C.F.R. homeSearch C.F.R.
C.F.R.Title 48Chapter 1—Federal Acquisition RegulationSubchapter B—Acquisition PlanningPart 9—Contractor QualificationsSubpart 9.5—Organizational and Consultant Conflicts of Interest

48 C.F.R. § 9.505-2 (2026)

9.505-2 Preparing specifications or work statements.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1985–2021 8citing cases
At a glance

Courts have cited this section in 8 opinions since 1985, 1 of them in the last five years. The most litigated part is subsection (a)(ii) (1 case).

(a)(1) If a contractor prepares and furnishes complete specifications covering nondevelopmental items, to be used in a competitive acquisition, that contractor shall not be allowed to furnish these items, either as a prime contractor or as a subcontractor, for a reasonable period of time including, at least, the duration of the initial production contract. The restriction in this paragraph (a)(1) shall not apply to—

(i) Contractors that furnish at Government request specifications or data regarding a product they provide, even though the specifications or data may have been paid for separately or in the price of the product; or

(ii) Situations in which contractors, acting as industry representatives, help Government agencies prepare, refine, or coordinate specifications, regardless of source, provided this assistance is supervised and controlled by Government representatives.

(2) If a single contractor drafts complete specifications for nondevelopmental equipment, it should be eliminated for a reasonable time from competition for production based on the specifications. This should be done in order to avoid a situation in which the contractor could draft specifications favoring its own products or capabilities. In this way the Government can be assured of getting unbiased advice as to the content of the specifications and can avoid allegations of favoritism in the award of production contracts.

(3) In development work, it is normal to select firms that have done the most advanced work in the field. These firms can be expected to design and develop around their own prior knowledge. Development contractors can frequently start production earlier and more knowledgeably than firms that did not participate in the development, and this can affect the time and quality of production, both of which are important to the Government. In many instances the Government may have financed the development. Thus, while the development contractor has a competitive advantage, it is an unavoidable one that is not considered unfair; hence no prohibition should be imposed.

(b)(1) If a contractor prepares, or assists in preparing, a work statement to be used in competitively acquiring a system or services—or provides material leading directly, predictably, and without delay to such a work statement—that contractor may not supply the system, major components of the system, or the services unless—

(i) It is the sole source;

(ii) It has participated in the development and design work; or

(iii) More than one contractor has been involved in preparing the work statement.

(2) Agencies should normally prepare their own work statements. When contractor assistance is necessary, the contractor might often be in a position to favor its own products or capabilities. To overcome the possibility of bias, contractors are prohibited from supplying a system or services acquired on the basis of work statements growing out of their services, unless excepted in paragraph (b)(1) of this section.

(3) For the reasons given in paragraph (a)(3) of this section, no prohibitions are imposed on development and design contractors.

[48 FR 42142, Sept. 19, 1983, as amended at 84 FR 19846, May 6, 2019]
The 8 cases that cite 48 C.F.R. § 9.505-2 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENVantage Assocs., Inc. v. United States, 59 Fed. Cl. 1 (Fed. Cl. 2003).
cites § 9.505-2 5×subsections: (a)(ii)cited by 22 cases
Where it cites § 9.505-2
“505 — 1(a); see also 48 C.F.R. §§ 9.505-2 (a)(3), 9.505-2(b)(l)(ii), 9.”
Later courts cite it for
“the wide discretion afforded contracting officers extends to a broad range of procurement functions, including the determination of what constitutes an advantage over those proposals.” · 4 citing courts
2
GREENUS ex rel. Ervin & Assoc. v. Hamilton SEC., 370 F. Supp. 2d 18 (D.D.C. 2005).
cites § 9.505-2 2×cited by 28 cases
Where it cites § 9.505-2
“48 C.F.R. § 9.505-2 (b)(1). Sections 9.505-2(b)(1)(ii) and (b)(3), however, specifically excepts certain government contractors from the prohibitions of Section 9.”
The case’s holding
Liability under the False Claims Act requires evidence that a defendant submitted false records or statements and that the materiality of such statements is an essential element of liability.
Later courts cite it for
“a relator must produce evidence that the defendant actually submitted false demands for payment or submitted false records or statements in order to get a false claim paid.” · 3 citing courts
3
GREENW.G. Yates & Sons Constr. Co. v. Louis Caldera, 192 F.3d 987 (Fed. Cir. 1999).
cites § 9.505-2 1×cited by 14 cases
Where it cites § 9.505-2
“§ 2319 , and the conflict of interest regulations at 48 C.F.R. § 9.505-2 (b) are questions of law and, therefore, are subject to de novo review.”
Later courts cite it for
“government has not consented to be sued by those with whom it is not in privity.” · 2 citing courts
4
GREENDSD Labs., Inc. v. United States, 46 Fed. Cl. 467 (Fed. Cl. 2000).
cites § 9.505-2 1×cited by 11 cases
Where it cites § 9.505-2
“” 48 C.F.R. § 9.505-2 (b)(2). A contractor determining specifications and work statements “should not be in a position to make decisions favoring its own products or capabilities.”
cites § 9.505-2 1×cited by 16 cases
Where it cites § 9.505-2
“48 C.F.R. § 9.505-2 (a)(3). Thus, the competitive advantages afforded the contractor in such situations are not prohibited as unfair because they are both unavoidable and advantageous to the government.”
6
GREENInformatics Gen. Corp. v. Weinberger, 617 F. Supp. 331 (D.D.C. 1985).
cites § 9.505-2 1×cited by 3 cases
Where it cites § 9.505-2
“See 48 C.F.R. § 9.505-2 (a)(3), (b). 13 . See Delta Data Systems, supra, note 6.”
7
NO FLAGErnst & Young, LLP v. United States, No. 17-1329 (Fed. Cl. Mar. 5, 2018).
cites § 9.505-2 5×cited by 0 cases
Summary
No passage or summary on file for this case yet.
8
NO FLAGAm. K-9 Detection Servs., LLC v. United States, No. 20-1614 (Fed. Cl. Aug. 16, 2021).
cites § 9.505-2 1×cited by 0 cases
Where it cites § 9.505-2
“” GK9 MJAR at 14 (quoting 48 C.F.R. § 9.505-2 (b)(1)). The CO conducted an extensive investigation into the results of MSA’s participation in the pilot program.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
198520032021

One bar per year. Tallest: 2 cases in 2005. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Fed. Cl.4D.D.C.2D.C. Cir.1Fed. Cir.1
By subsection
(a)(ii)1 case
Vantage Assocs., Inc. v. United States, 59 Fed. Cl. 1 (Fed. Cl. 2003).“505 — 1(a); see also 48 C.F.R. §§ 9.505-2 (a)(3), 9.505-2(b)(l)(ii), 9.”
Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com