Or. Rev. Stat. § 701.565 (2026)
Notice of defect requirement; contents; mailing
Edition and currency
Other sources
Courts have cited this section in 3 opinions since 2006. The most litigated part is subsection (1) (1 case).
701.565 Notice of defect requirement; contents; mailing. (1) Except as provided in ORS 701.600, an owner may not compel arbitration or commence a court action against a contractor, subcontractor or supplier to assert a claim arising out of or related to any defect in the construction, alteration or repair of a residence or in any system, component or material incorporated into a residence located in this state unless the owner has sent that contractor, subcontractor or supplier a notice of defect as provided in this section and has complied with ORS 701.575.
(2) An owner must send a notice of defect by registered or certified mail, return receipt requested. If a notice of defect is sent to a contractor or subcontractor, the owner must send the notice to the last known address for the contractor or subcontractor as shown in the records of the Construction Contractors Board. If a notice of defect is sent to a supplier, the owner must send the notice to the Oregon business address of the supplier or, if none, to the registered agent of the supplier.
(3) A notice of defect sent by an owner must include:
(a) The name and mailing address of the owner or the owner’s legal representative, if any;
(b) A statement that the owner may seek to compel arbitration or bring a court action against the contractor, subcontractor or supplier;
(c) The address and location of the affected residence;
(d) A description of:
(A) Each defect;
(B) The remediation the owner believes is necessary; and
(C) Any incidental damage not curable by remediation as described in subparagraph (B) of this paragraph; and
(e) Any report or other document evidencing the existence of the defects and any incidental damage. [2003 c.660 §2; 2011 c.268 §1]
Note: See note under 701.560.
- Where it cites § 701.565
- “595, to dismiss the action on the ground that plaintiffs had not complied with ORS 701.565 and ORS 701.575, which require homeowners to take certain steps to allow remediation of construction problems before bringing suit against residential contractors.”
- The case’s holding
- Statutory pre-suit notice and remediation requirements for residential construction defect claims apply to any court action commenced after the statute's effective date.
- Later courts cite it for
- “we assume the truth of all allegations in the pleading and view the allegations, as well as all reasonable inferences, in the light most favorable to the nonmoving party.” · 6 citing courts
- Where it cites § 701.565
- “Plaintiff served a Notice of Defect on defendant, pursuant to ORS 701.565, on June 25, 2010. The dispute centers on which statute of repose applies to these facts.”
- Later courts cite it for
- “derive from a contractor-contractee relationship.” · 2 citing courts
- Where it cites § 701.565
- “See Or. Rev. Stat. §§ 701.565 , 701.570(5)(c)(A), 701.580.”
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
One bar per year. Tallest: 1 case in 2006. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.
(1)1 case
(2)1 case
(3)(d)1 case
Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.
Edition shown: laws through the 2025 session (checked Sept. 2026). Syfert holds no earlier or later version of this section.