CURRENTlaws through the 2025 session (checked Sept. 2026) cited 2004–2023 7citing cases
At a glance

Courts have cited this section in 7 opinions since 2004, 1 of them in the last five years. The most litigated part is subsection (4) (3 cases).

      757.259 Amounts includable in rate schedule; deferral; limit in effect on rates by amortization; rules. (1) In addition to powers otherwise vested in the Public Utility Commission, and subject to the limitations contained in this section, under amortization schedules set by the commission, a rate or rate schedule:

      (a) May reflect:

      (A) Amounts lawfully imposed retroactively by order of another governmental agency; or

      (B) Amounts deferred under subsection (2) of this section.

      (b) Shall reflect amounts deferred under subsection (3) of this section if the public utility so requests.

      (2) Upon application of a utility or ratepayer or upon the commission’s own motion and after public notice, opportunity for comment and a hearing if any party requests a hearing, the commission by order may authorize deferral of the following amounts for later incorporation in rates:

      (a) Amounts incurred by a utility resulting from changes in the wholesale price of natural gas or electricity approved by the Federal Energy Regulatory Commission;

      (b) Balances resulting from the administration of Section 5(c) of the Pacific Northwest Electric Power Planning and Conservation Act of 1980;

      (c) Direct or indirect costs arising from any purchase made by a public utility from the Bonneville Power Administration pursuant to ORS 757.663, provided that such costs shall be recovered only from residential and small-farm retail electricity consumers;

      (d) Amounts accruing under a plan for the protection of short-term earnings under ORS 757.262 (2); or

      (e) Identifiable utility expenses or revenues, the recovery or refund of which the commission finds should be deferred in order to minimize the frequency of rate changes or the fluctuation of rate levels or to match appropriately the costs borne by and benefits received by ratepayers.

      (3) Upon request of the public utility, the commission by order shall allow deferral of amounts provided as financial assistance under an agreement entered into under ORS 757.072 for later incorporation in rates.

      (4) The commission may authorize deferrals under subsection (2) of this section beginning with the date of application, together with interest established by the commission. A deferral may be authorized for a period not to exceed 12 months beginning on or after the date of application. However, amounts deferred under subsection (2)(c) and (d) or (3) of this section are not subject to subsection (5), (6), (7), (8) or (10) of this section, but are subject to such limitations and requirements that the commission may prescribe and that are consistent with the provisions of this section.

      (5) Unless subject to an automatic adjustment clause under ORS 757.210 (1), amounts described in this section shall be allowed in rates only to the extent authorized by the commission in a proceeding under ORS 757.210 to change rates and upon review of the utility’s earnings at the time of application to amortize the deferral. The commission may require that amortization of deferred amounts be subject to refund. The commission’s final determination on the amount of deferrals allowable in the rates of the utility is subject to a finding by the commission that the amount was prudently incurred by the utility.

      (6) Except as provided in subsections (7), (8) and (10) of this section, the overall average rate impact of the amortizations authorized under this section in any one year may not exceed three percent of the utility’s gross revenues for the preceding calendar year.

      (7) The commission may allow an overall average rate impact greater than that specified in subsection (6) of this section for natural gas commodity and pipeline transportation costs incurred by a natural gas utility if the commission finds that allowing a higher amortization rate is reasonable under the circumstances.

      (8) The commission may authorize amortizations for an electric utility under this section with an overall average rate impact not to exceed six percent of the electric utility’s gross revenues for the preceding calendar year. If the commission allows an overall average rate impact greater than that specified in subsection (6) of this section, the commission shall estimate the electric utility’s cost of capital for the deferral period and may also consider estimated changes in the electric utility’s costs and revenues during the deferral period for the purpose of reviewing the earnings of the electric utility under the provisions of subsection (5) of this section.

      (9) The commission may impose requirements similar to those described in subsection (8) of this section for the amortization of other deferrals under this section, but may not impose such requirements for deferrals under subsection (2)(c) or (d) or (3) of this section.

      (10) The commission may authorize amortization of a deferred amount for an electric utility under this section with an overall average rate impact greater than that allowed by subsections (6) and (8) of this section if:

      (a) The deferral was directly related to extraordinary power supply expenses incurred during 2001;

      (b) The amount to be deferred was greater than 40 percent of the revenue received by the electric utility in 2001 from Oregon customers; and

      (c) The commission determines that the higher rate impact is reasonable under the circumstances.

      (11) If the commission authorizes amortization of a deferred amount under subsection (10) of this section, an electric utility customer that uses more than one average megawatt of electricity at any site in the immediately preceding calendar year may prepay the customer’s share of the deferred amount. The commission shall adopt rules governing the manner in which:

      (a) The customer’s share of the deferred amount is calculated; and

      (b) The customer’s rates are to be adjusted to reflect the prepayment of the deferred amount.

      (12) The provisions of this section do not apply to a telecommunications utility. [1987 c.563 §2; 1989 c.18 §1; 1989 c.956 §1; 1993 c.175 §1; 1999 c.865 §31; 2001 c.733 §3; 2003 c.132 §1; 2003 c.234 §3]

 

      757.260 [Amended by 1971 c.655 §18; renumbered 756.075]

The 7 cases that cite Or. Rev. Stat. § 757.259 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENUtil. Reform Proj. v. Pub. Util. Comm'n, 323 P.3d 430 (Or. Ct. App. 2014).
cites § 757.259 40×subsections: (5) 12× (8) 4× (2)(e) 2× (6)cited by 2 cases
Where it cites § 757.259
“610(1), petitioners Utility Reform Project and Ken Lewis (collectively referred to as URP) seek judicial review of an order of the Public Utility Commission (PUC) denying URP’s request under ORS 757.259 to direct respondent Portland General Electric (PGE) to amortize certain…”
2
GREENGearhart v. Pub. Util. Comm'n, 299 P.3d 533 (Or. Ct. App. 2013).
cites § 757.259 2×cited by 9 cases
Where it cites § 757.259
“Portland General Electric Company may seek recovery of the incremental administrative costs of implementing the refund mechanism by seeking a deferral of costs through an application filed pursuant to ORS 757.259. “5. Utility Reform Project’s and the Class Action Plaintiffs’…”
The case’s holding
Ratemaking is judged by the lawfulness of its end result, not the legality of each calculation or input, so an unlawful rate component does not invalidate rates absent unrectified harm to ratepayers.
Later courts cite it for
“we hold that the puc's conclusion-that the inclusion of the unlawful component did not cause the rates to be unjust or unreasonable and, therefore, has not resulted in any unrectified damages to ratepayers-was consonant with the remands and the puc's responsibility.” · 3 citing courts
3
GREENIndus. Customers of Nw. Utils. v. Pub. Util. Comm'n, 100 P.3d 1072 (Or. Ct. App. 2004).
cites § 757.259 5×subsections: (5) 3× (4)cited by 2 cases
Where it cites § 757.259
“A utility may then apply to PUC for permission to recover (or refund) the deferred amounts through amortization in future rates.”
4
GREENGearhart v. Pub. Util. Comm'n, 356 P.3d 216 (Or. 2014).
cites § 757.259 1×subsections: (4)cited by 16 cases
Where it cites § 757.259
“215(6) (requiring the PUC to include interest on amount subject to refund after the PUC approves rates lower than interim rates); ORS 757.259(4) (allowing the PUC to authorize deferrals for later incorporation in rates of certain amounts, “together with interest established by…”
The case’s holding
A public utility commission may reexamine past rates and order refunds to remedy legal errors identified on judicial review without violating the prohibition against retroactive ratemaking.
Later courts cite it for
“there is no single correct sum, but rather a range of reasonable rates.” · 2 citing courts
5
NEUTRALUtil. Reform Proj. v. Oregon Pub. Util. Comm'n, 372 P.3d 517 (Or. Ct. App. 2016).
cites § 757.259 7×subsections: (5) 4×cited by 1 case
Where it cites § 757.259
“account for “the difference between the balance derived from rates that included a return on PGE’s remaining Trojan investment and the balance derived from adjusted rates that excluded that return,” and (4) PGE “may seek recovery of the incremental administrative costs of…”
Later courts cite it for
“however, the puc does not have discretion to misinterpret or misapply the law, and we will not affirm if the formula used by the puc was based on an erroneous interpretation of the law, or was specifically precluded by some source of law.” · 1 citing court
6
NO FLAGPacifiCorp v. Dept. of Rev., No. TC 5411 (Or. T.C. July 17, 2023).
cites § 757.259 1×cited by 0 casesunpublished
Where it cites § 757.259
“While the court agrees with Defendant that regulators may provide for inflation, either in a rate case under ORS 757.259 or through an automatic adjustment clause under ORS 757.”
7
NO FLAGGearhart v. PUC, 339 P.3d 904 (Or. 2014).
cites § 757.259 1×subsections: (4)cited by 0 cases
Where it cites § 757.259
“215(6) (requiring the PUC to include interest on amount subject to refund after the PUC approves rates lower than interim rates); ORS 757.259(4) (allowing the PUC to authorize deferrals for later incorporation in rates of certain amounts, “together with interest established by…”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
200420132023

One bar per year. Tallest: 3 cases in 2014. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Or. Ct. App.4Or.2Or. T.C.1
By subsection
(2)(e)1 case
Util. Reform Proj. v. Pub. Util. Comm'n, 323 P.3d 430 (Or. Ct. App. 2014).“610(1), petitioners Utility Reform Project and Ken Lewis (collectively referred to as URP) seek judicial review of an order of the Public Utility Commission (PUC) denying URP’s request under ORS 757.259 to direct respondent Portland General Electric (PGE) to amortize certain…”
(4)3 cases
Gearhart v. Pub. Util. Comm'n, 356 P.3d 216 (Or. 2014).“215(6) (requiring the PUC to include interest on amount subject to refund after the PUC approves rates lower than interim rates); ORS 757.259(4) (allowing the PUC to authorize deferrals for later incorporation in rates of certain amounts, “together with interest established by…”
Indus. Customers of Nw. Utils. v. Pub. Util. Comm'n, 100 P.3d 1072 (Or. Ct. App. 2004).“A utility may then apply to PUC for permission to recover (or refund) the deferred amounts through amortization in future rates.”
Gearhart v. PUC, 339 P.3d 904 (Or. 2014).“215(6) (requiring the PUC to include interest on amount subject to refund after the PUC approves rates lower than interim rates); ORS 757.259(4) (allowing the PUC to authorize deferrals for later incorporation in rates of certain amounts, “together with interest established by…”
(5)3 cases
Util. Reform Proj. v. Pub. Util. Comm'n, 323 P.3d 430 (Or. Ct. App. 2014).
Indus. Customers of Nw. Utils. v. Pub. Util. Comm'n, 100 P.3d 1072 (Or. Ct. App. 2004).
Util. Reform Proj. v. Oregon Pub. Util. Comm'n, 372 P.3d 517 (Or. Ct. App. 2016).“account for “the difference between the balance derived from rates that included a return on PGE’s remaining Trojan investment and the balance derived from adjusted rates that excluded that return,” and (4) PGE “may seek recovery of the incremental administrative costs of…”
(6)1 case
Util. Reform Proj. v. Pub. Util. Comm'n, 323 P.3d 430 (Or. Ct. App. 2014).
(8)1 case
Util. Reform Proj. v. Pub. Util. Comm'n, 323 P.3d 430 (Or. Ct. App. 2014).
(11)1 case
Util. Reform Proj. v. Pub. Util. Comm'n, 323 P.3d 430 (Or. Ct. App. 2014).
Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: laws through the 2025 session (checked Sept. 2026). Syfert holds no earlier or later version of this section.

Oregon Revised Statutes Home  |  Search Oregon  |  Search cases for this section  |  syfert.com