Connecticut General Statutes homeSearch Connecticut
Conn. Gen. Stat.Title 49 — Mortgages and LiensChapter 847 — Liens

Conn. Gen. Stat. § 49-42 (2025)

Enforcement of right to payment on bond. Suit on bond, procedure and judgment

Edition and currency
laws through the 2024 session: the source has not yet published 2025 Public Acts (checked Sept. 2026). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTlaws through the 2024 session: the source has not yet published 2025 Public Acts (checked Sept. 2026) cited 1970–2026 39citing cases
At a glance

Courts have cited this section in 39 opinions since 1970, 3 of them in the last five years. The most litigated part is subsection (a) (5 cases).

(a)(1) Any person who performed work or supplied materials for which a requisition was submitted to, or for which an estimate was prepared by, the awarding authority and who does not receive full payment for such work or materials within sixty days of the applicable payment date provided for in subsection (a) of section 49-41a, or any person who supplied materials or performed subcontracting work not included on a requisition or estimate who has not received full payment for such materials or work within sixty days after the date such materials were supplied or such work was performed, may enforce such person's right to payment under the bond by serving a notice of claim on the surety that issued the bond and a copy of such notice to the contractor named as principal in the bond not later than one hundred eighty days after the last date any such materials were supplied or any such work was performed by the claimant. For the payment of retainage, as defined in section 42-158i, such notice shall be served not later than one hundred eighty days after the applicable payment date provided for in subsection (a) of section 49-41a. The notice of claim shall state with substantial accuracy the amount claimed and the name of the party for whom the work was performed or to whom the materials were supplied, and shall provide a detailed description of the bonded project for which the work or materials were provided. If the content of a notice prepared in accordance with subsection (c) of section 49-41a complies with the requirements of this section, a copy of such notice, served not later than one hundred eighty days after the date provided for in this section upon the surety that issued the bond and upon the contractor named as principal in the bond, shall satisfy the notice requirements of this section. Not later than ninety days after service of the notice of claim, the surety shall make payment under the bond and satisfy the claim, or any portion of the claim which is not subject to a good faith dispute, and shall serve a notice on the claimant denying liability for any unpaid portion of the claim. The surety's failure to discharge its obligations under this section shall not be deemed to constitute a waiver of defenses the surety or its principal on the bond may have or acquire as to the claim, except as to undisputed amounts for which the surety and claimant have reached agreement. If, however, the surety fails to discharge its obligations under this section, then the surety shall indemnify the claimant for the reasonable attorneys' fees and costs the claimant incurs thereafter to recover any sums found due and owing to the claimant. The notices required under this section shall be served by registered or certified mail, postage prepaid in envelopes addressed to any office at which the surety, principal or claimant conducts business, or in any manner in which civil process may be served.

(2) If the surety denies liability on the claim, or any portion thereof, the claimant may bring an action upon the payment bond in the Superior Court for such sums and prosecute the action to final execution and judgment. An action to recover on a payment bond under this section shall be privileged with respect to assignment for trial. The court shall not consolidate for trial any action brought under this section with any other action brought on the same bond unless the court finds that a substantial portion of the evidence to be adduced, other than the fact that the claims sought to be consolidated arise under the same general contract, is common to such actions and that consolidation will not result in excessive delays to any claimant whose action was instituted at a time significantly prior to the filing of the motion to consolidate. In any such proceeding, the court judgment shall award the prevailing party the costs for bringing such proceeding and allow interest at the rate of interest specified in the labor or materials contract under which the claim arises or, if no such interest rate is specified, at the rate of interest as provided in section 37-3a upon the amount recovered, computed from the date of service of the notice of claim, provided, for any portion of the claim which the court finds was due and payable after the date of service of the notice of claim, such interest shall be computed from the date such portion became due and payable. The court judgment may award reasonable attorneys' fees to either party if upon reviewing the entire record, it appears that either the original claim, the surety's denial of liability, or the defense interposed to the claim is without substantial basis in fact or law. Any person having direct contractual relationship with a subcontractor but no contractual relationship express or implied with the contractor furnishing the payment bond shall have a right of action upon the payment bond upon giving written notice of claim as provided in this section.

(b) Every suit instituted under this section shall be brought in the name of the person suing, in the superior court for the judicial district where the contract was to be performed, irrespective of the amount in controversy in the suit, but no such suit may be commenced after the expiration of one year after the last date that materials were supplied or any work was performed by the claimant, except that any such suit solely seeking payment for retainage, as defined in section 42-158i, shall be commenced not later than one year after the date payment of such retainage was due, pursuant to the provisions of subsection (a) of section 49-41a.

(c) The word “material” as used in sections 49-33 to 49-43, inclusive, shall include construction equipment and machinery that is rented or leased for use (1) in the prosecution of work provided for in the contract within the meaning of sections 49-33 to 49-43, inclusive, or (2) in the construction, raising or removal of any building or improvement of any lot or in the site development or subdivision of any plot of land within the meaning of sections 49-33 to 49-39, inclusive.

(1949 Rev., S. 7215; 1961, P.A. 228; 1969, P.A. 192, S. 1; P.A. 78-280, S. 2, 127; P.A. 79-602, S. 100; P.A. 87-345, S. 2; P.A. 94-188, S. 16; P.A. 00-36; P.A. 01-195, S. 48, 181; P.A. 06-78, S. 1; P.A. 09-146, S. 3; P.A. 16-104, S. 2.)

History: 1961 act required that payment be made within 90 days rather than 60 days in Subsec. (a); 1969 act required that suit commence within one year after date on which last of the labor was performed or material was supplied rather than within one year “after the date of final settlement of such contract” in Subsec. (b); P.A. 78-280 substituted “judicial district” for “county” in Subsec. (b); P.A. 79-602 made minor changes in wording but made no substantive changes; P.A. 87-345 substantially amended procedure set forth in Subsec. (a) for enforcement of right to payment under bond; P.A. 94-188 amended procedure set forth in Subsec. (a) for enforcement of right to payment under bond and amended Subsec. (b) by adding language concerning the applicable payment date provided for in Sec. 49-41a and the time within which to commence suit for materials or work not included on a requisition or estimate; P.A. 00-36 redefined “material” in Subsec. (c) to include construction equipment that is rented or leased for use in prosecution of work or in construction, raising, removal of any building or improvement of lot or in site development or subdivision and to apply term to Secs. 49-33 to 49-43, inclusive; P.A. 01-195 made technical changes in Subsecs. (a) and (c), effective July 11, 2001; P.A. 06-78 added provision in Subsec. (a) re notice for payment of retainage, added provisions in Subsec. (b) re commencement of suit within one year of last date materials were supplied or work was performed by claimant and requiring suit seeking payment solely for retainage to be commenced within one year after retainage payment was due, pursuant to Sec. 49-41a(a) and made conforming and technical changes in Subsecs. (a) and (b), effective May 30, 2006; P.A. 09-146 replaced reference to Sec. 49-41a(b) with reference to Sec. 49-41a(c) in Subsec. (a), effective July 1, 2009; P.A. 16-104 amended Subsec. (a) to designate existing provisions re enforcement of person's right to payment under bond by serving notice of claim on surety as Subdiv. (1) and amend same by adding provisions re surety's failure to discharge obligations not deemed to constitute waiver of defenses, and to designate existing provisions re surety that denies liability on claim may bring action in Superior Court as Subdiv. (2) and amend same by making technical changes, effective July 1, 2016.

Cited. 143 C. 85. History discussed. 151 C. 332. Material actually forming part of work provided for in public works contract, as well as labor performed at the site, is clearly within contemplated coverage of payment bond required for protection of persons who have furnished “labor or material in the prosecution of the work”. Id., 334. Test as to whether labor and materials used in making repairs which are major items are covered by payment bond is whether item was necessitated by rigors of job rather than prior condition of equipment and whether supplier and purchasing contractor reasonably expected that item would be substantially consumed on the job. Id., 335. Having found that no administrative determination by public works commissioner of final settlement date had been made under Sec. 49-43, court was justified in concluding that no final settlement within meaning of this section could be said to have preceded actual payment and exchange of releases, and that subject action commenced within 3 months of that date had been timely brought. 159 C. 563. Cited. 174 C. 219. Remedies afforded by this section and Sec. 49-41a(b) are independent and notice requirements of later are not prerequisite to suit initiated under this section. 207 C. 468. Cited. 229 C. 303; 236 C. 750; 238 C. 293; 239 C. 708; 240 C. 10. Under 1995 revision, action on bond executed by surety pursuant to Sec. 49-41 is governed by this section, and plaintiff cannot bring a common-law action on bond. 293 C. 569.

Cited. 25 CA 751; 29 CA 783; 32 CA 118; Id., 133. Claims under section are not preempted by ERISA. 40 CA 777. Neither Sec. 49-41a(c) nor this section contain any language to suggest that the substantial performance language of Sec. 49-41a(c) applies to a subcontractor's claim under this section against a surety. 207 CA 551.

Cited. 17 CS 297. Fact that written notice was given to the contractor in an action on bond must be recited in the complaint or a copy annexed thereto; failure to comply with this rule left the complaint deficient. 18 CS 43. Until the subcontractor exercises his right of action granted by section, there is no debt due from the contractor to the subcontractor which can be garnished. 21 CS 16. Cited. 32 CS 168.

Subsec. (a):

Decision permits subcontractor to sue on surety bond despite failure to comply precisely with notice requirements of section. 225 C. 367. 90-day response requirement is directory, not mandatory, and legislature did not intend that a surety that fails to pay or to deny a claim by the statutory deadline thereby waives any substantive defenses and forfeits its right to contest the merits of the claim. 314 C. 749.

Because section requires only “substantial accuracy” re complaint, plaintiff was not obligated to prove that company X was now known as company Y; trial court erred in refusing to admit evidence of notice of claim on the surety. 49 CA 522.

The 20 cases that cite Conn. Gen. Stat. § 49-42 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENNor'easter Grp., Inc. v. Colossale Concrete, Inc., 542 A.2d 692 (Conn. 1988).
cites § 49-42 32×cited by 134 cases
Where it cites § 49-42
“This is a contract action brought pursuant to General Statutes § 49-42 1 by the plaintiff, The *470 Nor’easter Group, Inc.”
Holding on this section
The notice requirement in General Statutes section 49-41a (b) is not a jurisdictional prerequisite to a suit brought under General Statutes section 49-42.
Later courts cite it for
“whether a building contract has been substantially performed is ordinarily a question of fact for the trier to determine.” · 4 citing courts
cites § 49-42 18×cited by 126 cases
Where it cites § 49-42
“The trial court allowed recovery of the earned profits of $17,654 under the provisions of § 49-42. We agree that the plaintiff is entitled to recover lost profits for work actually performed.”
The case’s holding
The Miller Act precludes recovery of unearned profits because its language and purpose require payment only for work performed or materials supplied.
Later courts cite it for
“in the interpretation of statutory provisions, the application of common sense to the language is not to be excluded.” · 4 citing courts
3
GREENOkee Indus., Inc. v. Nat'l Grange Mut. Ins., 623 A.2d 483 (Conn. 1993).
cites § 49-42 18×cited by 43 cases
Where it cites § 49-42
“The issue in this appeal is whether an unpaid subcontractor seeking to recover on a payment bond furnished for a public construction contract has adequately complied with the notice requirements contained in General Statutes § 49-42 (a). 1 Alleging nonpayment for materials…”
The case’s holding
Substantial compliance with statutory notice requirements for payment bonds is sufficient if the contractor receives actual notice of the claim.
Later courts cite it for
“is a remedial statute enacted to provide security for workers and materials suppliers unable to avail themselves of the protection of a mechanic's lien. . . . because the statutory requirement of a bond is designed to protect and benefit those who furnish materials and labor to the contractor on public work, in that they may be sure of payment of their just claims, without defeat or undue delay . . . such statutory provisions are to be liberally construed.” · 4 citing courts
4
GREENAm. Masons' Supply Co. v. F. W. Brown Co., 384 A.2d 378 (Conn. 1978).
cites § 49-42 12×cited by 75 cases
Where it cites § 49-42
“The plaintiff, a building materials supplier, brought this action under § 49-42 of the General Statutes, seeking reimbursement for materials alleged to have been furnished B & G Construction, Inc.”
The case’s holding
Statutory payment bond provisions are liberally construed to protect and benefit those furnishing materials and labor for public works.
Later courts cite it for
“the statutory requirement of a bond is designed to protect and benefit those who furnish materials and labor to the contractor on public work, in that they may be sure of payment of their just claims, without defeat or undue delay . . . and such statutory provisions are to be liberally construed.” · 5 citing courts
5
GREENMillgard Corp. v. White Oak Corp., 224 F. Supp. 2d 425 (D. Conn. 2002).
cites § 49-42 21×subsections: (a) 5× (b) 2×cited by 10 cases
Where it cites § 49-42
“Millgard alleges breach of contract and unjust enrichment against defendant White Oak Corporation (“White Oak”), and seeks to collect payment on a bond against defendant National Union Insurance Company of Pittsburgh, PA (“National Union”) pursuant to Conn.Gen.Stat. § 49-42,…”
6
GREENUnited Concrete Prods., Inc. v. NJR Constr., LLC, 263 A.3d 823 (Conn. App. Ct. 2021).
cites § 49-42 29×cited by 3 cases
Where it cites § 49-42
“On appeal, the plaintiff claims that the trial court improperly: (1) calculated its award of damages to NJR on the breach of contract count of NJR’s counterclaim; (2) concluded that NJR did not fail to mitigate its damages; (3) failed to render judgment against Aegis on the…”
7
GREENBlakeslee Arpaia Chapman, Inc. v. El Constructors, Inc., 628 A.2d 601 (Conn. App. Ct. 1993).
cites § 49-42 19×cited by 17 cases
Where it cites § 49-42
“The primary issue presented by this appeal is whether a prejudgment attachment may be obtained by a subcontractor against property owned by the issuer of a construction performance bond pursuant to General Statutes § 49-42 (a). 1 The trial court denied the plaintiff…”
Later courts cite it for
“thus, a plaintiff may be entitled to a prejudgment remedy because it has demonstrated the requisite probable cause, but it may still be denied the remedy if its interest is already adequately secured.” · 2 citing courts
8
GREENWickes Mfg. Co. v. Currier Elec. Co., 596 A.2d 1331 (Conn. App. Ct. 1991).
cites § 49-42 17×cited by 19 cases
Where it cites § 49-42
“The plaintiffs predecessor, Eagle Signal Corporation (Eagle), instituted this action under General Statutes § 49-42 1 seeking reimbursement for equipment furnished to the named defendant, a general contractor (contractor) that had contracted with the state to install traffic…”
9
GREENDysart Corp. v. Seaboard Sur. Co., 688 A.2d 306 (Conn. 1997).
cites § 49-42 13×cited by 28 cases
Where it cites § 49-42
“to 1991) § 49-42, as an assignee of the rights of the Diamond employees in their paychecks.”
The case’s holding
The endorsement of a check does not constitute a legal or equitable assignment of underlying payment bond rights.
Later courts cite it for
“remedial statutes should be construed liberally in favor of those whom the law is intended to protect” · 5 citing courts
10
GREENSaturn Constr. Co. v. Premier Roofing Co., 680 A.2d 1274 (Conn. 1996).
cites § 49-42 6×cited by 87 cases
Where it cites § 49-42
“10 In that connection, the plaintiff argues that the defendant did not provide adequate notice of its claim, as required by § 49-41a, because the January 21,1992 letter did not specifically invoke § 49-41a and was only intended to serve as notice under General Statutes § 49-42…”
The case’s holding
An arbitration award is not vacated for manifest disregard if the panel's statutory interpretation is reasonable or supported by an alternative legal theory.
Later courts cite it for
“the test consists of the following three elements, all of which must be satisfied in order for a court to vacate an arbitration award on the ground that the arbitration panel manifestly disregarded the law: (1) the error was obvious and capable of being readily and instantly perceived by the average person qualified to serve as an arbitrator; (2) the arbitration panel appreciated the existence of a clearly governing legal principle but decided to ignore it; and (3) the governing law alleged to have been ignored by the arbitration panel is well defined, explicit, and clearly applicable.” · 2 citing courts
cites § 49-42 5×cited by 96 cases
Where it cites § 49-42
“C The defendants further claim that, even if the services rendered by the plaintiff fall within the scope of the payment bond, the trial court improperly found that the plaintiff had commenced its action on the bond within the one year time limitation prescribed by General…”
The case’s holding
A contract modification may be inferred from the attendant circumstances and conduct of the parties.
Later courts cite it for
“as with any issue of statutory interpretation, our initial guide is the language of the statute itself.” · 5 citing courts
12
GREENSuntech of Conn., Inc. v. Lawrence Brunoli, Inc., 164 A.3d 36 (Conn. App. Ct. 2017).
cites § 49-42 5×cited by 8 cases
Where it cites § 49-42
“The plaintiff alleged four counts against the contractor for breach of contract, unjust enrichment, delay, and violation of General Statutes § 49-41a ; 5 and one count against the insurer pursuant to General Statutes § 49-42. 6 The contractor denied the substantive allegations…”
13
GREENKMK Insulation, Inc. v. A. Prete & Son Constr. Co., 715 A.2d 799 (Conn. App. Ct. 1998).
cites § 49-42 13×cited by 7 cases
Where it cites § 49-42
“to 1993) § 49-42 (a). 1 We agree and reverse the judgment of the trial court.”
14
GREENSuntech of Connecticut, Inc. v. Lawrence Brunoli, Inc., 72 A.3d 1113 (Conn. App. Ct. 2013).
cites § 49-42 9×cited by 5 cases
Where it cites § 49-42
“Suntech claims the court erred in concluding that Suntech had not proven that (1) Brunoli breached its subcontract with Suntech and (2) Safeco violated General Statutes § 49-42. We affirm the judgment of the trial court.”
15
GREENElgard Corp. v. Brennan Constr. Co., 157 F.R.D. 1 (D. Conn. 1994).
cites § 49-42 8×subsections: (b) 5×cited by 9 cases
Where it cites § 49-42
“Elgard asserts that it supplied Adco with the materials, that the State paid Brennan $107,445 for the materials, Brennan paid Adco, but Adco did not pay Elgard.”
Later courts cite it for
“the state cannot preclude a district court from exercising the judicial power conferred upon the united states in the constitution and in turn properly delegated to the district court.” · 2 citing courts
16
GREENEacott v. Ins. Co. of North Am., 673 A.2d 587 (Conn. App. Ct. 1996).
cites § 49-42 12×cited by 4 cases
Where it cites § 49-42
“The plaintiffs, pursuant to General Statutes § 49-42, 4 served written notice on the surety and the general contractor, as principal on the bond, seeking payment for the contributions owed to the fund by the subcontractor.”
17
GREENBarreira Landscaping & Masonry v. Frontier Ins., 779 A.2d 244 (Conn. Super. Ct. 2000).
cites § 49-42 14×cited by 3 cases
Where it cites § 49-42
“2 General Statutes § 49-42 was patterned after federal legislation popularly known as the Miller Act.”
18
GREENErnst Steel Corp. v. Reliance Ins., 536 A.2d 969 (Conn. App. Ct. 1988).
cites § 49-42 4×cited by 19 cases
Where it cites § 49-42
“The plaintiff has established its entitlement to additional attorney’s fees incurred in its defense of Yonkers’ countersuit for an alleged breach of the subcontract upon which the plaintiff had initially brought suit under General Statutes § 49-42 against the two sureties on the…”
Later courts cite it for
“although designated a third party cross-complaint,' under our practice such a pleading by a defendant against the plaintiff is called a counter-claim and the trial court properly referred to it as such.” · 1 citing court
19
NEUTRALComm'r of Labor v. C.J.M. Servs., Inc., 806 A.2d 1105 (Conn. App. Ct. 2002).
cites § 49-42 8×cited by 3 cases
Where it cites § 49-42
“First, the public works statute requires that all such projects be bonded in the amount of the contract and that the surety or sureties on the bond must be approved by the officer awarding the contract. Second, the bond enforcement statute sets out a procedure that requires a…”
20
GREENCampbell v. Town of Plymouth, 811 A.2d 243 (Conn. App. Ct. 2002).
cites § 49-42 2×cited by 23 cases
Where it cites § 49-42
“Hale, judge trial referee, held that General Statutes § 49-42 6 was not an exclusive remedy.”
Later courts cite it for
“a mere assertion of fact in the affidavit of the party opposing summary judgment is not enough to establish the existence of a material fact that, by itself, defeats a claim for summary judgment.” · 2 citing courts

Show all 39 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
197019982026

One bar per year. Tallest: 4 cases in 1996. 2026 is a partial year. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Conn. App. Ct.14Conn.12D. Conn.7Conn. Super. Ct.52d Cir.1
By subsection
(a)5 cases
Millgard Corp. v. White Oak Corp., 224 F. Supp. 2d 425 (D. Conn. 2002).“Millgard alleges breach of contract and unjust enrichment against defendant White Oak Corporation (“White Oak”), and seeks to collect payment on a bond against defendant National Union Insurance Company of Pittsburgh, PA (“National Union”) pursuant to Conn.Gen.Stat. § 49-42,…”
Bleiler v. Cristwood Contracting Co., 868 F. Supp. 461 (D. Conn. 1994).
Elgard Corp. v. Brennan Constr. Co., 388 F.3d 30 (2d Cir. 2004).
Steward Mach. Co. v. White Oak Corp., 462 F. Supp. 2d 251 (D. Conn. 2006).
Fisher Skylights, Inc. v. CFC Constr. Ltd. P'ship, 921 F. Supp. 65 (D. Conn. 1995).
(b)4 cases
Elgard Corp. v. Brennan Constr. Co., 157 F.R.D. 1 (D. Conn. 1994).“Elgard asserts that it supplied Adco with the materials, that the State paid Brennan $107,445 for the materials, Brennan paid Adco, but Adco did not pay Elgard.”
Millgard Corp. v. White Oak Corp., 224 F. Supp. 2d 425 (D. Conn. 2002).
Fisher Skylights, Inc. v. CFC Constr. Ltd. P'ship, 921 F. Supp. 65 (D. Conn. 1995).
Steward Mach. Co. v. White Oak Corp., 462 F. Supp. 2d 251 (D. Conn. 2006).

Show all 39 citing cases (list view) →

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: laws through the 2024 session: the source has not yet published 2025 Public Acts (checked Sept. 2026). Syfert holds no earlier or later version of this section.

Connecticut General Statutes Home  |  Search Connecticut  |  Search cases for this section  |  syfert.com