Skip to main content
C.F.R.Title 40Chapter I—Environmental Protection AgencySubchapter D—Water ProgramsPart 122—Epa Administered Permit Programs: The National Pollutant Discharge Elimination SystemSubpart C—Permit Conditions

40 C.F.R. § 122.47 (2026)

Schedules of compliance

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 2005–2016 5citing cases
At a glance

Courts have cited this section in 5 opinions since 2005.

(a) General (applicable to State programs, see § 123.25). The permit may, when appropriate, specify a schedule of compliance leading to compliance with CWA and regulations.

(1) Time for compliance. Any schedules of compliance under this section shall require compliance as soon as possible, but not later than the applicable statutory deadline under the CWA.

(2) The first NPDES permit issued to a new source or a new discharger shall contain a schedule of compliance only when necessary to allow a reasonable opportunity to attain compliance with requirements issued or revised after commencement of construction but less than three years before commencement of the relevant discharge. For recommencing dischargers, a schedule of compliance shall be available only when necessary to allow a reasonable opportunity to attain compliance with requirements issued or revised less than three years before recommencement of discharge.

(3) Interim dates. Except as provided in paragraph (b)(1)(ii) of this section, if a permit establishes a schedule of compliance which exceeds 1 year from the date of permit issuance, the schedule shall set forth interim requirements and the dates for their achievement.

(i) The time between interim dates shall not exceed 1 year, except that in the case of a schedule for compliance with standards for sewage sludge use and disposal, the time between interim dates shall not exceed six months.

(ii) If the time necessary for completion of any interim requirement (such as the construction of a control facility) is more than 1 year and is not readily divisible into stages for completion, the permit shall specify interim dates for the submission of reports of progress toward completion of the interim requirements and indicate a projected completion date.

Note:

Examples of interim requirements include: (a) Submit a complete Step 1 construction grant (for POTWs); (b) let a contract for construction of required facilities; (c) commence construction of required facilities; (d) complete construction of required facilities.

(4) Reporting. The permit shall be written to require that no later than 14 days following each interim date and the final date of compliance, the permittee shall notify the Director in writing of its compliance or noncompliance with the interim or final requirements, or submit progress reports if paragraph (a)(3)(ii) is applicable.

(b) Alternative schedules of compliance. An NPDES permit applicant or permittee may cease conducting regulated activities (by terminating of direct discharge for NPDES sources) rather than continuing to operate and meet permit requirements as follows:

(1) If the permittee decides to cease conducting regulated activities at a given time within the term of a permit which has already been issued:

(i) The permit may be modified to contain a new or additional schedule leading to timely cessation of activities; or

(ii) The permittee shall cease conducting permitted activities before non-compliance with any interim or final compliance schedule requirement already specified in the permit.

(2) If the decision to cease conducting regulated activities is made before issuance of a permit whose term will include the termination date, the permit shall contain a schedule leading to termination which will ensure timely compliance with applicable requirements no later than the statutory deadline.

(3) If the permittee is undecided whether to cease conducting regulated activities, the Director may issue or modify a permit to contain two schedules as follows:

(i) Both schedules shall contain an identical interim deadline requiring a final decision on whether to cease conducting regulated activities no later than a date which ensures sufficient time to comply with applicable requirements in a timely manner if the decision is to continue conducting regulated activities;

(ii) One schedule shall lead to timely compliance with applicable requirements, no later than the statutory deadline;

(iii) The second schedule shall lead to cessation of regulated activities by a date which will ensure timely compliance with applicable requirements no later than the statutory deadline.

(iv) Each permit containing two schedules shall include a requirement that after the permittee has made a final decision under paragraph (b)(3)(i) of this section it shall follow the schedule leading to compliance if the decision is to continue conducting regulated activities, and follow the schedule leading to termination if the decision is to cease conducting regulated activities.

(4) The applicant's or permittee's decision to cease conducting regulated activities shall be evidenced by a firm public commitment satisfactory to the Director, such as a resolution of the board of directors of a corporation.

[48 FR 14153, Apr. 1, 1983, as amended at 49 FR 38050, Sept. 26, 1984; 50 FR 6940, Feb. 19, 1985; 54 FR 18784, May 2, 1989; 65 FR 30909, May 15, 2000]
The 5 cases that cite 40 C.F.R. § 122.47 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
cites § 122.47 1×cited by 30 cases
Where it cites § 122.47
“We recognize that a schedule of compliance is “an enforceable sequence of actions or operations leading to compliance with an effluent limitation, other limitation, prohibition, or standard.”
The case’s holding
A permitting authority is not required to impose specific numeric effluent limitations to satisfy the maximum extent practicable standard for municipal stormwater permits.
Later courts cite it for
“it is also difficult to discern the amount of pollutant that any one discharger contributes to a waterbody because municipalities have so many outfalls, or discharge points, leading into the waters.” · 4 citing courts
2
GREENBldg. Indus. Ass'n v. State Water Resources Control Bd., 124 Cal. App. 4th 866 (Ct. App. 2005).
cites § 122.47 1×cited by 47 cases
Where it cites § 122.47
“(See 40 C.F.R. § 122.47 .) There is nothing in this record to show the Municipalities will be subject to immediate penalties for violation of water quality standards.”
The case’s holding
The Clean Water Act authorizes regulatory agencies to impose water quality standards in municipal storm sewer permits that exceed the maximum extent practicable standard.
Later courts cite it for
“we are not bound by the legal determinations made by the state or regional agencies, . . . we must give appropriate consideration to an administrative agency's expertise underlying its interpretation of an applicable statute.” · 6 citing courts
cites § 122.47 4×cited by 20 cases
Where it cites § 122.47
“" 40 C.F.R. § 122.47 (a) (2008). A "schedule of compliance" means "a schedule of remedial measures including an enforceable sequence of actions or operations leading to compliance with an effluent limitation, other limitation, prohibition, or standard.”
Later courts cite it for
“when a statute or regulation is silent on a precise issue, that silence may be evidence of ambiguity.” · 4 citing courts
cites § 122.47 1×cited by 9 cases
Where it cites § 122.47
“§ 1362 (17); 40 C.F.R. § 122.47 . Indeed, the current draft permit prepared by the NYDEC in this case includes a compliance schedule that requires the City to investigate both technological and structural solutions to the turbidity problem and to implement those solutions…”
Later courts cite it for
“in calculating civil penalties under the cwa, the court may begin either with the violator's estimated economic benefit from noncompliance (known as the 'bottom-up' method) or with. the,. statutory maximum allowable penalty (known as the 'top-down' method).” · 2 citing courts
5
GREENMiccosukee Tribe of Indians of Florida v. United States, 706 F. Supp. 2d 1296 (S.D. Fla. 2010).
cites § 122.47 1×cited by 1 case
Where it cites § 122.47
“, 40 C.F.R. 122.47 (allowing for limited schedules of compliance); see also 40 C.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
200520102016

One bar per year. Tallest: 1 case in 2005. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
2d Cir.1Cal. Ct. App.1S.D. Fla.1Md.1Minn.1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.