Skip to main content
Or. Rev. Stat.Oregon Revised Statutes

Or. Rev. Stat. § 757.210 (2026)

Hearing to establish new schedules; alternative regulation plan; mitigating increases in residential customer rates

Edition and currency
laws through the 2025 session (checked Sept. 2026). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTlaws through the 2025 session (checked Sept. 2026) cited 1961–2023 28citing cases
At a glance

Courts have cited this section in 28 opinions since 1961, 2 of them in the last five years. The most litigated part is subsection (1) (6 cases).

      757.210 Hearing to establish new schedules; alternative regulation plan; mitigating increases in residential customer rates. (1)(a) Whenever any public utility files with the Public Utility Commission any rate or schedule of rates stating or establishing a new rate or schedule of rates or increasing an existing rate or schedule of rates, the commission may, either upon written complaint or upon the commission’s own initiative, after reasonable notice, conduct a hearing to determine whether the rate or schedule is fair, just and reasonable. The commission shall conduct the hearing upon written complaint filed by the utility, its customer or customers, or any other proper party within 60 days of the utility’s filing; provided that no hearing need be held if the particular rate change is the result of an automatic adjustment clause. At the hearing the utility shall bear the burden of showing that the rate or schedule of rates proposed to be established or increased or changed is fair, just and reasonable. The commission may not authorize a rate or schedule of rates that is not fair, just and reasonable.

      (b) As used in this subsection, “automatic adjustment clause” means a provision of a rate schedule that provides for rate increases or decreases or both, without prior hearing, reflecting increases or decreases or both in costs incurred, taxes paid to units of government or revenues earned by a utility and that is subject to review by the commission at least once every two years.

      (2)(a) Subsection (1) of this section does not apply to rate changes under an approved alternative form of regulation plan, including a resource rate plan under ORS 757.212.

      (b) Any alternative form of regulation plan shall include provisions to ensure that the plan operates in the interests of utility customers and the public generally and results in rates that are just and reasonable and may include provisions establishing a reasonable range for rate of return on investment. In approving a plan, the commission shall, at a minimum, consider whether the plan:

      (A) Promotes increased efficiencies and cost control;

      (B) Is consistent with least-cost resources acquisition policies;

      (C) Yields rates that are consistent with those that would be obtained following application of ORS 757.269;

      (D) Is consistent with maintenance of safe, adequate and reliable service; and

      (E) Is beneficial to utility customers generally, for example, by minimizing utility rates.

      (c) As used in this subsection, “alternative form of regulation plan” means a plan adopted by the commission upon petition by a public utility, after notice and an opportunity for a hearing, that sets rates and revenues and a method for changes in rates and revenues using alternatives to cost-of-service rate regulation.

      (d) Prior to implementing a rate change under an alternative form of regulation plan, the utility shall present a report that demonstrates the calculation of any proposed rate change at a public meeting of the commission.

      (3) Except as provided in ORS 757.212, the commission, at any time, may order a utility to appear and establish that any, or all, of its rates in a plan authorized under subsection (2) of this section are in conformity with the plan and are just and reasonable. Except as provided in ORS 757.212, such rates, and the alternative form of regulation plan under which the rates are set, also shall be subject to complaint under ORS 756.500.

      (4) Periodically, but not less often than every two years after the implementation of a plan referred to in subsection (2) of this section, the commission shall submit a report to the Legislative Assembly that shows the impact of the plan on rates paid by utility customers.

      (5) The commission and staff may consult at any time with, and provide technical assistance to, utilities, their customers, and other interested parties on matters relevant to utility rates and charges. If a hearing is held with respect to a rate change, the commission’s decisions shall be based on the record made at the hearing.

      (6) The commission may adjust rates to mitigate an increase in residential customer rates if the increase is of such magnitude that, if applied at the higher rate or all at one time, the increase would affect the ability of residential customers to maintain adequate utility service. In considering whether to adjust rates under this subsection, the commission:

      (a) Must determine whether the proposed adjusted rates are fair, just and reasonable;

      (b) May not adjust rates in a manner that results in rates that are not fair, just and reasonable; and

      (c) Shall consider and may approve deferred accounting for future cost recovery from customers for those amounts that are subject to rate mitigation.

      (7) Any increase in residential rates may not take effect from November 1 to March 31. [Amended by 1971 c.655 §70a; 1981 c.715 §1; 1985 c.550 §2; 1987 c.447 §97; 1987 c.613 §1; 1989 c.5 §§3,23; 1995 c.785 §1; 2001 c.913 §3; 2005 c.845 §5; 2011 c.137 §3; 2025 c.503 §3]

The 20 cases that cite Or. Rev. Stat. § 757.210 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENPac. Nw. Bell Tel. Co. v. Davis, 608 P.2d 547 (Or. Ct. App. 1979).
cites § 757.210 10×cited by 11 cases
Where it cites § 757.210
“" They first contend that the standard of proof provisions are invalid because they contravene or impermissably expand on the statutory standard of proof, ORS 757.210, [11] and because they are not reasonably calculated to accomplish the legislative purpose.”
Later courts cite it for
“adopt and amend reasonable and proper rules and regulations relative to all statutes administered by him,” · 1 citing court
2
GREENGearhart v. Pub. Util. Comm'n, 299 P.3d 533 (Or. Ct. App. 2013).
cites § 757.210 6×cited by 9 cases
Where it cites § 757.210
“The rates named therein are the lawful rates until they are changed as provided in ORS 757.210 to 757.220.” See also Dreyer, 341 Or at 279 (holding that ORS 757.225 is “a direction to utilities to charge all their ratepayers the PUC-approved rate and, if a utility is dissatisfied with a rate, to obtain a new PUC-approved rate” through the statutory processes set out in ORS 757.210 to 757.220).”
The case’s holding
Ratemaking is judged by the lawfulness of its end result, not the legality of each calculation or input, so an unlawful rate component does not invalidate rates absent unrectified harm to ratepayers.
Later courts cite it for
“we hold that the puc's conclusion-that the inclusion of the unlawful component did not cause the rates to be unjust or unreasonable and, therefore, has not resulted in any unrectified damages to ratepayers-was consonant with the remands and the puc's responsibility.” · 3 citing courts
3
GREENDreyer v. Portland Gen. Elec. Co., 142 P.3d 1010 (Or. 2006).
cites § 757.210 5×cited by 12 cases
Where it cites § 757.210
“225 manifests a legislative intent that PUC-approved rates be treated as conclusively lawful for all purposes “until they are *279 changed as provided in ORS 757.210 to 757.220.” We find it significant that, although the public utility statutes provide more than one process for…”
The case’s holding
A court must stay proceedings when an administrative agency has primary jurisdiction over the issues involved (concluding that court had legal duty to abate the proceedings pending agency's resolution).
Later courts cite it for
“what, if any, remedy it could offer to pge ratepayers, through rate reductions or refunds, for the amounts that pge collected in violation of ors 757.355 (1993) between april 1995 and october 2000.” · 4 citing courts
4
GREENGearhart v. Pub. Util. Comm'n, 356 P.3d 216 (Or. 2014).
cites § 757.210 3×subsections: (1)(a)cited by 16 cases
Where it cites § 757.210
“The rates named therein are the lawful rates until they are changed as provided in ORS 757.210 to 757.220.” The court in Dreyer did not find that argument persuasive.”
The case’s holding
A public utility commission may reexamine past rates and order refunds to remedy legal errors identified on judicial review without violating the prohibition against retroactive ratemaking.
Later courts cite it for
“there is no single correct sum, but rather a range of reasonable rates.” · 2 citing courts
5
GREENAm. Can Co. v. Davis, 559 P.2d 898 (Or. Ct. App. 1977).
cites § 757.210 3×cited by 25 cases
Where it cites § 757.210
“The Commissioner then held hearings, as provided by ORS 757.210, to determine whether the proposed rates were just and reasonable.”
The case’s holding
The court noted that the utility serves customers in parts of Portland, a factual observation about service territory rather than a stated legal rule.
Later courts cite it for
“commensurate with that of the legislature itself.” · 1 citing court
cites § 757.210 1×cited by 365 cases
Where it cites § 757.210
“Likewise, the Public Utility Commissioner is required to regulate public utilities so as to allow them rates that are "just and reasonable,” ORS 757.210, and to "protect such customers, and the public generally, from unjust and unreasonable extractions and practices and to…”
The case’s holding
Administrative agencies hold the authority to interpret delegative terms such as good cause, which require the agency to make general policy decisions (basis: delegative terms require agencies to make general policy decisions).
Later courts cite it for
“within the range of discretion allowed by the more general policy of the statute.” · 17 citing courts
7
GREENUtil. Reform Proj. v. Pub. Util. Comm'n, 323 P.3d 430 (Or. Ct. App. 2014).
cites § 757.210 7×subsections: (1) 3×cited by 2 cases
Where it cites § 757.210
“259(5) provides that, unless subject to an automatic adjustment clause, the deferral and amortization of amounts described in subsection (2) “shall be allowed in rates only to the extent authorized by the commission in a proceeding under ORS 757.210 to change rates and upon…”
8
GREENUtil. Reform Proj. v. Oregon Pub. Util. Comm'n, 170 P.3d 1074 (Or. Ct. App. 2007).
cites § 757.210 2×cited by 8 cases
Where it cites § 757.210
“The rates named therein are the lawful rates until they are changed as provided in ORS 757.210 to 757.220.” According to the PUC, “[t]he statute does not allow for retroactive changes pursuant to court decision or otherwise.”
The case’s holding
An administrative commission order based on an erroneous legal conclusion regarding the filed-rate doctrine must be remanded for reconsideration of the underlying issues.
Later courts cite it for
“remanded to circuit court with instructions to remand order no. 02-227 to puc for reconsideration of issues raised on appeal and cross-appeal.” · 2 citing courts
9
GREENPac. Tel. & Tel. Co. v. Hill, 367 P.2d 790 (Or. 1961).
cites § 757.210 4×cited by 9 cases
Where it cites § 757.210
“Rates must be "just and reasonable," ORS 757.210. Mr. Bushnell, as a witness, expounded upon a method of rate fixing of which we will now take notice.”
Later courts cite it for
“the rate base represents the invested capital upon which the utility is entitled to earn a return.” · 2 citing courts
10
GREENCalpine Energy Solutions LLC v. Pub. Util. Comm'n of Or., 445 P.3d 308 (Or. Ct. App. 2019).
cites § 757.210 4×subsections: (1)(a) 4×cited by 1 case
Where it cites § 757.210
“We first summarize the regulatory landscape, as applicable to this case, to provide context for the PUC order on review. Under ORS 756.040(1), the PUC is directed to "balance the interests of the utility investor and the consumer in establishing fair and reasonable rates"…”
Later courts cite it for
“as such, our review is 'confined to the record,' and we will 'not substitute our judgment for that of the puc as to any issue of fact or agency discretion.” · 2 citing courts
11
GREENGarrison v. Pac. Nw. Bell, 608 P.2d 1206 (Or. Ct. App. 1980).
cites § 757.210 1×cited by 23 cases
Where it cites § 757.210
“565, "All rates, tariffs, classifications, regulations, practices and service fixed, approved or prescribed by the commissioner * * * shall be in force and shall be prima facie lawful and reasonable, until found otherwise in a proceeding brought for *530 that purpose under ORS…”
The case’s holding
State regulation limiting a telephone company's liability for its own negligence is valid (upholding state regulation limiting telephone company's liability where it has acted negligently).
Later courts cite it for
“gross negligence is characterized by conscious indifference to or reckless disregard of the rights of others.” · 3 citing courts
12
GREENFields v. Davis, 571 P.2d 511 (Or. Ct. App. 1977).
cites § 757.210 3×cited by 3 cases
Where it cites § 757.210
“Whenever a new tariff is filed, or when the rates in an existing tariff are changed, the Commissioner may, either upon written complaint from a member of the public or at his own initiative, conduct an investigation and a hearing to determine the propriety and reasonableness of…”
Later courts cite it for
“(b) subject to the provisions of section 301 of this title, nothing in this chapter shall be construed to apply, or to give the commission jurisdiction, with respect to charges, classifications, practices, services, facilities, or regulations for or in connection with wire, mobile, or point-to-point radio telephone exchange service, or any combination thereof, even though a portion of such exchange service constitutes interstate or foreign communication, in any case where such matters are subject to regulation by a state commission or by local governmental authority.” · 2 citing courts
13
GREENMultnomah Cnty. v. Davis, 581 P.2d 968 (Or. Ct. App. 1978).
cites § 757.210 3×cited by 3 cases
Where it cites § 757.210
“ORS 757.210, 757.215, 757.220 and 757.225.”
14
GREENCascade Nat. Gas Corp. v. Davis, 560 P.2d 301 (Or. Ct. App. 1977).
cites § 757.210 1×cited by 11 cases
Where it cites § 757.210
“ORS 757.210. Setting of utility rates is a process of allowing a certain rate of return on a rate base, i.”
Later courts cite it for
“beyond that the judgment of the psc is not reviewable by this court.” · 1 citing court
15
GREENSimpson v. Phone Directories Co., 729 P.2d 578 (Or. Ct. App. 1986).
cites § 757.210 1×cited by 11 cases
Where it cites § 757.210
“Under ORS 757.210, when a public utility files a new schedule of rates, the PUC may, on a complaint being made or on its own motion, conduct hearings to determine the reasonableness of rates.”
16
GREENPac. Nw. Bell Tel. Co. v. Sabin, 534 P.2d 984 (Or. Ct. App. 1975).
cites § 757.210 1×cited by 31 cases
Where it cites § 757.210
“” ORS 757.210. ④ By comparing the gross operating revenues found to have been earned during the designated “test” period to the sum of (1) the utility’s costs and expenses for that period, and (2) the product of the rate base multiplied by the rate of return, the Commissioner is…”
The case’s holding
A regulatory commission is not required to use a single formula to determine just and reasonable rates and is not estopped by prior approvals from exercising regulatory discretion.
Later courts cite it for
“is not obligated to employ any single formula or combination of formulas to determine what are in each case 'just and reasonable rates.” · 2 citing courts
17
cites § 757.210 7×subsections: (1) 2×cited by 3 cases
Where it cites § 757.210
“2 In each case, the PUC opened a proceeding for the filing and held hearings pursuant to ORS 757.210 to examine the propriety and reasonableness of the rate revision.”
18
NEUTRALUtil. Reform Proj. v. Oregon Pub. Util. Comm'n, 16 P.3d 516 (Or. Ct. App. 2000).
cites § 757.210 6×subsections: (1) 6×cited by 3 cases
Where it cites § 757.210
“At portions of the brief, plaintiffs complain about the failure of the Commission to conduct a “contested case,” as provided in ORS 183.”
19
GREENNw. Climate Conditioning Ass'n v. Lobdell, 720 P.2d 1281 (Or. Ct. App. 1986).
cites § 757.210 2×cited by 2 cases
Where it cites § 757.210
“A utility’s rate schedules are subject to review by the Commissioner, ORS 757.210, and in setting “just and reasonable” rates he has “great discretion.”
20
GREENIndus. Customers of Nw. Utils. v. Pub. Util. Comm'n, 100 P.3d 1072 (Or. Ct. App. 2004).
cites § 757.210 1×subsections: (1)cited by 2 cases
Where it cites § 757.210
“259(5) 1 requires PUC to conduct an earnings review to determine whether the utility can afford to absorb the costs and a rate change proceeding under ORS 757.210(1) to determine whether the proposed rate increase is “just and reasonable.”

Show all 28 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
196119922023

One bar per year. Tallest: 4 cases in 2014. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Or. Ct. App.20Or.7Or. T.C.1
By subsection
(1)6 cases
Util. Reform Proj. v. Pub. Util. Comm'n, 323 P.3d 430 (Or. Ct. App. 2014).“259(5) provides that, unless subject to an automatic adjustment clause, the deferral and amortization of amounts described in subsection (2) “shall be allowed in rates only to the extent authorized by the commission in a proceeding under ORS 757.210 to change rates and upon…”
Util. Reform Proj. v. Oregon Pub. Util. Comm'n, 16 P.3d 516 (Or. Ct. App. 2000).“At portions of the brief, plaintiffs complain about the failure of the Commission to conduct a “contested case,” as provided in ORS 183.”
Indus. Customers of Nw. Utils. v. Pub. Util. Comm'n, 100 P.3d 1072 (Or. Ct. App. 2004).“259(5) 1 requires PUC to conduct an earnings review to determine whether the utility can afford to absorb the costs and a rate change proceeding under ORS 757.210(1) to determine whether the proposed rate increase is “just and reasonable.”
Low-Income Consumers Union v. Oregon Pub. Util. Comm'n, 946 P.2d 1164 (Or. Ct. App. 1997).
Coalition for Safe Power v. Oregon Pub. Util. Comm'n, 939 P.2d 1167 (Or. 1997).“2 In each case, the PUC opened a proceeding for the filing and held hearings pursuant to ORS 757.210 to examine the propriety and reasonableness of the rate revision.”
Showing the top 5 of 6. More in the list view →
(1)(a)5 cases
Gearhart v. Pub. Util. Comm'n, 356 P.3d 216 (Or. 2014).“The rates named therein are the lawful rates until they are changed as provided in ORS 757.210 to 757.220.” The court in Dreyer did not find that argument persuasive.”
Calpine Energy Solutions LLC v. Pub. Util. Comm'n of Or., 445 P.3d 308 (Or. Ct. App. 2019).“We first summarize the regulatory landscape, as applicable to this case, to provide context for the PUC order on review. Under ORS 756.040(1), the PUC is directed to "balance the interests of the utility investor and the consumer in establishing fair and reasonable rates"…”
Util. Reform Proj. v. Oregon Pub. Util. Comm'n, 372 P.3d 517 (Or. Ct. App. 2016).
Nw. Pub. Commc'ns Council v. Qwest, 527 P.3d 30 (Or. Ct. App. 2022).
Gearhart v. PUC, 339 P.3d 904 (Or. 2014).

Show all 28 citing cases (list view) →

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions