Or. Rev. Stat. § 701.575 (2026)
Availability of residence; scope of inspection; report of inspection results
Edition and currency
Other sources
Courts have cited this section in 1 opinion since 2006.
701.575 Availability of residence; scope of inspection; report of inspection results. (1) An owner sending a notice of defect under ORS 701.565 shall make the residence available for visual examination pursuant to any written request sent under ORS 701.570 or 701.572. The owner shall make the residence available for visual examination, during normal business hours or as otherwise agreed, not later than 20 days after receiving the written request for visual examination.
(2) An owner sending a notice of defect under ORS 701.565 shall make the residence available for an inspection pursuant to any written request sent under ORS 701.570 or 701.572. The owner shall make the residence available for inspection during normal business hours or at a time that is mutually agreeable to the owner and the requester.
(3) An inspection by a contractor, subcontractor or supplier may include any reasonable measures, including testing, for determining the nature, cause and extent of the defects described in the notice of defect or incidental damage and the nature and extent of the necessary remediation. Unless the contractor, subcontractor or supplier conducting the inspection and the owner agree otherwise, the contractor, subcontractor or supplier conducting the inspection shall repair any damage caused by the inspection. Any damage caused by the inspection that is not repaired may be sought as incidental damage in any subsequent arbitration or court action by an owner against the contractor, subcontractor or supplier conducting the inspection.
(4) A contractor, subcontractor or supplier that requests to inspect a residence must include as part of the written response of the contractor, subcontractor or supplier under ORS 701.570, a written report or other document evidencing the result of the inspection and the existence or nonexistence of the defects described in the notice of defect or discovered during the inspection. [2003 c.660 §4; 2025 c.578 §14]
Note: See note under 701.560.
- Where it cites § 701.575
- “565 and ORS 701.575, which require homeowners to take certain steps to allow remediation of construction problems before bringing suit against residential contractors.”
- The case’s holding
- Statutory pre-suit notice and remediation requirements for residential construction defect claims apply to any court action commenced after the statute's effective date.
- Later courts cite it for
- “we assume the truth of all allegations in the pleading and view the allegations, as well as all reasonable inferences, in the light most favorable to the nonmoving party.” · 6 citing courts
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.
Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.
Edition shown: laws through the 2025 session (checked Sept. 2026). Syfert holds no earlier or later version of this section.