liquidated damages clause (Minnesota) · Go Syfert
← Minnesota issues

liquidated damages clause in Minnesota

6 Minnesota opinions name it 1 courts 1986–2024 2 in the last five years

The cases below were cited by Minnesota courts in a sentence that names this issue. Sides come from how each citing opinion treated the case (Syfertize flag on that citation), so a case can appear on both: that is where the law is contested. A red or yellow chip is the case's own overall treatment.

Followed or applied (12)

CaseFollowedCited
Gorco Construction Co. v. Steingreen
minn · 1959 · cited in 3 Minnesota opinions naming this issue, 1986–2024
2 sentences

2024A liquidated-damages clause is unenforceable if the amount of liquidated damages is “not a reasonable forecast of just compensation.” Id.

2024And “the proponent of a liquidated-damages clause bears the burden of introducing evidence to justify the liquidated-damages clause.” Id. at 124 . 3 Recognizing that the district court did not have the benefit of Lagoon, we only address the homeowners’ first argument that the district court erred by construing Gorco to put the evidentiary burden on the homeowners. 1 The district court determined the homeowners did not introduce any affirmative evidence that the amount sought by Capital under the liquidated-damages clause was either punitive or an unreasonable forecast of just compensation.

33
Dean Van Horn Consulting Associates, Inc. v. Woldgreen
minnctapp · 1986 · cited in 2 Minnesota opinions naming this issue, 2023–2024
2 sentences

2024See Lagoon, 999 N.W.2d at 119 (noting that liquidated-damages clauses are prima facie valid); Dean Van Horn Consulting Assocs., Inc. v. Wold, 395 N.W.2d 405, 407-08 (Minn. App. 1986) (although a liquidated damages clause is prima facie valid, the trial court may hear evidence regarding the reasonableness of the liquidated damages clause).

2024This is consistent with Dean Van Horn, which held that the trial court may hear evidence regarding the reasonableness of a liquidated-damages clause. 395 N.W.2d at 408 .

22
Galbraith v. Woodgreen
minn · 1914 · cited in 1 Minnesota opinions naming this issue, 2023–2023
2 sentences

2023In general, if a tenant has breached a lease and the landlord has terminated the lease, the landlord’s customary remedy is “damages resulting from the breach with the attendant obligation upon the lessor to use reasonable efforts to mitigate such damages subsequent to the breach.” Gruman v. Investors Diversified Services, 78 N.W.2d 377, 381 (Minn. 1956); see also Newberg, 252 N.W. at 222 (affirming trial court’s damages award consisting of tenant’s unpaid rent less rent payments received from new tenant); Galbraith v. Wood, 144 N.W. 945, 948 (Minn. 1914) (stating that liability for unpaid rent

2023In general, if a tenant has breached a lease and the landlord has terminated the lease, the landlord’s customary remedy is “damages resulting from the breach with the attendant obligation upon the lessor to use reasonable efforts to mitigate such damages subsequent to the breach.” Gruman v. Investors Diversified Services, 78 N.W.2d 377, 381 (Minn. 1956); see also Newberg, 252 N.W. at 222 (affirming trial court’s damages award consisting of tenant’s unpaid rent less rent payments received from new tenant); Galbraith v. Wood, 144 N.W. 945, 948 (Minn. 1914) (stating that liability for unpaid rent

11
Palace Theatre, Inc. v. Northwest Theatres Circuitgreen
minn · 1932 · cited in 1 Minnesota opinions naming this issue, 2023–2023
2 sentences

2023Similarly, in Palace Theatre, which concerned a commercial lease, the supreme court determined that the liquidated-damages clause was unenforceable because some components of the landlord’s claim for damages “would necessarily be inconsiderable in amount as compared with” the amount of liquidated damages. 243 N.W. at 851. 17 In Meuwissen, on the other hand, the supreme court determined that the liquidated- damages clause was enforceable because the amount of liquidated damages had a “reasonable relation to the contemplated damages.” 16 N.W.2d at 551.

2023Similarly, in Palace Theatre, which concerned a commercial lease, the supreme court determined that the liquidated-damages clause was unenforceable because some components of the landlord’s claim for damages “would necessarily be inconsiderable in amount as compared with” the amount of liquidated damages. 243 N.W. at 851 . 17 In Meuwissen, on the other hand, the supreme court determined that the liquidated- damages clause was enforceable because the amount of liquidated damages had a “reasonable relation to the contemplated damages.” 16 N.W.2d at 551 .

11
Newberg v. Conleygreen
minn · 1934 · cited in 1 Minnesota opinions naming this issue, 2023–2023
2 sentences

2023In general, if a tenant has breached a lease and the landlord has terminated the lease, the landlord’s customary remedy is “damages resulting from the breach with the attendant obligation upon the lessor to use reasonable efforts to mitigate such damages subsequent to the breach.” Gruman v. Investors Diversified Services, 78 N.W.2d 377, 381 (Minn. 1956); see also Newberg, 252 N.W. at 222 (affirming trial court’s damages award consisting of tenant’s unpaid rent less rent payments received from new tenant); Galbraith v. Wood, 144 N.W. 945, 948 (Minn. 1914) (stating that liability for unpaid rent

2023In general, if a tenant has breached a lease and the landlord has terminated the lease, the landlord’s customary remedy is “damages resulting from the breach with the attendant obligation upon the lessor to use reasonable efforts to mitigate such damages subsequent to the breach.” Gruman v. Investors Diversified Services, 78 N.W.2d 377, 381 (Minn. 1956); see also Newberg, 252 N.W. at 222 (affirming trial court’s damages award consisting of tenant’s unpaid rent less rent payments received from new tenant); Galbraith v. Wood, 144 N.W. 945, 948 (Minn. 1914) (stating that liability for unpaid rent

11
Meuwissen v. H. E. Westerman Lumber Co.green
minn · 1944 · cited in 1 Minnesota opinions naming this issue, 2023–2023
2 sentences

2023Similarly, in Palace Theatre, which concerned a commercial lease, the supreme court determined that the liquidated-damages clause was unenforceable because some components of the landlord’s claim for damages “would necessarily be inconsiderable in amount as compared with” the amount of liquidated damages. 243 N.W. at 851. 17 In Meuwissen, on the other hand, the supreme court determined that the liquidated- damages clause was enforceable because the amount of liquidated damages had a “reasonable relation to the contemplated damages.” 16 N.W.2d at 551.

2023Similarly, in Palace Theatre, which concerned a commercial lease, the supreme court determined that the liquidated-damages clause was unenforceable because some components of the landlord’s claim for damages “would necessarily be inconsiderable in amount as compared with” the amount of liquidated damages. 243 N.W. at 851 . 17 In Meuwissen, on the other hand, the supreme court determined that the liquidated- damages clause was enforceable because the amount of liquidated damages had a “reasonable relation to the contemplated damages.” 16 N.W.2d at 551 .

11
Bellboy Seafood Corp. v. Nathansongreen
minnctapp · 1987 · cited in 1 Minnesota opinions naming this issue, 2023–2023
2 sentences

2023See Maslowski v. Prospect Funding Partners LLC, 978 N.W.2d 447, 455 (Minn. App. 2022), rev’d on other grounds, 994 N.W.2d 293 (Minn. 2023); Bellboy Seafood Corp. v. Nathanson, 410 N.W.2d 349, 352 (Minn. App. 1987); Dean Van Horn Consulting Associates, Inc. v. Wold, 395 N.W.2d 405, 407 (Minn. App. 1986). 9 A liquidated-damages clause in a contract is “prima facie valid on the assumption that the parties in naming a liquidated sum intended it to be a fair compensation for an injury caused by a breach of contract and not a penalty for nonperformance.” Gorco, 99 N.W.2d at 74.

2023See Maslowski v. Prospect Funding Partners LLC, 978 N.W.2d 447 , 455 (Minn. App. 2022), rev’d on other grounds, 994 N.W.2d 293 (Minn. 2023); Bellboy Seafood Corp. v. Nathanson, 410 N.W.2d 349, 352 (Minn. App. 1987); Dean Van Horn Consulting Associates, Inc. v. Wold, 395 N.W.2d 405, 407 (Minn. App. 1986). 9 A liquidated-damages clause in a contract is “prima facie valid on the assumption that the parties in naming a liquidated sum intended it to be a fair compensation for an injury caused by a breach of contract and not a penalty for nonperformance.” Gorco, 99 N.W.2d at 74 .

11
Thiele v. Stichgreen
minn · 1988 · cited in 1 Minnesota opinions naming this issue, 2023–2023
2 sentences

2023See Thiele v. Stich, 425 N.W.2d 580, 582 (Minn. 1988). 7 court concluded that the liquidated-damages clause in the lease is enforceable and that, as a consequence, Lagoon is not required to mitigate its damages.

2023See Thiele v. Stich, 425 N.W.2d 580, 582 (Minn. 1988). 7 court concluded that the liquidated-damages clause in the lease is enforceable and that, as a consequence, Lagoon is not required to mitigate its damages.

11
Aurora Business Park Associates, L.P. v. Michael Albert, Inc.green
iowa · 1996 · cited in 1 Minnesota opinions naming this issue, 2023–2023
2 sentences

2023Park v. Albert, Inc., 548 N.W.2d 153, 157 (Iowa 1996) (concluding that liquidated-damages clause was reasonable because it considered landlord’s duty to mitigate). 22 issues raised in the pending motion.” That ruling was predicated on the district court’s decision that the liquidated-damages clause is enforceable as a matter of law.

2023Park v. Albert, Inc., 548 N.W.2d 153, 157 (Iowa 1996) (concluding that liquidated-damages clause was reasonable because it considered landlord’s duty to mitigate). 22 issues raised in the pending motion.” That ruling was predicated on the district court’s decision that the liquidated-damages clause is enforceable as a matter of law.

11
Gruman v. Investors Diversified Services, Inc.green
minn · 1956 · cited in 1 Minnesota opinions naming this issue, 2023–2023
2 sentences

2023In general, if a tenant has breached a lease and the landlord has terminated the lease, the landlord’s customary remedy is “damages resulting from the breach with the attendant obligation upon the lessor to use reasonable efforts to mitigate such damages subsequent to the breach.” Gruman v. Investors Diversified Services, 78 N.W.2d 377, 381 (Minn. 1956); see also Newberg, 252 N.W. at 222 (affirming trial court’s damages award consisting of tenant’s unpaid rent less rent payments received from new tenant); Galbraith v. Wood, 144 N.W. 945, 948 (Minn. 1914) (stating that liability for unpaid rent

2023In general, if a tenant has breached a lease and the landlord has terminated the lease, the landlord’s customary remedy is “damages resulting from the breach with the attendant obligation upon the lessor to use reasonable efforts to mitigate such damages subsequent to the breach.” Gruman v. Investors Diversified Services, 78 N.W.2d 377, 381 (Minn. 1956); see also Newberg, 252 N.W. at 222 (affirming trial court’s damages award consisting of tenant’s unpaid rent less rent payments received from new tenant); Galbraith v. Wood, 144 N.W. 945, 948 (Minn. 1914) (stating that liability for unpaid rent

11
Grossman v. Shermangreen
colo · 1979 · cited in 1 Minnesota opinions naming this issue, 2000–2000
1 sentence

2000Id. at 911.

11
Hilltop Construction, Inc. v. Lou Park Apartmentsgreen
minn · 1982 · cited in 1 Minnesota opinions naming this issue, 1987–1987
1 sentence

1987See Hilltop Construction, 324 N.W.2d at 239 (“A mere ambiguity in the opinion accompanying an award which permits an inference that the arbitrators may have exceeded their authority is no reason for refusing to enforce the award”).

11

Distinguished, questioned or overruled (0)

CaseNegativeCited
No negative-treatment citations attached to this issue in Minnesota. Read the followed side critically anyway.

Also cited on this issue (3)

CaseCitedYears
Gary Outdoor Advertising Co. v. Sun Lodge, Inc. green
ariz · 1982
2 sentences

2023Co. v. Sun Lodge Inc., 650 P.2d 1222, 21 That conclusion is an additional reason why the liquidated-damages clause in the parties’ lease is unenforceable.

2023Co. v. Sun Lodge Inc., 650 P.2d 1222 , 21 That conclusion is an additional reason why the liquidated-damages clause in the parties’ lease is unenforceable.

12023–2023
Quintero-Chadid Corp. v. Gersten green
fladistctapp · 1991
2 sentences

2023See Tremitek, LLC v. Resilience Code, LLC, 535 P.3d 1005, 1011-12 (Colo. App. 2023); Quintero-Chadid Corp. v. Gersten, 582 So. 2d 685, 688- 89 (Fla. App. 3d Dist. 1991); Gary Outdoor Advert.

2023See Tremitek, LLC v. Resilience Code, LLC, 535 P.3d 1005 , 1011-12 (Colo. App. 2023); Quintero-Chadid Corp. v. Gersten, 582 So. 2d 685 , 688- 89 (Fla. App. 3d Dist. 1991); Gary Outdoor Advert.

12023–2023
Meyer v. Hansen green
nd · 1985
2 sentences

1989The court reasoned that a provision for liquidated damages does not prevent recovery for actual damages caused by events not contemplated by the clause, “unless the contract expressly provides that damages other than those enumerated shall not be recovered.” Id.

1989Id. at 396 .

11989–1989

Where else courts name it

NY 113 (1868–2026) IL 73 (1971–2025) TX 70 (1942–2026) CA 57 (1960–2025) OH 41 (1982–2025) MA 37 (1959–2026) FL 37 (1962–2025) CT 36 (1964–2022) IN 35 (1976–2026) MO 30 (1966–2021) PA 26 (1966–2025) GA 21 (1978–2026) MD 19 (1987–2023) NJ 19 (1991–2024) CO 18 (1971–2025) WA 16 (1979–2026) ND 13 (1975–2007) KS 12 (1981–2024) NC 11 (1987–2026) ID 11 (1971–2025) AZ 10 (1989–2022) WI 10 (1975–2025) VA 9 (1988–2025) UT 8 (1993–2013) AL 8 (1991–2026) ME 7 (1985–2022) MI 7 (1986–2026) MN 6 (1986–2024) AK 6 (1977–2012) DC 6 (1969–2019) MT 6 (1976–2020) TN 6 (1985–2019) LA 6 (1962–2018) OR 5 (1979–1998) VT 5 (1991–2025) NH 5 (1990–2020) WV 4 (1994–2024) WY 4 (1978–2015) SD 4 (1984–2005) DE 4 (1992–2021) NM 4 (1986–2020) SC 3 (2013–2024) IA 3 (1976–2024) RI 3 (1992–2009) NV 2 (1990–1993) OK 2 (1988–2008) KY 2 (1985–2024)

Opinions by the citing court's state. A doctrine retained in one state and abandoned in another shows up here as a year span that stalls.

← Caselaw search · G Cite Topics · Brief Check