52.249-8 Default (Fixed-Price Supply and Service).

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1990–2022 27citing cases
At a glance

Courts have cited this section in 27 opinions since 1990, 1 of them in the last five years.

As prescribed in 49.504(a)(1), insert the following clause:

Default (Fixed-Price Supply and Service) (APR 1984)

(a)(1) The Government may, subject to paragraphs (c) and (d) below, by written notice of default to the Contractor, terminate this contract in whole or in part if the Contractor fails to—

(i) Deliver the supplies or to perform the services within the time specified in this contract or any extension;

(ii) Make progress, so as to endanger performance of this contract (but see subparagraph (a)(2) below); or

(iii) Perform any of the other provisions of this contract (but see subparagraph (a)(2) below).

(2) The Government's right to terminate this contract under subdivisions (1)(ii) and (1)(iii) above, may be exercised if the Contractor does not cure such failure within 10 days (or more if authorized in writing by the Contracting Officer) after receipt of the notice from the Contracting Officer specifying the failure.

(b) If the Government terminates this contract in whole or in part, it may acquire, under the terms and in the manner the Contracting Officer considers appropriate, supplies or services similar to those terminated, and the Contractor will be liable to the Government for any excess costs for those supplies or services. However, the Contractor shall continue the work not terminated.

(c) Except for defaults of subcontractors at any tier, the Contractor shall not be liable for any excess costs if the failure to perform the contract arises from causes beyond the control and without the fault or negligence of the Contractor. Examples of such causes include (1) acts of God or of the public enemy, (2) acts of the Government in either its sovereign or contractual capacity, (3) fires, (4) floods, (5) epidemics, (6) quarantine restrictions (7) strikes, (8) freight embargoes, and (9) unusually severe weather. In each instance the failure to perform must be beyond the control and without the fault or negligence of the Contractor.

(d) If the failure to perform is caused by the default of a subcontractor at any tier, and if the cause of the default is beyond the control of both the Contractor and subcontractor, and without the fault or negligence of either, the Contractor shall not be liable for any excess costs for failure to perform, unless the subcontracted supplies or services were obtainable from other sources in sufficient time for the Contractor to meet the required delivery schedule.

(e) If this contract is terminated for default, the Government may require the Contractor to transfer title and deliver to the Government, as directed by the Contracting Officer, any (1) completed supplies, and (2) partially completed supplies and materials, parts, tools, dies, jigs, fixtures, plans, drawings, information, and contract rights (collectively referred to as manufacturing materials in this clause) that the Contractor has specifically produced or acquired for the terminated portion of this contract. Upon direction of the Contracting Officer, the Contractor shall also protect and preserve property in its possession in which the Government has an interest.

(f) The Government shall pay contract price for completed supplies delivered and accepted. The Contractor and Contracting Officer shall agree on the amount of payment for manufacturing materials delivered and accepted and for the protection and preservation of the property. Failure to agree will be a dispute under the Disputes clause. The Government may withhold from these amounts any sum the Contracting Officer determines to be necessary to protect the Government against loss because of outstanding liens or claims of former lien holders.

(g) If, after termination, it is determined that the Contractor was not in default, or that the default was excusable, the rights and obligations of the parties shall be the same as if the termination had been issued for the convenience of the Government.

(h) The rights and remedies of the Government in this clause are in addition to any other rights and remedies provided by law or under this contract.

(End of clause)

Alternate I (APR 1984). If the contract is for transportation or transportation-related services, delete paragraph (f) of the basic clause, redesignate the remaining paragraphs accordingly, and substitute the following paragraphs (a) and (e) for paragraphs (a) and (e) of the basic clause:

(a)(1) The Government may, subject to paragraphs (c) and (d) below, by written notice of default to the Contractor, terminate this contract in whole or in part if the Contractor fails to—

(i) Pick up the commodities or to perform the services, including delivery services, within the time specified in this contract or any extension;

(ii) Make progress, so as to endanger performance of this contract (but see subparagraph (a)(2) below); or

(iii) Perform any of the other provisions of this contract (but see subparagraph (a)(2) below).

(2) The Government's right to terminate this contract under subdivisions (1)(ii) and (1)(iii) above, may be exercised if the Contractor does not cure such failure within 10 days (or more if authorized in writing by the Contracting Officer) after receipt of the notice from the Contracting Officer specifying the failure.

(e) If this contract is terminated while the Contractor has possession of Government goods, the Contractor shall, upon direction of the Contracting Officer, protect and preserve the goods until surrendered to the Government or its agent. The Contractor and Contracting Officer shall agree on payment for the preservation and protection of goods. Failure to agree on an amount will be a dispute under the Disputes clause.

[48 FR 42478, Sept. 19, 1983, as amended at 60 FR 34762, July 3, 1995]
The 20 cases that cite 48 C.F.R. § 52.249-8 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENEmpire Energy Mgmt. Sys., Inc. v. James G. Roche, 362 F.3d 1343 (Fed. Cir. 2004).
cites § 52.249-8 3×cited by 34 cases
Where it cites § 52.249-8
“” 48 C.F.R. § 52.249-8 (a)(2). Part I, Section H, Paragraph 21 of Mod 7 provides additional default provisions, including the following: With respect to any condition of default .”
The case’s holding
A contracting officer's decision to terminate a contract for default is reasonable when a contractor fails to make sufficient progress to complete the project within the remaining time.
Later courts cite it for
“the contracting officer's decision to terminate . . . was reasonable given the events that occurred before the termination decision was made.” · 4 citing courts
2
GREENEnron Fed. Solutions, Inc. v. United States, 80 Fed. Cl. 382 (Fed. Cl. 2008).
cites § 52.249-8 3×cited by 27 cases
Where it cites § 52.249-8
“” 48 C.F.R. § 52.249-8 (0- However, the CO maintained that FAR § 52.”
The case’s holding
Courts interpret a government contract by starting with its plain text, read as a whole in context, and a provision is not ambiguous merely because the parties disagree about it.
Later courts cite it for
“context defines a contract and the issues deriving thereof.” · 10 citing courts
3
GREENArmour of Am. v. United States, 96 Fed. Cl. 726 (Fed. Cl. 2011).
cites § 52.249-8 5×cited by 10 cases
Where it cites § 52.249-8
“]” 48 C.F.R. § 52.249-8 (a)(l)(ii), Default (Fixed-Price Supply and Service) (Apr.”
4
GREENNCLN20, Inc. v. United States, 99 Fed. Cl. 734 (Fed. Cl. 2011).
cites § 52.249-8 5×cited by 7 cases
Where it cites § 52.249-8
“See 48 C.F.R. § 52.249-8 (a)(l)(i). But, GSA could not terminate NCLN20 prior to that date, unless GSA gave NCLN20 a notice of a deficiency in performance and NCLN20 did not cure within ten days.”
Later courts cite it for
“the united states court of appeals for the federal circuit has held that a termination for convenience will be upheld unless the contractor can establish bad faith or clear abuse of discretion.” · 2 citing courts
5
GREENJohnson Mgmt. Grp. CFC, Inc. v. Mel. R. Martinez, 308 F.3d 1245 (Fed. Cir. 2002).
cites § 52.249-8 2×cited by 32 cases
Where it cites § 52.249-8
“” 48 C.F.R. § 52.249-8 (1984). That clause provides in pertinent part as follows: *1250 (a)(1) The Government may, .”
Later courts cite it for
“the government bears the burden of proof in establishing the validity of a default termination.” · 3 citing courts
6
GREENCharles W. Daff v. United States, 78 F.3d 1566 (Fed. Cir. 1996).
cites § 52.249-8 3×cited by 34 cases
Where it cites § 52.249-8
“249-8, 48 C.F.R. § 52.249-8 (1984). The TVPC contract became effective September 21, 1984.”
The case’s holding
A contracting officer's termination for default is a valid final decision under the CDA if it rests on a permissible contract ground, even though it also asserts fraud.
7
GREENUnited States v. Carolina Parachute Corp., 907 F.2d 1469 (4th Cir. 1990).
cites § 52.249-8 2×cited by 59 cases
The case’s holding
The automatic stay terminates once the requirements of bankruptcy reorganization are met and the plan is confirmed.
Later courts cite it for
“the equitable powers of section 105(a) 'are not a license for a court to disregard the clear language and meaning of the bankruptcy statutes and rules.” · 2 citing courts
8
GREENTecom, Inc. v. United States, 66 Fed. Cl. 736 (Fed. Cl. 2005).
cites § 52.249-8 1×cited by 64 cases
Where it cites § 52.249-8
“The Contracting Officer had noted that the Air Force had “three organizations who either refuse to bring in their vehicles because repair is so untimely that it is impacting their mission, or who are looking at other alternatives for vehicle support (e.”
The case’s holding
The government breaches the implied duty of cooperation when it takes unreasonable actions that interfere with a contractor's ability to perform under a contract.
Later courts cite it for
“government actions that are unreasonable under the circumstances” · 4 citing courts
9
GREENMega Constr. Co. v. United States, 29 Fed. Cl. 396 (Fed. Cl. 1993).
cites § 52.249-8 1×cited by 107 cases
Where it cites § 52.249-8
“Compare General Provision 11 with 48 CFR § 52.249-8 (1985); see also Halifax Eng’g, Inc.”
The case’s holding
A contractor is precluded from recovering damages under the implied warranty of adequate specifications if it fails to comply fully with the design specifications.
Later courts cite it for
“a strong partisan position by expert in favor of plaintiff, in conflict with one of his duties as an expert witness to objectively assist the court to understand the facts and issues” · 3 citing courts
10
GREENUnited States v. Murdock Mach. & Eng'g Co. of Utah, 81 F.3d 922 (10th Cir. 1996).
cites § 52.249-8 1×cited by 75 cases
Where it cites § 52.249-8
“See 48 C.F.R. §§ 52.249-8 , 52.249-2. The default clause provided that if the government’s default termination was proper, the government could recover from the contractor its excess costs of reprocurement, unliq- *926 uidated progress payments, and other damages.”
The case’s holding
The government retains sovereign immunity from automatic stays in bankruptcy unless Congress unequivocally expresses an intention to waive that immunity within the statutory text.
Later courts cite it for
“only when congress unequivocally expresses its intention to waive the government's sovereign immunity in the statutory text.” · 7 citing courts
11
GREENComposite Laminates, Inc. v. United States, 27 Fed. Cl. 310 (Fed. Cl. 1992).
cites § 52.249-8 3×cited by 8 cases
Where it cites § 52.249-8
“48 C.F.R. § 52.249-8 (1989). 7 All default terminations are not the same.”
Later courts cite it for
“when the government issues a cure notice, in order for a contractor to avoid default, a contractor must be able to provide adequate assurances to the government that it can complete the contract requirements on time.” · 2 citing courts
12
GREENLB&B Assocs. Inc. v. United States, 91 Fed. Cl. 142 (Fed. Cl. 2010).
cites § 52.249-8 2×cited by 7 cases
Summary
No passage or summary on file for this case yet.
13
GREENLibertatia Assocs., Inc. v. United States, 46 Fed. Cl. 702 (Fed. Cl. 2000).
cites § 52.249-8 1×cited by 34 cases
Where it cites § 52.249-8
“’s Facts at ¶31 (quoting 48 C.F.R. § 52.249-8 (Apr.1984)). The contract required TLA to submit weekly work schedules that identified when and where each requirement would be performed on each day.”
The case’s holding
A contractor may overcome the presumption of government good faith only with clear and strong evidence of specific acts of bad faith, such as an official's specific intent to injure the contractor.
Later courts cite it for
“in order to overcome this presumption, plaintiff must allege and prove, by clear and strong evidence, specific acts of bad faith on the part of the government.” · 2 citing courts
14
GREENSt. Bernard Port v. Violet Dock Port, Inc., LLC, 809 F. Supp. 2d 524 (E.D. La. 2011).
cites § 52.249-8 1×cited by 10 cases
Where it cites § 52.249-8
“2-2 at 37; 48 C.F.R. § 52.249-8 .) 10 . (R. Doc. 13-4.”
Later courts cite it for
“nor has violet submitted anything, other than its own characterization, to suggest that acquisition of the navy property was the primary motivating cause of this 70 acre expropriation.” · 1 citing court
15
GREENHanover Ins. v. Hermosa Constr. Grp., LLC, 57 F. Supp. 3d 1389 (N.D. Ga. 2014).
cites § 52.249-8 1×cited by 10 cases
Where it cites § 52.249-8
“See Federal Acquisition Regulations Systems ("FAR"), 48 C.F.R. § 52.249-8 . .Farrier disputes this date.”
16
GREENConsol. Indus., Inc. v. United States, 195 F.3d 1341 (Fed. Cir. 1999).
cites § 52.249-8 1×cited by 19 cases
Where it cites § 52.249-8
“We grant defendant’s counterclaim on the basis of that representation.”
Later courts cite it for
“contracting officer has broad discretion to determine whether to terminate a contract for default and the reviewing court will only overturn that decision if it is 'arbitrary, capricious, or constitutes an abuse of discretion.” · 3 citing courts
17
GREENDaff v. United States, 31 Fed. Cl. 682 (Fed. Cl. 1994).
cites § 52.249-8 1×cited by 17 cases
Where it cites § 52.249-8
“The answer depends on the meaning of the applicable default regulations, found at 48 C.F.R. § 52.249-8 . Subparagraph (e) provides that upon default termination, the government may require the contractor to transfer title to completed supplies and to manufacturing materials,…”
The case’s holding
Fraud in performance of a government contract, even if discovered only after termination, may sustain a default termination when it is relevant to the claims at issue.
Later courts cite it for
“although ... fraud does not have to occur in the court proceeding itself, it plainly has to be relevant to the present assertion of a claim in court, arising out of the same transaction or contract.” · 4 citing courts
18
GREENGreen Mgmt. Corp. v. United States, 42 Fed. Cl. 411 (Fed. Cl. 1998).
cites § 52.249-8 1×cited by 13 cases
Where it cites § 52.249-8
“48 C.F.R. § 52.249-8 (1987). As specified in the factual account included in this opinion, Contracting Officer John Parker issued a Notice of Termination to Green Management on May 24, 1989, by which the contract was terminated on that date.”
19
GREENUniversal Shelters of Am., Inc. v. United States, 87 Fed. Cl. 127 (Fed. Cl. 2009).
cites § 52.249-8 1×cited by 6 cases
Where it cites § 52.249-8
“See 48 C.F.R. § 52.249-8 (g). . Prior to starting Universal, Mr.”
20
GREENA/S Dampskibssetskabet Torm v. United States, 64 F. Supp. 2d 298 (S.D.N.Y. 1999).
cites § 52.249-8 2×cited by 4 cases
Where it cites § 52.249-8
“In consequence, the Court finds that the MSC was not justified in terminating the Contract on the basis of 48 C.F.R. § 52.249-8 (a)(l)(i). Since any other termination for default required defendant to provide Torm with ten days notice and opportunity to cure prior to terminating…”

Show all 27 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
199020062022

One bar per year. Tallest: 3 cases in 2011. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Fed. Cl.13Fed. Cir.6A.S.B.C.A.24th Cir.210th Cir.1N.D. Ga.1E.D. La.1S.D.N.Y.1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Show all 27 citing cases (list view) →

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.