10 C.F.R. § 50.35 (2026)

Issuance of construction permits. 1

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1961–1990 12citing cases
At a glance

Courts have cited this section in 12 opinions since 1961. The most litigated part is subsection (a) (2 cases).

1 The Commission may issue a provisional construction permit pursuant to the regulations in this part in effect on March 30, 1970, for any facility for which a notice of hearing on an application for a provisional construction permit has been published on or before that date.

(a) When an applicant has not supplied initially all of the technical information required to complete the application and support the issuance of a construction permit which approves all proposed design features, the Commission may issue a construction permit if the Commission finds that (1) the applicant has described the proposed design of the facility, including, but not limited to, the principal architectural and engineering criteria for the design, and has identified the major features or components incorporated therein for the protection of the health and safety of the public; (2) such further technical or design information as may be required to complete the safety analysis, and which can reasonably be left for later consideration, will be supplied in the final safety analysis report; (3) safety features or components, if any, which require research and development have been described by the applicant and the applicant has identified, and there will be conducted, a research and development program reasonably designed to resolve any safety questions associated with such features or components; and that (4) on the basis of the foregoing, there is reasonable assurance that, (i) such safety questions will be satisfactorily resolved at or before the latest date stated in the application for completion of construction of the proposed facility, and (ii) taking into consideration the site criteria contained in part 100 of this chapter, the proposed facility can be constructed and operated at the proposed location without undue risk to the health and safety of the public.

Note:

When an applicant has supplied initially all of the technical information required to complete the application, including the final design of the facility, the findings required above will be appropriately modified to reflect that fact.

(b) A construction permit will constitute an authorization to the applicant to proceed with construction but will not constitute Commission approval of the safety of any design feature or specification unless the applicant specifically requests such approval and such approval is incorporated in the permit. The applicant, at his option, may request such approvals in the construction permit or, from time to time, by amendment of his construction permit. The Commission may, in its discretion, incorporate in any construction permit provisions requiring the applicant to furnish periodic reports of the progress and results of research and development programs designed to resolve safety questions.

(c) Any construction permit will be subject to the limitation that a license authorizing operation of the facility will not be issued by the Commission until (1) the applicant has submitted to the Commission, by amendment to the application, the complete final safety analysis report, portions of which may be submitted and evaluated from time to time, and (2) the Commission has found that the final design provides reasonable assurance that the health and safety of the public will not be endangered by operation of the facility in accordance with the requirements of the license and the regulations in this chapter.

[27 FR 12915, Dec. 29, 1962, as amended at 31 FR 12780, Sept. 30, 1966; 35 FR 5318, Mar. 31, 1970; 35 FR 6644, Apr. 25, 1970; 35 FR 11461, July 7, 1970]
The 11 cases that cite 10 C.F.R. § 50.35 most heavily, weighted by court and treatment. RelevanceNewestTreatment
cites § 50.35 1×cited by 2,316 cases
Where it cites § 50.35
“§2241 ; 10 CFR §50.35 (a) *527 (1977), and that the environmental cost-benefit balance favors the issuance of a permit.”
The case’s holding
Administrative agencies may fashion their own rules of procedure absent constitutional constraints or extremely compelling circumstances.
Later courts cite it for
“absent constitutional constraints or extremely compelling circumstances the administrative agencies should be free to fashion their own rules of procedure and to pursue methods of inquiry capable of permitting them to discharge their multitudinous duties.” · 68 citing courts
cites § 50.35 2×cited by 440 cases
Where it cites § 50.35
“The crucial regulation for our purposes is the Commission's regulation 50.35, 10 CFR § 50.35 : "§ 50.35. Extended time for providing technical information.”
The case’s holding
Courts accord respect to an administrative agency's interpretation of its own regulations and governing statutes.
Later courts cite it for
“particularly is this respect due when the administrative practice at stake 'involves a contemporaneous construction of a statute by the men charged with the responsibility of setting its machinery in motion; of making the parts work efficiently and smoothly while they are yet untried and new.” · 53 citing courts
cites § 50.35 2×cited by 78 cases
Where it cites § 50.35
“” 10 C.F.R. § 50.35 (a). The issuance of a construction permit is the first step in the two-step process prescribed by 42 U.”
The case’s holding
An organization possesses derivative standing based on the standing of its individual members.
Later courts cite it for
“the standing of an organization is derivative of its members' standing.” · 2 citing courts
cites § 50.35 1×cited by 56 cases
The case’s holding
An agency's failure to follow its own regulations is fatal to the deviant action, but procedural directives that are not binding regulations do not trigger this rule.
Later courts cite it for
“(a)n amendment can be made without opportunity for a hearing if the aec determines that it 'involves no significant hazards consideration.” · 4 citing courts
5
GREENUnited States v. City of New York, 463 F. Supp. 604 (S.D.N.Y. 1978).
cites § 50.35 1×subsections: (a)cited by 9 cases
Where it cites § 50.35
“” 10 C.F.R. 50.35(a). See also 10 C.F.R. §§ 50.40 , 50.50, 50.56-57.”
Later courts cite it for
“radiological regulation of the operation of nuclear reactors” · 2 citing courts
6
GREENNader v. Nuclear Regulatory Comm'n, 513 F.2d 1045 (D.C. Cir. 1975).
cites § 50.35 1×cited by 22 cases
Where it cites § 50.35
“g„ 10 C.F.R. §§ 50.35 (c), 50.40(a), 50.57(a)(III) (1974).”
The case’s holding
Parties who refrain from participating in agency rulemaking proceedings are precluded from seeking direct judicial review of the resulting regulations.
Later courts cite it for
“those who refrain from participation in rulemaking proceedings may not obtain direct judicial review of the regulations resulting” · 4 citing courts
7
NO FLAGGen. Pub. Utils. Corp. v. United States, 745 F.2d 239 (3d Cir. 1984).
cites § 50.35 1×cited by 48 cases
Summary
No passage or summary on file for this case yet.
8
GREENCities of Statesville v. Atomic Energy Comm'n, 441 F.2d 962 (D.C. Cir. 1969).
cites § 50.35 1×subsections: (a)cited by 16 cases
Where it cites § 50.35
“The only issues were whether the construction and operation would be in compliance with 10 C.F.R. § 50.35 (a) (1968) with respect to health and safety, and in regard to the national security.”
Later courts cite it for
“an agency 'should be accorded broad discretion in establishing and applying rules for public participation .” · 2 citing courts
9
GREENNader v. Ray, 363 F. Supp. 946 (D.D.C. 1973).
cites § 50.35 1×cited by 11 cases
Where it cites § 50.35
“Under the Atomic Energy Act, the standard applied in issuing facility operating licenses for nuclear power reactors is whether the Commission can find that there will be “adequate protection to the health and safety of the public.” 42 U.S.C. § 2232 (a).”
10
GREENCarstens v. Nuclear Regulatory Comm'n, 742 F.2d 1546 (D.C. Cir. 1984).
cites § 50.35 1×cited by 9 cases
Where it cites § 50.35
“An examination of the entire record in this case demonstrates that petitioners were given a full and fair opportunity to present their arguments before the Commission, and that the Commission has fully complied with the procedures mandated in the applicable statutes and…”
Later courts cite it for
“since the board is obviously best situated to assess the credibility and demeanor of expert witnesses, this court must defer to that judgment so long as it is reasonable.” · 2 citing courts
cites § 50.35 1×cited by 1 case
Superseded by Nuclear Information Resource Service v. Nuclear Regulatory Commission (1991): the Court of Appeals for the D.C. Circuit's own en banc opinion in this case.
Where it cites § 50.35
“104 (b) (emphasis supplied); see also 10 C.F.R. § 50.35 . After construction and upon certain findings, the Commission would issue an operating license; a hearing on an operating license application would be held upon the request of an interested party.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
196119751990

One bar per year. Tallest: 2 cases in 1969. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
D.C. Cir.6SCOTUS23rd Cir.17th Cir.1D.D.C.1S.D.N.Y.1
By subsection
(a)2 cases
United States v. City of New York, 463 F. Supp. 604 (S.D.N.Y. 1978).“” 10 C.F.R. 50.35(a). See also 10 C.F.R. §§ 50.40 , 50.50, 50.56-57.”
Cities of Statesville v. Atomic Energy Comm'n, 441 F.2d 962 (D.C. Cir. 1969).“The only issues were whether the construction and operation would be in compliance with 10 C.F.R. § 50.35 (a) (1968) with respect to health and safety, and in regard to the national security.”
Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.