C.F.R. homeSearch C.F.R.
C.F.R.Title 40Chapter I—Environmental Protection AgencySubchapter D—Water ProgramsPart 125—Criteria and Standards for the National Pollutant Discharge Elimination SystemSubpart N—Requirements Applicable to Cooling Water Intake Structures for New Offshore Oil and Gas Extraction Facilities Under Section 316(b) of the Act

40 C.F.R. § 125.131 (2026)

Who is subject to this subpart?

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 2010 2citing cases
At a glance

Courts have cited this section in 2 opinions since 2010.

(a) This subpart applies to a new offshore oil and gas extraction facility if it meets all of the following criteria:

(1) It is a point source that uses or proposes to use a cooling water intake structure;

(2) It has at least one cooling water intake structure that uses at least 25 percent of the water it withdraws for cooling purposes as specified in paragraph (c) of this section; and

(3) It has a design intake flow greater than two (2) million gallons per day (MGD).

(b) Use of a cooling water intake structure includes obtaining cooling water by any sort of contract or arrangement with an independent supplier (or multiple suppliers) of cooling water if the supplier or suppliers withdraw(s) water from waters of the United States. Use of cooling water does not include obtaining cooling water from a public water system or the use of treated effluent that otherwise would be discharged to a water of the U.S.

(c) The threshold requirement that at least 25 percent of water withdrawn be used for cooling purposes must be measured on an average monthly basis. A new offshore oil and gas extraction facility meets the 25 percent cooling water threshold if, based on the new facility's design, any monthly average over a year for the percentage of cooling water withdrawn is expected to equal or exceed 25 percent of the total water withdrawn.

(d) Neither this subpart nor Subpart I of this part applies to seafood processing vessels or offshore liquefied natural gas import terminals that are new facilities as defined in 40 CFR 125.83. Seafood processing vessels and offshore liquefied natural gas import terminals must meet requirements established by the Director on a case-by-case, best professional judgment (BPJ) basis.

The 2 cases that cite 40 C.F.R. § 125.131 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENConocoPhillips Co. v. United States Env't Prot. Agency, 612 F.3d 822 (5th Cir. 2010).
cites § 125.131 1×cited by 24 cases
Where it cites § 125.131
“40 C.F.R. § 125.131 (a). 69 . 71 Fed.Reg.”
Later courts cite it for
“nouns joined by coordinating conjunctions are usually treated as a single, compounded unit, and a postmodifying prepositional phrase is most naturally read to modify that single unit.” · 2 citing courts
2
GREENConocoPhillips Co v. EPA, No. 06-60662 (5th Cir. Aug. 9, 2010).
cites § 125.131 1×cited by 0 cases
Summary
No passage or summary on file for this case yet.

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.