9903.306 Interpretations.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 2006–2016 6citing cases
At a glance

Courts have cited this section in 6 opinions since 2006. The most litigated part is subsection (f) (1 case).

In determining amounts of increased costs in the clauses at 9903.201-4(a), Cost Accounting Standards, 9903.201-4(c), Disclosure and Consistency of Cost Accounting Practices, and 9903.201-4(d), Consistency in Cost Accounting, the following considerations apply:

(a) Increased costs shall be deemed to have resulted whenever the cost paid by the Government results from a change in a contractor's cost accounting practices or from failure to comply with applicable Cost Accounting Standards, and such cost is higher than it would have been had the practices not been changed or applicable Cost Accounting Standards complied with.

(b) If the contractor under any fixed-price contract, including a firm fixed-price contract, fails during contract performance to follow its cost accounting practices or to comply with applicable Cost Accounting Standards, increased costs are measured by the difference between the contract price agreed to and the contract price that would have been agreed to had the contractor proposed in accordance with the cost accounting practices used during contract performance. The determination of the contract price that would have been agreed to will be left to the contracting parties and will depend on the circumstances of each case.

(c) The statutory requirement underlying this interpretation is that the United States not pay increased costs, including a profit enlarged beyond that in the contemplation of the parties to the contract when the contract costs, price, or profit is negotiated, by reason of a contractor's failure to use applicable Cost Accounting Standards, or to follow consistently its cost accounting practices. In making price adjustments under the Cost Accounting Standards clause at 9903.201-4(a) in fixed price or cost reimbursement incentive contracts, or contracts providing for prospective or retroactive price redetermination, the Federal agency shall apply this requirement appropriately in the circumstances.

(d) The contractor and the contracting officer may enter into an agreement as contemplated by subdivision (a)(4)(ii) of the Cost Accounting Standards clause at 9903.201-4(a), covering a change in practice proposed by the Government or the contractor for all of the contractor's contracts for which the contracting officer is responsible, provided that the agreement does not permit any increase in the cost paid by the Government. Such agreement may be made final and binding, notwithstanding the fact that experience may subsequently establish that the actual impact of the change differed from that agreed to.

(e) An adjustment to the contract price or of cost allowances pursuant to the Cost Accounting Standards clause at 9903.201-4(a) may not be required when a change in cost accounting practices or a failure to follow Standards or cost accounting practices is estimated to result in increased costs being paid under a particular contract by the United States. This circumstance may arise when a contractor is performing two or more covered contracts, and the change or failure affects all such contracts. The change or failure may increase the cost paid under one or more of the contracts, while decreasing the cost paid under one or more of the contracts. In such case, the Government will not require price adjustment for any increased costs paid by the United States, so long as the cost decreases under one or more contracts are at least equal to the increased cost under the other affected contracts, provided that the contractor and the affected contracting officers agree on the method by which the price adjustments are to be made for all affected contracts. In this situation, the contracting agencies would, of course, require an adjustment of the contract price or cost allowances, as appropriate, to the extent that the increases under certain contracts were not offset by the decreases under the remaining contracts.

(f) Whether cost impact is recognized by modifying a single contract, several but not all contracts, or all contracts, or any other suitable technique, is a contract administration matter. The Cost Accounting Standards rules do not in any way restrict the capacity of the parties to select the method by which the cost impact attributable to a change in cost accounting practice is recognized.

The 6 cases that cite 48 C.F.R. § 9903.306 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENLockheed Martin Corp. v. United States, 70 Fed. Cl. 745 (Fed. Cl. 2006).
cites § 9903.306 9×cited by 12 cases
Where it cites § 9903.306
“Explaining this provision, 48 C.F.R. § 9903.306 (e) states that “when a contractor is performing two or more covered contracts, and the change or failure affects all such contracts,” the change in cost accounting practice “may increase the cost paid under one or more of the…”
2
GREENDirectv Grp., Inc. v. United States, 670 F.3d 1370 (Fed. Cir. 2012).
cites § 9903.306 12×subsections: (f)cited by 19 cases
Where it cites § 9903.306
“205-6(j)(4) for rules related to refund or credit to the Government upon termination of an overfunded defined-benefit pension plan.”
Later courts cite it for
“as a matter of elementary grammar, the statute's 27 use of 'such' is a demonstrative adjective, and it must refer to a clear antecedent.” · 2 citing courts
3
GREENGates v. Raytheon Co., 584 F.3d 1062 (Fed. Cir. 2009).
cites § 9903.306 1×cited by 24 cases
Where it cites § 9903.306
“” 48 C.F.R. § 9903.306 (a). 8 . Raytheon argues that because the Government requested a check to cover Raytheon’s segment-closing adjustment obligation rather than requesting a direct adjustment of contract prices, no contract prices would have been adjusted regardless of the…”
The case’s holding
CAS 413 requires a segment-closing pension adjustment to be paid in the current period of segment closing, not merely dictating accounting treatment, so a late payment causes increased costs.
Later courts cite it for
“pro- vides uniformity in how contractors measure, assign, and allocate costs to government contracts.” · 1 citing court
4
GREENGen. Elec. Co. v. United States, 84 Fed. Cl. 129 (Fed. Cl. 2008).
cites § 9903.306 1×cited by 10 cases
Where it cites § 9903.306
“” 48 C.F.R. § 9903.306 (e) provides that, even if the failure of a contractor to follow the CAS is estimated to result in increased costs to the government under a particular contract, "the Government will not require price adjustment for any increased costs paid by the United…”
The case’s holding
Under the original Cost Accounting Standard 413, a segment closing adjustment covers the entire closed segment, and the government must credit any cost benefit it derived from transferred pension surplus.
Later courts cite it for
“in no case shall the government recover costs greater than the increased cost ... to the government, in the aggregate, on the relevant contracts subject to the price adjustment, unless the contractor made a change in its cost accounting practices of which it was aware or should have been aware at the time of the price negotiation and which it failed to disclose to the government.” · 1 citing court
5
GREENDonley v. Lockheed Martin Corp., 608 F.3d 1348 (Fed. Cir. 2010).
cites § 9903.306 1×cited by 3 cases
Where it cites § 9903.306
“See 48 C.F.R. § 9903.306 (a) (1993) (“In creased costs shall be deemed to have resulted whenever the cost paid by the Government results from a change in a contractor’s cost accounting practices .”
6
NO FLAGExelis, Inc., ASBCA No. 60131 (A.S.B.C.A. Aug. 29, 2016).
cites § 9903.306 1×cited by 0 cases
Where it cites § 9903.306
“Compare 48 C.F.R. § 9903.306 (b) (providing for the calculation of increased costs on fixed-price contracts for CAS violations) with FAR 16.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
200620112016

One bar per year. Tallest: 1 case in 2006. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Fed. Cir.3Fed. Cl.2A.S.B.C.A.1
By subsection
(f)1 case
Directv Grp., Inc. v. United States, 670 F.3d 1370 (Fed. Cir. 2012).“205-6(j)(4) for rules related to refund or credit to the Government upon termination of an overfunded defined-benefit pension plan.”
Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com