Ohio Revised Code homeSearch Ohio
Ohio Rev. CodeChapter 4906

Ohio Rev. Code § 4906.04 (2026)

Certificate required for construction of major utility facility

Edition and currency
laws through the 2026 session (checked Sept. 2026). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTlaws through the 2026 session (checked Sept. 2026) ACTIVE · 4 IN 5Y cited 2010–2026 6citing cases
At a glance

Courts have cited this section in 6 opinions since 2010, 4 of them in the last five years. The most litigated part is subsection (B)(1) (1 case).

No person shall commence to construct a major utility facility in this state without first having obtained a certificate for the facility. The replacement of an existing facility with a like facility, as determined by the power siting board, shall not constitute construction of a major utility facility. Such replacement of a like facility is not exempt from any other requirements of state or local laws or regulations. Any facility, with respect to which such a certificate is required, shall thereafter be constructed, operated, and maintained in conformity with such certificate and any terms, conditions, and modifications contained therein. A certificate may only be issued pursuant to Chapter 4906. of the Revised Code.

A certificate may be transferred, subject to the approval of the board, to a person who agrees to comply with the terms, conditions, and modifications contained therein.

The 6 cases that cite Ohio Rev. Code § 4906.04 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENIn re Application of Buckeye Wind, L.L.C., 2012-Ohio-878, 131 Ohio St. 3d 449.
cites § 4906.04 2×cited by 15 cases
Where it cites § 4906.04
“See R.C. 4906.04. A group of neighboring landowners, Union Neighbors United (“UNU”), Robert and Diane McConnell, and Julia Johnson (collectively, “the neighbors”), opposed the application.”
The case’s holding
The Power Siting Board may grant a major utility facility certificate subject to whatever terms, conditions, or modifications of construction, operation, or maintenance it considers appropriate.
Later courts cite it for
“upon such terms, conditions, or modifications of the construction, operation, or maintenance of the major utility facility as the board considers appropriate.” · 1 citing court
2
GREENIn re Application of Middletown Coke Co., 2010-Ohio-5725, 939 N.E.2d 1210.
cites § 4906.04 6×subsections: (B)(1) 2×cited by 3 cases
Where it cites § 4906.04
“R.C. 4906.04. Under R.C. 4906.01(B)(1), a “major utility facility” includes “[e]lectric generating plant and associated facilities designed for, or capable of, operation at a capacity of fifty megawatts or more.”
3
GREENIn re Application of Suburban Nat. Gas Co., 2021-Ohio-3224, 184 N.E.3d 44.
cites § 4906.04 1×cited by 3 cases
Where it cites § 4906.04
“See R.C. 4906.04. But by keeping the extension below five miles, Suburban was able to take advantage of an expedited approval process before the Power Siting Board.”
Later courts cite it for
“the prudent-investment test is backward-looking," asking whether the investment was "prudent when it was made” · 1 citing court
cites § 4906.04 2×cited by 1 case
Where it cites § 4906.04
“FACTS AND PROCEDURAL BACKGROUND {¶ 4} R.C. 4906.04 provides that no person shall construct a major utility facility in Ohio without first having obtained a construction certificate from the board.”
5
GREENIn re Application of Harvey Solar I, L.L.C., 2025-Ohio-1503, 267 N.E.3d 649.
cites § 4906.04 1×cited by 1 case
Where it cites § 4906.04
“R.C. 4906.04. In August 2021, Harvey Solar applied to build a solar farm in Hartford and Bennington Townships in Licking County that would generate up to 350 megawatts.”
Later courts cite it for
“it is well-settled that the board is not required to resolve every issue before issuing a certificate.” · 1 citing court
6
NEUTRALIn re Application of Oak Run Solar Proj., L.L.C., 2026-Ohio-1849, 279 N.E.3d 599.
cites § 4906.04 1×cited by 0 cases
Where it cites § 4906.04
“01(B)(1) (defining “major utility facility”); R.C. 4906.04 (“No person shall commence to construct a major utility facility in this state without first having obtained a certificate for the facility.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
201020182026

One bar per year. Tallest: 1 case in 2010. 2026 is a partial year. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By subsection
(B)(1)1 case
In re Application of Middletown Coke Co., 2010-Ohio-5725, 939 N.E.2d 1210.“R.C. 4906.04. Under R.C. 4906.01(B)(1), a “major utility facility” includes “[e]lectric generating plant and associated facilities designed for, or capable of, operation at a capacity of fifty megawatts or more.”
Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: laws through the 2026 session (checked Sept. 2026). Syfert holds no earlier or later version of this section.

Ohio Revised Code Home  |  Search Ohio  |  Search cases for this section  |  syfert.com