Or. Rev. Stat. § 758.015 (2026)

Certificate of public convenience and necessity

Edition and currency
laws through the 2025 session (checked Sept. 2026). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTlaws through the 2025 session (checked Sept. 2026) cited 1987–2005 5citing cases
At a glance

Courts have cited this section in 5 opinions since 1987.

      758.015 Certificate of public convenience and necessity. (1) When any person, as defined in ORS 758.400, providing electric utility service, as defined in ORS 758.400, or any transmission company, proposes to construct an overhead transmission line which will necessitate a condemnation of land or an interest therein, it shall petition the Public Utility Commission for a certificate of public convenience and necessity setting forth a detailed description and the purpose of the proposed transmission line, the estimated cost, the route to be followed, the availability of alternate routes, a description of other transmission lines connecting the same areas, and such other information in such form as the commission may reasonably require in determining the public convenience and necessity.

      (2)(a) The commission shall give notice and hold a public hearing on such petition. The commission, in addition to considering facts presented at such hearing, shall make the commission’s own investigation to determine whether the proposed transmission line meets a need for increased transmission capacity and reliability in the electric grid and shall enter an order accordingly. The commission shall consider a petition for a certificate of public convenience and necessity and enter an order without requiring a petitioner to first obtain any required state or local land use approvals.

      (b) Except for petitions for a proposed transmission line for which the petitioner also seeks approval from the Energy Facility Siting Council for the same transmission line, the order shall be subject to review as in other cases. Orders on petitions for a proposed transmission line for which the petitioner also seeks approval from the Energy Facility Siting Council for the same transmission line are subject to judicial review in the same manner as an order in a contested case as set forth in ORS 758.017.

      (c) In any proceeding for condemnation, a certified copy of such order shall be conclusive evidence that the transmission line for which the land is required is a public use and necessary for public convenience.

      (3) This section shall not apply to construction of transmission lines in connection with a project for which a permit or license is otherwise obtained pursuant to state or federal law.

      (4) As used in this section and ORS 758.020, “transmission company” means a person or entity that owns or operates high voltage transmission lines and is subject to the jurisdiction of the Federal Energy Regulatory Commission. “Transmission company” does not include a cooperative organized under ORS chapter 62. [1961 c.691 §19; 2001 c.913 §6; 2013 c.335 §1; 2025 c.305 §4]

The 5 cases that cite Or. Rev. Stat. § 758.015 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENSpringfield Util. Bd. v. Emerald PUD, 125 P.3d 740 (Or. 2005).
cites § 758.015 2×cited by 16 cases
Where it cites § 758.015
“470 provides, in part: "(1) ORS 758.015 and 758.400 to 758.475 shall not be construed or applied to restrict the powers granted to cities to issue franchises, or to restrict the exercise of the power of condemnation by a municipality; and when a municipality has condemned or…”
Later courts cite it for
“provide authority for the people of a city to determine the organization, and to define the powers, of their local government without first having to obtain authorization from the state legislature.” · 2 citing courts
2
GREENPacificorp v. City of Ashland, 744 P.2d 257 (Or. Ct. App. 1987).
cites § 758.015 5×cited by 4 cases
Where it cites § 758.015
“It provides: “(1) ORS 758.015 and 758.400 to 758.475 shall not be construed or applied to restrict the powers granted to cities to issue franchises, or to restrict the exercise of the power of condemnation by a municipality; and when a municipality has condemned or otherwise…”
Later courts cite it for
“we need not decide whether plaintiff is correct in implying that, if a city chooses to provide utility services and to 'eject or exclude' a public utility from its allocated territory within the city, the allocation statutes would prevent the city from providing services in the territory from which it has ejected the exclusive provider.” · 1 citing court
3
GREENPacifiCorp v. City of Ashland, 749 P.2d 1189 (Or. Ct. App. 1988).
cites § 758.015 2×cited by 13 cases
Where it cites § 758.015
“475 shall not be construed or applied to restrict the powers granted to cities to issue franchises, or to restrict the exercise of the power of condemnation by a municipality; and when a municipality has condemned or otherwise acquired another person's equipment, plant or…”
4
GREENCox v. Polk Cnty., 25 P.3d 970 (Or. Ct. App. 2001).
cites § 758.015 1×cited by 4 cases
Where it cites § 758.015
“400(3) (for the purpose of ORS 758.015 and ORS 758.400 to ORS 758.475, “utility service” means services provided by “any equipment, plant or facility” for the distribution of electricity or gas).”
Later courts cite it for
“amicus oregon farm bureau federation contends that the proposed project is not a farm use under ors 215.203. however, the parties to this case do not assign error to luba's conclusion that the project is a farm use. accordingly, we do not address that question.” · 1 citing court
cites § 758.015 2×cited by 1 case
Where it cites § 758.015
“470 provides, in part: “(1) ORS 758.015 and 758.400 to 758.475 shall not be construed or applied to restrict the powers granted to cities to issue franchises, or to restrict the exercise of the power of condemnation by a municipality; and when a municipality has condemned or…”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
198719962005

One bar per year. Tallest: 2 cases in 2005. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Or. Ct. App.3Or.2
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: laws through the 2025 session (checked Sept. 2026). Syfert holds no earlier or later version of this section.