C.F.R. homeSearch C.F.R.
C.F.R.Title 18Chapter I—Federal Energy Regulatory Commission, Department of EnergySubchapter X—Procedural RulesPart 385—Rules of Practice and ProcedureSubpart B—Pleadings, Tariff and Rate Filings, Notices of Tariff or Rate Examination, Orders to Show Cause, Intervention, and Summary Disposition

18 C.F.R. § 385.206 (2026)

Complaints (Rule 206)

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1984–2024 24citing cases
At a glance

Courts have cited this section in 24 opinions since 1984, 5 of them in the last five years.

(a) General rule. Any person may file a complaint seeking Commission action against any other person alleged to be in contravention or violation of any statute, rule, order, or other law administered by the Commission, or for any other alleged wrong over which the Commission may have jurisdiction.

(b) Contents. A complaint must:

(1) Clearly identify the action or inaction which is alleged to violate applicable statutory standards or regulatory requirements;

(2) Explain how the action or inaction violates applicable statutory standards or regulatory requirements;

(3) Set forth the business, commercial, economic or other issues presented by the action or inaction as such relate to or affect the complainant;

(4) Make a good faith effort to quantify the financial impact or burden (if any) created for the complainant as a result of the action or inaction;

(5) Indicate the practical, operational, or other nonfinancial impacts imposed as a result of the action or inaction, including, where applicable, the environmental, safety or reliability impacts of the action or inaction;

(6) State whether the issues presented are pending in an existing Commission proceeding or a proceeding in any other forum in which the complainant is a party, and if so, provide an explanation why timely resolution cannot be achieved in that forum;

(7) State the specific relief or remedy requested, including any request for stay or extension of time, and the basis for that relief;

(8) Include all documents that support the facts in the complaint in possession of, or otherwise attainable by, the complainant, including, but not limited to, contracts and affidavits;

(9) State

(i) Whether the Enforcement Hotline, Dispute Resolution Service, tariff-based dispute resolution mechanisms, or other informal dispute resolution procedures were used, or why these procedures were not used;

(ii) Whether the complainant believes that alternative dispute resolution (ADR) under the Commission's supervision could successfully resolve the complaint;

(iii) What types of ADR procedures could be used; and

(iv) Any process that has been agreed on for resolving the complaint.

(10) Include a form of notice of the complaint suitable for publication in the Federal Register in accordance with the specifications in § 385.203(d) of this part. The form of notice shall be on electronic media as specified by the Secretary. This paragraph (b)(10) shall cease to have effect on December 5, 2026, unless the Commission determines that the cessation deadline should be extended to a date not more than 5 years in the future after offering the public an opportunity to provide input on the costs and benefits of this paragraph (b)(10) and considering that input. The Commission will publish a document in the Federal Register announcing its determination and revising or removing this paragraph (b)(10) accordingly.

(11) Explain with respect to requests for Fast Track processing pursuant to section 385.206(h), why the standard processes will not be adequate for expeditiously resolving the complaint.

(c) Service. Any person filing a complaint must serve a copy of the complaint on the respondent, affected regulatory agencies, and others the complainant reasonably knows may be expected to be affected by the complaint. Service must be simultaneous with filing at the Commission for respondents. Simultaneous or overnight service is permissible for other affected entities. Simultaneous service can be accomplished by electronic mail in accordance with § 385.2010(f)(3), facsimile, express delivery, or messenger.

(d) Notice. Public notice of the complaint will be issued by the Commission.

(e) [Reserved]

(f) Answers, interventions and comments. Unless otherwise ordered by the Commission, answers, interventions, and comments to a complaint must be filed within 20 days after the complaint is filed. In cases where the complainant requests privileged treatment for information in its complaint, answers, interventions, and comments are due within 30 days after the complaint is filed. In the event there is an objection to the protective agreement, the Commission will establish when answers will be due.

(g) Complaint resolution paths. One of the following procedures may be used to resolve complaints:

(1) The Commission may assign a case to be resolved through alternative dispute resolution procedures in accordance with §§ 385.604-385.606, in cases where the affected parties consent, or the Commission may order the appointment of a settlement judge in accordance with § 385.603;

(2) The Commission may issue an order on the merits based upon the pleadings;

(3) The Commission may establish a hearing before an ALJ;

(h) Fast Track processing. (1) The Commission may resolve complaints using Fast Track procedures if the complaint requires expeditious resolution. Fast Track procedures may include expedited action on the pleadings by the Commission, expedited hearing before an ALJ, or expedited action on requests for stay, extension of time, or other relief by the Commission or an ALJ.

(2) A complainant may request Fast Track processing of a complaint by including such a request in its complaint, captioning the complaint in bold type face “COMPLAINT REQUESTING FAST TRACK PROCESSING,” and explaining why expedition is necessary as required by section 385.206(b)(11).

(3) Based on an assessment of the need for expedition, the period for filing answers, interventions and comments to a complaint requesting Fast Track processing may be shortened by the Commission from the time provided in section 385.206(f).

(4) After the answer is filed, the Commission will issue promptly an order specifying the procedure and any schedule to be followed.

(i) Simplified procedure for small controversies. A simplified procedure for complaints involving small controversies is found in section 385.218 of this subpart.

(j) Satisfaction. (1) If the respondent to a complaint satisfies such complaint, in whole or in part, either before or after an answer is filed, the complainant and the respondent must sign and file:

(i) A statement setting forth when and how the complaint was satisfied; and

(ii) A motion for dismissal of, or an amendment to, the complaint based on the satisfaction.

(2) The decisional authority may order the submission of additional information before acting on a motion for dismissal or an amendment under paragraph (c)(1)(ii) of this section.

[Order 225, 47 FR 19022, May 3, 1982, as amended by Order 602, 64 FR 17097, Apr. 8, 1999; Order 602-A, 64 FR 43608, Aug. 11, 1999; Order 647, 69 FR 32440, June 10, 2004; Order 769, 77 FR 65476, Oct. 29, 2012; Order 914, 90 FR 48406, Oct. 21, 2025]
The 20 cases that cite 18 C.F.R. § 385.206 most heavily, weighted by court and treatment. RelevanceNewestTreatment
cites § 385.206 3×cited by 22 cases
Where it cites § 385.206
“” 18 C.F.R. § 385.206 . Petitioners’ complaint alleged that Amer-en’s actions with regard to the discharge pipe and seawall violated the project license, as well as the National Environmental Policy Act (“NEPA”), the National Historic Preservation Act (“NHPA”), the Clean Water…”
Later courts cite it for
“federal control and responsibility for an action is not enough to trigger the eis requirement.” · 3 citing courts
cites § 385.206 2×cited by 41 cases
The case’s holding
The Mobile-Sierra presumption that contract rates are just and reasonable applies to challenges initiated by noncontracting parties as well as contracting parties.
Later courts cite it for
“generally purchase more capacity, i.e., rights to acquire energy, than necessary to meet their customers' anticipated demand.” · 2 citing courts
3
cites § 385.206 1×cited by 20 cases
Where it cites § 385.206
“Under the FPA, any person may file a complaint with FERO, 18 C.F.R. § 385.206 (a), and FERC’s decision is subject to judicial review in the D.”
Later courts cite it for
“requesting an amicus brief from the agency may represent a more efficient and expeditious alternative” · 2 citing courts
4
GREENWilliams Pipe Line Co. v. Empire Gas Corp., 76 F.3d 1491 (10th Cir. 1996).
cites § 385.206 2×cited by 31 cases
Where it cites § 385.206
“§§ 10701 (a); 10704(f); 10741(a); see also 18 C.F.R. §§ 385.206 , 385.207 (filing complaint or petition with regulatory agency).”
cites § 385.206 1×cited by 126 cases
Where it cites § 385.206
“See 18 CFR §385.206 (1986). IV We turn, finally, to the problem of “take-or-pay” contracts.”
The case’s holding
A natural gas producer must obtain commission permission under section 7(b) of the Natural Gas Act before abandoning its contractual obligations.
Later courts cite it for
“an agency need not solve every problem before it in the same proceeding.” · 6 citing courts
cites § 385.206 1×cited by 123 cases
Where it cites § 385.206
“Although the petitioners object that the complaint process, 18 C.F.R. § 385.206 , provides inadequate protection, it is evident that the Commission intended the complaint process to serve only as a back-up to the right-of-first-refusal mechanism.”
The case’s holding
The commission possesses the authority under the Natural Gas Act to mandate the unbundling of natural gas sales and transportation services to prevent monopoly power.
Later courts cite it for
“defer to the commission's expertise if it provides substantial evidence to support its choice and responds to substantial criticisms of that figure.” · 5 citing courts
7
GREENColumbia Gulf Transmission, LLC v. FERC, 106 F.4th 1220 (D.C. Cir. 2024).
cites § 385.206 3×cited by 3 cases
Where it cites § 385.206
“Petitioners Columbia Gulf and Range brought administrative complaints against Texas Eastern under 18 C.F.R. § 385.206 , asking FERC to require that Texas Eastern ensure its pipeline system’s operating pressure is sufficiently high to move the gas into Columbia Gulf’s pipeline…”
cites § 385.206 1×cited by 20 cases
Where it cites § 385.206
“See 18 C.F.R. § 385.206 (8). According to FERC, the evidence should have appeared in Marcus Hook’s original filings.”
The case’s holding
FERC must explain its reasoning on system benefit under the interconnection tariff, rather than relying on unexplained, shifting rationales, or its cost-allocation decision is arbitrary and must be remanded.
Later courts cite it for
“first-come, first-served queue.” · 2 citing courts
9
GREENPub. Citizen, Inc. v. FERC, 7 F.4th 1177 (D.C. Cir. 2021).
cites § 385.206 1×cited by 8 cases
Later courts cite it for
“distributors of electricity purchase commitments from generators to produce set amounts of electricity in the future.” · 2 citing courts
10
GREENWagner & Brown v. Anr Pipeline Co., 837 F.2d 199 (5th Cir. 1988).
cites § 385.206 1×cited by 38 cases
Where it cites § 385.206
“” 18 C.F.R. § 385.206 (1987). 9 .The contract provides that prepayments are nonrefundable but that ANR may make up the payments within five years by accepting quantities of gas corresponding to the payments.”
The case’s holding
A court may defer to an agency's primary jurisdiction only if the benefits of agency review exceed the costs imposed on the parties.
Later courts cite it for
“primary jurisdiction is a judicially created doctrine whereby a court of competent jurisdiction may dismiss or stay an action pending a resolution of some portion of the actions by an administrative agency.” · 4 citing courts
11
GREENDiLaura v. Power Auth. of State of NY, 654 F. Supp. 641 (W.D.N.Y. 1987).
cites § 385.206 1×cited by 8 cases
Where it cites § 385.206
“§ 825e; 18 C.F.R. § 385.206 (a). Upon review FERC concluded that “the Niagara Power Project was not the cause of the ice jamming and flooding in question.”
12
GREENLouisville G&E Co. v. FERC, 988 F.3d 841 (6th Cir. 2021).
cites § 385.206 1×cited by 2 cases
Where it cites § 385.206
“§ 825e; 18 C.F.R. § 385.206 (a). The Commission agreed with Owensboro that the contract required Louisville Gas to absorb all the costs that Owensboro had incurred from MISO since February, 2018.”
13
GREENGeorgia Indus. Grp. v. Fed. Energy Regulatory Comm'n, 137 F.3d 1358 (D.C. Cir. 1998).
cites § 385.206 1×cited by 5 cases
Summary
No passage or summary on file for this case yet.
14
GREENCity of Albany v. Fed. Energy Regulatory Comm'n, 7 F.3d 671 (7th Cir. 1993).
cites § 385.206 1×cited by 3 cases
Summary
No passage or summary on file for this case yet.
cites § 385.206 1×cited by 3 cases
Where it cites § 385.206
“FERC stated in its original order: “Because we find it possible to assess the reasonableness of [Union Electric’s] fees on the existing record, we will not assign the proceeding to an Administrative Law Judge for a formal evidentiary hearing, as the Coalition requests.” 90 FERC…”
The case’s holding
Courts defer to an agency's interpretation of a statute if that interpretation is consistent with the plain meaning or is a permissible construction of an ambiguous statute.
Later courts cite it for
“unless it violates the constitution or a federal statute, or unless the interpretation is 'plainly erroneous or inconsistent with the regulation.” · 7 citing courts
16
GREENCity of Vernon v. Fed. Energy Regulatory Comm'n, 983 F.2d 1089 (D.C. Cir. 1993).
cites § 385.206 1×cited by 1 case
Where it cites § 385.206
“18 CFR § 385.206 (1992). Municipalities may challenge any action of a public utility such as Edison that violates a statute administered by FERC simply by filing a complaint with the Commission.”
17
GREENPac. Gas & Elec. Co. v. Fed. Energy Regulatory Comm'n, 746 F.2d 1383 (9th Cir. 1984).
cites § 385.206 1×cited by 3 cases
Where it cites § 385.206
“6 of the FERC Rules, 18 CFR § 385.206 . The complaint sought declaration of SMUD’s rights under the agreement to transmission service over the Pacific Intertie.”
The case’s holding
An agency may decide a contract dispute summarily, without a formal hearing, when no material facts are disputed, and courts defer to its reasonable interpretation of its own rules and procedures.
Later courts cite it for
“ferc was presented with highly technical legal analyses by all of the concerned parties, ... and all the parties were afforded a full opportunity to respond in writing, to supply exhibits, and to present affidavits.” · 2 citing courts
18
NO FLAGVill. of Ilion v. Fed. Energy Regulatory Comm'n, 790 F.2d 212 (2d Cir. 1986).
cites § 385.206 1×cited by 2 cases
Where it cites § 385.206
“§ 825e, see also 18 C.F.R. § 385.206 , et seq. challenging PASNY’s action and seeking a reallocation of the pool of preference power which would increase the allotment of such power to it.”
19
NO FLAGSaale Fam. L.P. v. Spire STL Pipeline, LLC, No. 4:19-cv-01402 (E.D. Mo. Nov. 27, 2019).
cites § 385.206 3×cited by 0 casesunknown
Where it cites § 385.206
“Spire’s argument fails at the first prong because 18 C.F.R. § 385.206 does not provide an exclusive cause of action for any of the claims asserted in Plaintiffs’ Complaint.”
20
NO FLAGBrackett v. Columbia Gulf Transmission, LLC, No. 1:20-cv-00168 (W.D. Ky. June 27, 2024).
cites § 385.206 3×cited by 0 casesunknown
Where it cites § 385.206
“6 Defendants contend that 18 C.F.R. § 385.206 (a), which contains a complaint procedure for violations of “any statute, rule, order, or other law administered by [FERC],” is the proper method for Plaintiffs to claim that the Compressor Station does not meet FERC’s noise…”

Show all 24 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
198420042024

One bar per year. Tallest: 3 cases in 2024. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
D.C. Cir.71st Cir.2SCOTUS210th Cir.12d Cir.14th Cir.15th Cir.16th Cir.1

The 8 courts with the most citing cases, of 16 courts in all.

By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Show all 24 citing cases (list view) →

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com