MD 19 (1987–2023) NJ 19 (1991–2024) CO 18 (1971–2025) WA 16 (1979–2026) ND 13 (1975–2007) KS 12 (1981–2024) NC 11 (1987–2026) ID 11 (1971–2025) AZ 10 (1989–2022) WI 10 (1975–2025) VA 9 (1988–2025) UT 8 (1993–2013) AL 8 (1991–2026) ME 7 (1985–2022) MI 7 (1986–2026) MN 6 (1986–2024) AK 6 (1977–2012) DC 6 (1969–2019) MT 6 (1976–2020) TN 6 (1985–2019) LA 6 (1962–2018) OR 5 (1979–1998) VT 5 (1991–2025) NH 5 (1990–2020) WV 4 (1994–2024) WY 4 (1978–2015) SD 4 (1984–2005) DE 4 (1992–2021) NM 4 (1986–2020) SC 3 (2013–2024) IA 3 (1976–2024) RI 3 (1992–2009) NV 2 (1990–1993) OK 2 (1988–2008) KY 2 (1985–2024)

Opinions by the citing court's state. A doctrine retained in one state and abandoned in another shows up here as a year span that stalls.

← Caselaw search · G Cite Topics · Brief Check