429.060. Lien shall have precedence over subsequent encumbrances. — The lien for work and materials as aforesaid shall be preferred to all other encumbrances which may be attached to or upon such buildings, bridges or other improvements, or the ground, or either of them, subsequent to the commencement of such buildings or improvements.
--------
(RSMo 1939 § 3553)
Prior revisions: 1929 § 3163; 1919 § 7223; 1909 § 8219
(1967) A properly filed mechanic's lien dates from the visible commencement of actual operations on the ground for the erection of the building or the making of the improvement which makes it apparent that a building has been commenced or that an improvement is to be made, done with the intention and formed purpose to continue the work until completed. H. B. Deal Construction Co. v. Labor Discount Center, Inc. (Mo.), 418 S.W.2d 940.
(1978) Statutes providing for priority of mechanic's lien over deed of trust did not violate due process rights of lender under the deed of trust. Westinghouse Electric Company v. Vann Realty Company (Mo.), 568 S.W.2d 777.
- Where it cites § 429.060
- “For encumbrances on the land, the “first spade rule” under section 429.060 gives the mechanic’s lien relation-back priority to the date when work commenced: The lien for work and materials as aforesaid shall be preferred to all other encumbrances which may be attached to or upon…”
- The case’s holding
- A properly filed mechanic's lien has priority over any third-party encumbrance attaching after the date work began.
- Later courts cite it for
- “in rare circumstances, however, the overruling of a party's motion for summary judgment can be reviewed when its merits are intertwined completely with a grant of summary judgment in favor of an opposing party.” · 7 citing courts
- Where it cites § 429.060
- “Section 429.060, RSMo (1986) provides that mechanics’ liens shall be preferred to all other encumbrances on the improvements or the ground subsequent to the commencement of the improvements.”
- The case’s holding
- A lender waives priority over mechanics' liens when it funds construction with knowledge of the project and the potential for liens.
- Later courts cite it for
- “breach of the fiduciary duty constitutes a tort.” · 3 citing courts
- Where it cites § 429.060
- “In its Motion For Summary Judgment Paric claims priority as a mechanic lien claimant by virtue of Section 429.060 of the Revised Missouri Statute, commonly referred to as the First Spade Rule.”
- Where it cites § 429.060
- “Section 429.060 states that "[t]he lien for work and materials as aforesaid shall be preferred to all other encumbrances which may be attached to or upon such buildings, bridges or other improvements, or the ground, or either of them, subsequent to the commencement of such…”
- Where it cites § 429.060
- “Lien claimants contend that under § 429.060, V.A.M.S.1969, their liens for work and materials are superior to the four deeds of trust.”
- Later courts cite it for
- “after substantial work was begun and at a time when the lender was aware of the total project being built.” · 2 citing courts
- Where it cites § 429.060
- “050, § 429.060 and § 429.260. “Under section 429.060 and the first spade rule, mechanic’s liens attach with the first delivery of material or commencement of work.””
- Later courts cite it for
- “is silent on this issue and on its face gives no hint that it was a construction loan as opposed to a purchase money deed of trust or other similar instrument.” · 1 citing court
- Where it cites § 429.060
- “On the other hand, the DMI lien under its deed of trust, having been perfected prior to the commencement of any construction work, has priority under Section 429.060 with respect to the ground itself.”
- Where it cites § 429.060
- “shall be preferred to all other encumbrances which may be attached to or upon such buildings, bridges or other improvements, or the ground, or either of them, subsequent to the commencement of such buildings or improvements.”
- Where it cites § 429.060
- “Under section 429.060, a mechanic's lien for materials furnished shall be preferred to all other encumbrances which may be attached to or upon the building or improvement or the land upon which the building or improvement are situated, or either of them, subsequent to the…”
- Where it cites § 429.060
- “Section 429.060 provides that the mechanic’s lien shall be preferred to all other encumbrances on the improvements or on the ground but only if subsequent to the commencement of the improvements.”
- Where it cites § 429.060
- “]” Under section 429.060, a mechanic’s lien “shall be preferred to all other encumbrances which may be attached to or upon such buildings, bridges or other improvements, or the ground, or either of them, subsequent to the commencement of such buildings or improvements.”
- Later courts cite it for
- “a legislative response to a judicial pronouncement provides reliable indicia of intent and purpose of lawmaking activity.” · 2 citing courts
- Where it cites § 429.060
- “§ 429.060; Dave Kolb Grading, 837 S.W.2d at 934 ; Glaseo, 751 S.”
- Where it cites § 429.060
- “See Mo. Rev. Stat. § 429.060 . Fidelity also deleted the policy language that required the loan to be fully funded.”
- Where it cites § 429.060
- “” Mo.Rev.Stat. § 429.060. . The loan policy provides coverage for mechanics' liens at Insuring Provision 7.”
- Where it cites § 429.060
- “The lien for work and materials as aforesaid shall be preferred to all other encumbrances which may be attached to or upon such buildings, bridges or other improvements, or the ground, or either of them, subsequent to the commencement of such buildings or improvements.”
- The case’s holding
- Commencement of an improvement requires visible actual operations on the ground performed with the intention to continue the work until completion.
- Later courts cite it for
- “the visible commencement of actual operations on the ground for the erection of the building or the making of the improvement which makes it apparent that a building has been commenced or that an improvement is to be made, done with the intention and formed purpose to continue the work until completed.” · 2 citing courts
- Where it cites § 429.060
- “If the loan proceeds were not used to purchase the real property, then Allied’s lien is superior to the deed of trust under § 429.060 RSMo and the “first spade rule”, since we have determined that the lien relates back to June 7, 1984.”
- Where it cites § 429.060
- “[8] Section 429.060, R.S.Mo.1969, V.A.M.S. provides: "The lien for work and materials as aforesaid shall be preferred to all other encumbrances which may be attached to or upon such buildings, bridges or other improvements, or the ground, or either of them, subsequent to the…”
- Where it cites § 429.060
- “On the other hand, the respondents have priority under § 429.060 as to the land itself because their deeds of trust were perfected prior to the commencement of any work by appellant.”
- Where it cites § 429.060
- “1967), to the following effect: *923 “A mechanic’s lien properly filed dates from the commencement of the building or improvement, Section 429.060 ... The commencement of the building or improvement, under the ‘first spade rule’ which we recognize in this state, means the…”
- Where it cites § 429.060
- “§ 429.060 sets the priority of the liens as to buildings, etc.”
- The case’s holding
- A security interest holder is not an owner or cestui que trust under mechanics' lien statutes and does not require notice of intention to file liens.
- Later courts cite it for
- “the 10 day notice of intentions to file liens which may be gleaned from the mechanics' lien statutes.” · 2 citing courts
Show all 27 citing cases (list view) →
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
One bar per year. Tallest: 2 cases in 1972. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.
Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.
Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.
Edition shown: laws through the 2026 session (checked Sept. 2026). Syfert holds no earlier or later version of this section.