533.390 Statement of work actually constructed; verification; penalty
for failure to file proof of completion of work.
1. Any person holding a permit from the
State Engineer shall, on or before the date set for the completion of the work,
file in detail a description of the work as actually constructed. This
statement must be verified by the affidavit of the applicant or the applicant’s
agent or attorney.
2. Should any person holding a permit from
the State Engineer fail to file with the State Engineer the proof of completion
of work, as provided in this chapter, the State Engineer shall advise the
holder of the permit, by registered or certified mail, that it is held for
cancellation, and should the holder, within 30 days after the mailing of such
advice, fail to file the required affidavit, the State Engineer shall cancel
the permit. For good cause shown, upon application made prior to the expiration
of the 30-day period, the State Engineer may, in his or her discretion, grant
an extension of time in which to file the instruments.
[67:140:1913; A 1951,
132]—(NRS A 1967,
194; 1981,
113)
Notes of Decisions
Engelmann v. Westergard, 647 P.2d 385 (Nev. 1982).
· cites it 6× “end the time within which construction work shall begin, within which construction work shall be completed, or water applied to a beneficial use under any permit therefore issued by the state engineer; but an application for such extension must in all cases be made within 30…”
State Eng'r Vs. Happy Creek, Inc., 2019 NV 41 (Nev. 2019).
· cites it 4× “If any permit is cancelled under the provisions of NRS 533.390, 533.395 or 533.410; the holder of the permit may within 60 days of the cancellation• of the permit file a written petition with the state engineer requesting a review of the cancellation by the state engineer at a…”
— Nev. Rev. Stat. § 533.390(2) — 1 case
Engelmann v. Westergard, 647 P.2d 385 (Nev. 1982).
“end the time within which construction work shall begin, within which construction work shall be completed, or water applied to a beneficial use under any permit therefore issued by the state engineer; but an application for such extension must in all cases be made within 30…”
Annotations are extracted automatically from the opinions in the
Syfert caselaw corpus and ranked by authority, recency, and
treatment. Dots show Syfertize treatment of the citing case itself.