52.216-7 Allowable Cost and Payment.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1997–2025 33citing cases
At a glance

Courts have cited this section in 33 opinions since 1997, 3 of them in the last five years.

As prescribed in 16.307(a), insert the following clause:

Allowable Cost and Payment (AUG 2018)

(a) Invoicing. (1) The Government will make payments to the Contractor when requested as work progresses, but (except for small business concerns) not more often than once every 2 weeks, in amounts determined to be allowable by the Contracting Officer in accordance with Federal Acquisition Regulation (FAR) subpart 31.2 in effect on the date of this contract and the terms of this contract. The Contractor may submit to an authorized representative of the Contracting Officer, in such form and reasonable detail as the representative may require, an invoice or voucher supported by a statement of the claimed allowable cost for performing this contract.

(2) Contract financing payments are not subject to the interest penalty provisions of the Prompt Payment Act. Interim payments made prior to the final payment under the contract are contract financing payments, except interim payments if this contract contains Alternate I to the clause at 52.232-25.

(3) The designated payment office will make interim payments for contract financing on the __ [Contracting Officer insert day as prescribed by agency head; if not prescribed, insert “30th”] day after the designated billing office receives a proper payment request.

In the event that the Government requires an audit or other review of a specific payment request to ensure compliance with the terms and conditions of the contract, the designated payment office is not compelled to make payment by the specified due date.

(b) Reimbursing costs. (1) For the purpose of reimbursing allowable costs (except as provided in paragraph (b)(2) of the clause, with respect to pension, deferred profit sharing, and employee stock ownership plan contributions), the term costs includes only—

(i) Those recorded costs that, at the time of the request for reimbursement, the Contractor has paid by cash, check, or other form of actual payment for items or services purchased directly for the contract;

(ii) When the Contractor is not delinquent in paying costs of contract performance in the ordinary course of business, costs incurred, but not necessarily paid, for—

(A) Supplies and services purchased directly for the contract and associated financing payments to subcontractors, provided payments determined due will be made—

(1) In accordance with the terms and conditions of a subcontract or invoice; and

(2) Ordinarily within 30 days of the submission of the Contractor's payment request to the Government;

(B) Materials issued from the Contractor's inventory and placed in the production process for use on the contract;

(C) Direct labor;

(D) Direct travel;

(E) Other direct in-house costs; and

(F) Properly allocable and allowable indirect costs, as shown in the records maintained by the Contractor for purposes of obtaining reimbursement under Government contracts; and

(iii) The amount of financing payments that have been paid by cash, check, or other forms of payment to subcontractors.

(2) Accrued costs of Contractor contributions under employee pension plans shall be excluded until actually paid unless—

(i) The Contractor's practice is to make contributions to the retirement fund quarterly or more frequently; and

(ii) The contribution does not remain unpaid 30 days after the end of the applicable quarter or shorter payment period (any contribution remaining unpaid shall be excluded from the Contractor's indirect costs for payment purposes).

(3) Notwithstanding the audit and adjustment of invoices or vouchers under paragraph (g) below, allowable indirect costs under this contract shall be obtained by applying indirect cost rates established in accordance with paragraph (d) below.

(4) Any statements in specifications or other documents incorporated in this contract by reference designating performance of services or furnishing of materials at the Contractor's expense or at no cost to the Government shall be disregarded for purposes of cost-reimbursement under this clause.

(c) Small business concerns. A small business concern may receive more frequent payments than every 2 weeks.

(d) Final indirect cost rates. (1) Final annual indirect cost rates and the appropriate bases shall be established in accordance with subpart 42.7 of the Federal Acquisition Regulation (FAR) in effect for the period covered by the indirect cost rate proposal.

(2)(i) The Contractor shall submit an adequate final indirect cost rate proposal to the Contracting Officer (or cognizant Federal agency official) and auditor within the 6-month period following the expiration of each of its fiscal years. Reasonable extensions, for exceptional circumstances only, may be requested in writing by the Contractor and granted in writing by the Contracting Officer. The Contractor shall support its proposal with adequate supporting data.

(ii) The proposed rates shall be based on the Contractor's actual cost experience for that period. The appropriate Government representative and the Contractor shall establish the final indirect cost rates as promptly as practical after receipt of the Contractor's proposal.

(iii) An adequate indirect cost rate proposal shall include the following data unless otherwise specified by the cognizant Federal agency official:

(A) Summary of all claimed indirect expense rates, including pool, base, and calculated indirect rate.

(B) General and Administrative expenses (final indirect cost pool). Schedule of claimed expenses by element of cost as identified in accounting records (Chart of Accounts).

(C) Overhead expenses (final indirect cost pool). Schedule of claimed expenses by element of cost as identified in accounting records (Chart of Accounts) for each final indirect cost pool.

(D) Occupancy expenses (intermediate indirect cost pool). Schedule of claimed expenses by element of cost as identified in accounting records (Chart of Accounts) and expense reallocation to final indirect cost pools.

(E) Claimed allocation bases, by element of cost, used to distribute indirect costs.

(F) Facilities capital cost of money factors computation.

(G) Reconciliation of books of account (i.e., General Ledger) and claimed direct costs by major cost element.

(H) Schedule of direct costs by contract and subcontract and indirect expense applied at claimed rates, as well as a subsidiary schedule of Government participation percentages in each of the allocation base amounts.

(I) Schedule of cumulative direct and indirect costs claimed and billed by contract and subcontract.

(J) Subcontract information. Listing of subcontracts awarded to companies for which the contractor is the prime or upper-tier contractor (include prime and subcontract numbers; subcontract value and award type; amount claimed during the fiscal year; and the subcontractor name, address, and point of contact information).

(K) Summary of each time-and-materials and labor-hour contract information, including labor categories, labor rates, hours, and amounts; direct materials; other direct costs; and, indirect expense applied at claimed rates.

(L) Reconciliation of total payroll per IRS form 941 to total labor costs distribution.

(M) Listing of decisions/agreements/approvals and description of accounting/organizational changes.

(N) Certificate of final indirect costs (see 52.242-4, Certification of Final Indirect Costs).

(O) Contract closing information for contracts physically completed in this fiscal year (include contract number, period of performance, contract ceiling amounts, contract fee computations, level of effort, and indicate if the contract is ready to close).

(iv) The following supplemental information is not required to determine if a proposal is adequate, but may be required during the audit process:

(A) Comparative analysis of indirect expense pools detailed by account to prior fiscal year and budgetary data.

(B) General organizational information and limitation on allowability of compensation for certain contractor personnel. See 31.205-6(p). Additional salary reference information is available at https://www.whitehouse.gov/wp-content/uploads/2017/11/ContractorCompensationCapContractsAwardedBeforeJune24.pdf and https://www.whitehouse.gov/wp-content/uploads/2017/11/ContractorCompensationCapContractsAwardedafterJune24.pdf.

(C) Identification of prime contracts under which the contractor performs as a subcontractor.

(D) Description of accounting system (excludes contractors required to submit a CAS Disclosure Statement or contractors where the description of the accounting system has not changed from the previous year's submission).

(E) Procedures for identifying and excluding unallowable costs from the costs claimed and billed (excludes contractors where the procedures have not changed from the previous year's submission).

(F) Certified financial statements and other financial data (e.g., trial balance, compilation, review, etc.).

(G) Management letter from outside CPAs concerning any internal control weaknesses.

(H) Actions that have been and/or will be implemented to correct the weaknesses described in the management letter from subparagraph (G) of this section.

(I) List of all internal audit reports issued since the last disclosure of internal audit reports to the Government.

(J) Annual internal audit plan of scheduled audits to be performed in the fiscal year when the final indirect cost rate submission is made.

(K) Federal and State income tax returns.

(L) Securities and Exchange Commission 10-K annual report.

(M) Minutes from board of directors meetings.

(N) Listing of delay claims and termination claims submitted which contain costs relating to the subject fiscal year.

(O) Contract briefings, which generally include a synopsis of all pertinent contract provisions, such as: Contract type, contract amount, product or service(s) to be provided, contract performance period, rate ceilings, advance approval requirements, pre-contract cost allowability limitations, and billing limitations.

(v) The Contractor shall update the billings on all contracts to reflect the final settled rates and update the schedule of cumulative direct and indirect costs claimed and billed, as required in paragraph (d)(2)(iii)(I) of this section, within 60 days after settlement of final indirect cost rates.

(3) The Contractor and the appropriate Government representative shall execute a written understanding setting forth the final indirect cost rates. The understanding shall specify (i) the agreed-upon final annual indirect cost rates, (ii) the bases to which the rates apply, (iii) the periods for which the rates apply, (iv) any specific indirect cost items treated as direct costs in the settlement, and (v) the affected contract and/or subcontract, identifying any with advance agreements or special terms and the applicable rates. The understanding shall not change any monetary ceiling, contract obligation, or specific cost allowance or disallowance provided for in this contract. The understanding is incorporated into this contract upon execution.

(4) Failure by the parties to agree on a final annual indirect cost rate shall be a dispute within the meaning of the Disputes clause.

(5) Within 120 days (or longer period if approved in writing by the Contracting Officer) after settlement of the final annual indirect cost rates for all years of a physically complete contract, the Contractor shall submit a completion invoice or voucher to reflect the settled amounts and rates. The completion invoice or voucher shall include settled subcontract amounts and rates. The prime contractor is responsible for settling subcontractor amounts and rates included in the completion invoice or voucher and providing status of subcontractor audits to the contracting officer upon request.

(6)(i) If the Contractor fails to submit a completion invoice or voucher within the time specified in paragraph (d)(5) of this clause, the Contracting Officer may—

(A) Determine the amounts due to the Contractor under the contract; and

(B) Record this determination in a unilateral modification to the contract.

(ii) This determination constitutes the final decision of the Contracting Officer in accordance with the Disputes clause.

(e) Billing rates. Until final annual indirect cost rates are established for any period, the Government shall reimburse the Contractor at billing rates established by the Contracting Officer or by an authorized representative (the cognizant auditor), subject to adjustment when the final rates are established. These billing rates—

(1) Shall be the anticipated final rates; and

(2) May be prospectively or retroactively revised by mutual agreement, at either party's request, to prevent substantial overpayment or underpayment.

(f) Quick-closeout procedures. Quick-closeout procedures are applicable when the conditions in FAR 42.708(a) are satisfied.

(g) Audit. At any time or times before final payment, the Contracting Officer may have the Contractor's invoices or vouchers and statements of cost audited. Any payment may be (1) reduced by amounts found by the Contracting Officer not to constitute allowable costs or (2) adjusted for prior overpayments or underpayments.

(h) Final payment. (1) Upon approval of a completion invoice or voucher submitted by the Contractor in accordance with paragraph (d)(5) of this clause, and upon the Contractor's compliance with all terms of this contract, the Government shall promptly pay any balance of allowable costs and that part of the fee (if any) not previously paid.

(2) The Contractor shall pay to the Government any refunds, rebates, credits, or other amounts (including interest, if any) accruing to or received by the Contractor or any assignee under this contract, to the extent that those amounts are properly allocable to costs for which the Contractor has been reimbursed by the Government. Reasonable expenses incurred by the Contractor for securing refunds, rebates, credits, or other amounts shall be allowable costs if approved by the Contracting Officer. Before final payment under this contract, the Contractor and each assignee whose assignment is in effect at the time of final payment shall execute and deliver—

(i) An assignment to the Government, in form and substance satisfactory to the Contracting Officer, of refunds, rebates, credits, or other amounts (including interest, if any) properly allocable to costs for which the Contractor has been reimbursed by the Government under this contract; and

(ii) A release discharging the Government, its officers, agents, and employees from all liabilities, obligations, and claims arising out of or under this contract, except—

(A) Specified claims stated in exact amounts, or in estimated amounts when the exact amounts are not known;

(B) Claims (including reasonable incidental expenses) based upon liabilities of the Contractor to third parties arising out of the performance of this contract; provided, that the claims are not known to the Contractor on the date of the execution of the release, and that the Contractor gives notice of the claims in writing to the Contracting Officer within 6 years following the release date or notice of final payment date, whichever is earlier; and

(C) Claims for reimbursement of costs, including reasonable incidental expenses, incurred by the Contractor under the patent clauses of this contract, excluding, however, any expenses arising from the Contractor's indemnification of the Government against patent liability.

(End of clause)

Alternate I (FEB 1997). As prescribed in 16.307(a)(2), substitute the following paragraph (b)(1)(iii) for paragraph (b)(1)(iii) of the basic clause:

(b)(1)(iii) The amount of progress and other payments to the Contractor's subcontractors that either have been paid, or that the Contractor is required to pay pursuant to the clause of this contract entitled “Prompt Payment for Construction Contracts.” Payments shall be made by cash, check, or other form of payment to the Contractor's subcontractors under similar cost standards.

Alternate II (AUG 2012). As prescribed in 16.307(a)(3), substitute the following paragraph (a)(1) for paragraph (a)(1) of the basic clause:

(a)(1) The Government will make payments to the Contractor when requested as work progresses, but not more often than once every two weeks, in amounts determined to be allowable by the Contracting Officer in accordance with FAR subpart 31.3 in effect on the date of this contract and the terms of this contract. The Contractor may submit to an authorized representative of the Contracting Officer, in such form and reasonable detail as the representative may require, an invoice or voucher supported by a statement of the claimed allowable cost for performing this contract.

Alternate III (AUG 2012). As prescribed in 16.307(a)(4), substitute the following paragraph (a)(1) for paragraph (a)(1) of the basic clause:

(a)(1) The Government will make payments to the Contractor when requested as work progresses, but not more often than once every two weeks, in amounts determined to be allowable by the Contracting Officer in accordance with FAR subpart 31.6 in effect on the date of this contract and the terms of this contract. The Contractor may submit to an authorized representative of the Contracting Officer, in such form and reasonable detail as the representative may require, an invoice or voucher supported by a statement of the claimed allowable cost for performing this contract.

Alternate IV (AUG 2012). As prescribed in 16.307(a)(5), substitute the following paragraph (a)(1) for paragraph (a)(1) of the basic clause:

(a)(1) The Government will make payments to the Contractor when requested as work progresses, but not more often than once every two weeks, in amounts determined to be allowable by the Contracting Officer in accordance with FAR subpart 31.7 in effect on the date of this contract and the terms of this contract. The Contractor may submit to an authorized representative of the Contracting Officer, in such form and reasonable detail as the representative may require, an invoice or voucher supported by a statement of the claimed allowable cost for performing this contract.

[48 FR 42478, Sept. 19, 1983] Editorial Note:For Federal Register citations affecting section 52.216-7, see the List of CFR Sections Affected, which appears in the Finding Aids section of the printed volume and at www.govinfo.gov.
The 20 cases that cite 48 C.F.R. § 52.216-7 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENUnited States ex rel. Hassan Foreman v. AECOM, 19 F.4th 85 (2d Cir. 2021).
cites § 52.216-7 1×cited by 185 cases
Where it cites § 52.216-7
“; 48 C.F.R. § 52.216-7 (h)(1) ("Upon 9 approval of a completion invoice or voucher submitted by the Contractor in 10 accordance with paragraph (d)(5) of this clause, and upon the Contractor's 11 compliance with all terms of this contract, the Government shall promptly pay 12 any…”
The case’s holding
A district court may only consider the facts alleged in a complaint, documents attached as exhibits, and documents incorporated by reference when ruling on a motion to dismiss.
Later courts cite it for
“i whether the government expressly designates compliance with a particular statutory, regulatory, or contractual requirement as a condition of payment; ii the government's response to noncompliance with the relevant contractual, statutory, or regulatory provision; and iii whether the defendants' alleged noncompliance was 'minor or insubstantial.” · 7 citing courts
2
GREENUnited States v. Dyncorp Int'l, LLC, 253 F. Supp. 3d 89 (D.D.C. 2017).
cites § 52.216-7 2×cited by 23 cases
Where it cites § 52.216-7
“48 C.F.R. § 52.216-7 (a), (g). If a claimed cost is “expressly unallowable”—that is, “specifically named and stated to be unallowable”— penalties are assessed against the contractor.”
Later courts cite it for
“it is common sense that the government would not pay claims if it knew that they were outrageously excessive” · 3 citing courts
3
GREENUnited States v. Intrados/Int'l Mgmt. Grp., 265 F. Supp. 2d 1 (D.D.C. 2002).
cites § 52.216-7 3×cited by 22 cases
Where it cites § 52.216-7
“216-7 of the Federal Acquisition Regulation, as amended, 48 C.F.R. § 52.216-7 , defines the term “allowable *4 cost,” which is incorporated into the contract’s terms.”
Later courts cite it for
“fca plaintiff need not allege with specificity every element of its cause of action if the complaint contains allegations from which an inference may be drawn that the plaintiff will produce evidence on the essential elements.” · 3 citing courts
4
GREENATK Thiokol, Inc. v. United States, 76 Fed. Cl. 654 (Fed. Cl. 2007).
cites § 52.216-7 7×cited by 4 cases
Where it cites § 52.216-7
“(citing 48 C.F.R. §§ 52.216-7 (a), (e)). Therefore, any monetary relief awarded by the court would be treated only as “an interim payment subject to future reconciliation upon contract closeout[.”
5
GREENDirectv Grp., Inc. v. United States, 670 F.3d 1370 (Fed. Cir. 2012).
cites § 52.216-7 7×cited by 19 cases
Where it cites § 52.216-7
“More specifically, the trial court found that neither the Allowable Cost and Payment clause, 48 C.F.R. § 52.216-7 (h)(2), nor the Credits provision, 48 C.”
Later courts cite it for
“as a matter of elementary grammar, the statute's 27 use of 'such' is a demonstrative adjective, and it must refer to a clear antecedent.” · 2 citing courts
6
GREENTeledyne, Inc. v. United States, 50 Fed. Cl. 155 (Fed. Cl. 2001).
cites § 52.216-7 2×cited by 27 cases
Where it cites § 52.216-7
“48 C.F.R. §§ 52.216-7 (h)(2) (1998), 31.201-5 (1998).”
The case’s holding
The original Cost Accounting Standard 413.50(c)(12) permits only cost adjustments and does not allow the government to recover pension surpluses from firm-fixed-price contracts.
Later courts cite it for
“teledyne retained responsibility for the pensions, but not the contracts over which the gains and losses attributable to the government's share of pension costs would ordinarily be amortized.” · 3 citing courts
7
GREENHercules Inc. v. United States, 292 F.3d 1378 (Fed. Cir. 2002).
cites § 52.216-7 1×cited by 106 cases
Where it cites § 52.216-7
“48 C.F.R. § 52.216-7 (h)(2) (2001). The incorporated “Credits” clause, FAR § 31.”
The case’s holding
Contract interpretation begins with the plain language of the written agreement and must effectuate its spirit and purpose by giving reasonable meaning to all parts of the contract.
Later courts cite it for
“contract must be construed to effectuate its spirit and purpose giving reasonable meaning to all parts of the contract” · 25 citing courts
8
GREENDIRECTV Grp., Inc. v. United States, 89 Fed. Cl. 302 (Fed. Cl. 2009).
cites § 52.216-7 5×cited by 4 cases
Where it cites § 52.216-7
“216-7(h), 48 C.F.R. § 52.216-7 (h) (2002), and the Credits clause, FAR 31.”
Later courts cite it for
“where the undisputed evidence demonstrates that the government received the value of directv's cas 413 segment closing obligation through a cost reduction from the successor contractors, the existence of a government agreement in which the government protected its interest in the pension asset surplus through a novation agreement or other means is not material.” · 1 citing court
cites § 52.216-7 1×cited by 12 cases
Where it cites § 52.216-7
“, 48 C.F.R. § 52.216-7 (g) (granting authority for the Contracting Officer to perform an audit and reduce payment for non-allowable costs or adjust for ■ overpayments); id.”
Later courts cite it for
“because these arguments were not raised in the district court, we do not consider them.” · 2 citing courts
10
GREENViacom, Inc. v. United States, 70 Fed. Cl. 649 (Fed. Cl. 2006).
cites § 52.216-7 2×cited by 9 cases
Where it cites § 52.216-7
“” 48 C.F.R. § 52.216-7 (b)(2) (1996). The current version provides: "Accrued costs of Contractor contributions under employee pension plans shall be excluded until actually paid .”
11
GREENHercules Inc. v. United States, 49 Fed. Cl. 80 (Fed. Cl. 2001).
cites § 52.216-7 2×cited by 6 cases
Where it cites § 52.216-7
“48 C.F.R. § 52.216-7 (h)(2). The contract also incorporates the “TAXES” provision of the Federal Acquisition Regulations (FAR), which states, in relevant part: (d) Any taxes, interest, or penalties that were allowed as contract costs and are refunded to the contractor shall be…”
12
GREENRes Rei Dev., Inc. v. United States, 126 Fed. Cl. 535 (Fed. Cl. 2016).
cites § 52.216-7 1×cited by 7 cases
Where it cites § 52.216-7
“AR at 663, 667 (incorporating by reference 48 C.F.R. §§ 52.216-7 , 52.216-8), 686. That contract will have a five-year ordering period and a ceiling value of $150,000,000.”
13
GREENCBS Corp. v. United States, 90 Fed. Cl. 456 (Fed. Cl. 2009).
cites § 52.216-7 7×cited by 1 case
Where it cites § 52.216-7
“216-7, 48 C.F.R. § 52.216-7 (2002), 3 CBS cannot claim reimbursement for pension costs attributable to the pension deficit CBS transferred to Northrop Grumman as part of the ESG sale.”
14
GREENGen. Elec. Co. v. United States, 84 Fed. Cl. 129 (Fed. Cl. 2008).
cites § 52.216-7 1×cited by 10 cases
Where it cites § 52.216-7
“” 48 C.F.R. § 52.216-7 (h)(2). The provision is then implemented through the Credits clause, which states that, "The applicable portion of any income, rebate, allowance, or other credit relating to any allowable cost and received by or accruing to the contractor shall be…”
The case’s holding
Under the original Cost Accounting Standard 413, a segment closing adjustment covers the entire closed segment, and the government must credit any cost benefit it derived from transferred pension surplus.
Later courts cite it for
“in no case shall the government recover costs greater than the increased cost ... to the government, in the aggregate, on the relevant contracts subject to the price adjustment, unless the contractor made a change in its cost accounting practices of which it was aware or should have been aware at the time of the price negotiation and which it failed to disclose to the government.” · 1 citing court
15
GREENUnited States Enrichment Corp. v. United States, 121 Fed. Cl. 532 (Fed. Cl. 2015).
cites § 52.216-7 1×cited by 9 cases
Where it cites § 52.216-7
“216-7 of the Federal Acquisition Regulations (“FAR”), 48 C.F.R. § 52.216-7 , and USEC’s contracts with DOE, USEC is entitled to recover its allowable indirect costs (e.”
16
GREENGen. Motors Corp. v. United States, 66 Fed. Cl. 153 (Fed. Cl. 2005).
cites § 52.216-7 1×cited by 9 cases
Where it cites § 52.216-7
“48 C.F.R. § 52.216-7 (b)(2). Finally, CAS 412 provides that annual pension costs that were assignable to a particular cost accounting period are not allocable to the cost objectives of that period unless “liquidation of the liability for such [pension] cost can be compelled or…”
17
GREENInfo. Sys. & Network Corp. v. United States, 437 F.3d 1173 (Fed. Cir. 2006).
cites § 52.216-7 1×cited by 7 cases
Where it cites § 52.216-7
“See 48 C.F.R. § 52.216-7 (d)(2)(ii) (2004). A cost is allowable only when the cost complies with all of the following requirements: (1) Reasonableness.”
18
GREENKellogg Brown & Root Servs. Inc. v. United States, 103 Fed. Cl. 714 (Fed. Cl. 2012).
cites § 52.216-7 1×cited by 7 cases
Where it cites § 52.216-7
“LOGCAP III was a cost-plus-award-fee agreement that incorporated the provisions of 48 C.F.R. § 52.216-7 (2000), whereby the Army would reimburse KBR for all costs that it incurred in contract performance, including payments to subcontractors, along with a fee determined by…”
The case’s holding
A corporation is liable for civil penalties under the Anti-Kickback Act for the knowing violations of its employees acting within the scope of their employment.
Later courts cite it for
“it is entirely consistent for the statute to punish knowing violations more severely than those of which the corporation was unaware.” · 1 citing court
19
NEUTRALGen. Elec. Co. v. United States, 112 Fed. Cl. 1 (Fed. Cl. 2013).
cites § 52.216-7 6×cited by 3 cases
Where it cites § 52.216-7
“The government may recover the SCAO through the FAR, and in particular, the Allowable Cost and Payment Clause, 48 C.F.R. § 52.216-7 (h)(2), and the Credits Clause, 48 C.”
20
GREENDie Casters Int'l, Inc. v. United States, 73 Fed. Cl. 174 (Fed. Cl. 2006).
cites § 52.216-7 1×cited by 5 cases
Where it cites § 52.216-7
“(4) Any statements in specifications or other documents incorporated in this contract by reference designating performance of services or furnishing of materials at the Contractor's expense or at no cost to the Government shall be disregarded for purposes of cost-reimbursement…”

Show all 33 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
199720112025

One bar per year. Tallest: 3 cases in 2002. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Fed. Cl.21Fed. Cir.5D.D.C.310th Cir.12d Cir.1D. Colo.1C.D. Ill.1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Show all 33 citing cases (list view) →

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.