31 U.S.C. § 3553 (2026)
Review of protests; effect on contracts pending decision
Edition and currency
Other sources
Courts have cited this section in 195 opinions since 1984, 16 of them in the last five years. The most litigated part is subsection (d)(3)(A)(ii) (2 cases).
2021—Subsec. (d)(4)(B). Pub. L. 117–81 substituted “section 3304(c)(1)(G)” for “section 2305(b)(5)(B)(vii)”.
2017—Subsec. (d)(4). Pub. L. 115–91 redesignated existing provisions as subpar. (A) and former subpars. (A) and (B) as cls. (i) and (ii), respectively, of subpar. (A) and added subpar. (B).
2004—Subsec. (g). Pub. L. 108–375 added subsec. (g).
1996—Subsec. (b)(2)(A). Pub. L. 104–106, § 5501(1), substituted “30 days” for “35 days”.
Subsec. (b)(3). Pub. L. 104–106, § 4321(d)(2), substituted “3554(a)(4)” for “3554(a)(3)”.
1994—Subsec. (b)(1). Pub. L. 103–355, § 1402(a)(1)(A), substituted “one day after” for “one working day of”.
Subsec. (b)(2)(A). Pub. L. 103–355, § 1402(a)(1)(B)(i), substituted “35 days after” for “25 working days from”.
Subsec. (b)(2)(C). Pub. L. 103–355, § 1402(a)(1)(B)(ii), substituted “20 days after” for “10 working days from”.
Subsec. (c)(3). Pub. L. 103–355, § 1402(a)(2), substituted “after the making of such finding” for “thereafter”.
Subsec. (d). Pub. L. 103–355, § 1402(b), amended subsec. (d) generally. Prior to amendment, subsec. (d) read as follows:
“(d)(1) If a Federal agency receives notice of a protest under this section after the contract has been awarded but within 10 days of the date of the contract award, the Federal agency (except as provided under paragraph (2)) shall, upon receipt of that notice, immediately direct the contractor to cease performance under the contract and to suspend any related activities that may result in additional obligations being incurred by the United States under that contract. Performance of the contract may not be resumed while the protest is pending.
“(2) The head of the procuring activity responsible for award of a contract may authorize the performance of the contract (notwithstanding a protest of which the Federal agency has notice under this section)—
“(A) upon a written finding—
“(i) that performance of the contract is in the best interests of the United States; or
“(ii) that urgent and compelling circumstances that significantly affect interests of the United States will not permit waiting for the decision of the Comptroller General concerning the protest; and
“(B) after the Comptroller General is notified of that finding.”
Subsec. (f). Pub. L. 103–355, § 1403(c), designated existing provisions as par. (1) and added par. (2).
Amendment by Pub. L. 108–375 applicable to protests filed under this subchapter that relate to studies initiated under Office of Management and Budget Circular A–76 on or after the end of the 90-day period beginning on
For effective date and applicability of amendment by section 4321(d)(2) of Pub. L. 104–106, see section 4401 of Pub. L. 104–106, set out as a note under section 2220 of Title 10, Armed Forces.
Amendment by section 5501(1) of Pub. L. 104–106 effective 180 days after
For effective date and applicability of amendment by Pub. L. 103–355, see section 10001 of Pub. L. 103–355, set out as a note under section 8752 of Title 10, Armed Forces.
Section applicable with respect to any protest filed after
Amendment by Pub. L. 108–375 not to be construed to authorize the use of a protest under this subchapter with regard to a decision made by an agency tender official, see section 326(e) of Pub. L. 108–375, set out as a note under section 3551 of this title.
- Where it cites § 3553
- “Post-award bid protest; override of the CICA automatic stay, 31 U.S.C. § 3553 (d); Defense Logistics Agency Troop Support; judgment on the administrative record, RCFC 52.”
- The case’s holding
- An agency decision to override a statutory stay is arbitrary and capricious if the agency fails to consider relevant factors or provides an explanation contrary to the evidence.
- Later courts cite it for
- “a motion for judgment on the administrative record examines whether the administrative body, given all the disputed and undisputed facts appearing in the record, acted in a manner that complied with the legal standards governing the decision under review.” · 4 citing courts
- Where it cites § 3553
- “As required by 31 U.S.C. § 3553 (c)(1), the award of the 3216 Contract to Dairy Maid was stayed pending a decision by the GAO on CIC’s protest.”
- Later courts cite it for
- “a clear and prejudicial violation of the applicable law ... and was arbitrary, capricious and otherwise not in accordance with the law,” · 1 citing court
- Where it cites § 3553
- “See 31 U.S.C. § 3553 (c)(1). CICA, however, also allows an agency to override the automatic stay if it issues a written finding that “urgent and compelling circumstances which significantly affect interests of the United States will not permit waiting” for the bid protest…”
- The case’s holding
- Jurisdiction exists under the Administrative Dispute Resolution Act if a plaintiff alleges a violation of a statute or regulation in connection with a procurement.
- Later courts cite it for
- “the operative phrase 'in connection with' is very sweeping in scope.” · 24 citing courts
- Where it cites § 3553
- “31 U.S.C. § 3553 (d)(3). CICA further provides, however, that the agency may nonetheless override the automatic stay and proceed with contract performance upon a written determination that either of the following requirements is met: (I) performance of the contract is in the…”
- The case’s holding
- A CICA stay override is reviewed under the arbitrary and capricious standard, asking whether the decision was rational and considered relevant factors, not whether it conformed to a prescribed framework.
- Later courts cite it for
- “standing is not often discussed at length in cica stay override cases,” · 6 citing courts
- Where it cites § 3553
- “Specifically, plaintiff seeks to enjoin the Government from continuing to override the automatic statutory stay of proceedings issued pursuant to the Competition in Contracting Act, 31 U.S.C. §§ 3553 (c)(1), 3553(d)(3)(C) (2000) (the “GICA”), upon plaintiffs timely bid protest.”
- Later courts cite it for
- “failing the ability to show that urgent and compelling circumstances justify the override, the agency head can elect to make the unremarkable determination that contract performance is in the best interests of the united states.” · 3 citing courts
- Where it cites § 3553
- “Moreover, this Court, on August 6, 2004, issued a preliminary injunction enjoining the agency from overriding the automatic stay provision of the Competition in Contracting Act (“CICA”), 31 U.S.C. § 3553 (d)(3)(A), pending a determination by the GAO of the merits of the…”
- The case’s holding
- Government Accountability Office decisions are not binding on the court but serve as persuasive authority (noting that GAO decisions are not binding on the court but are persuasive).
- Later courts cite it for
- “when the court considers a bid protest challenge to a past performance evaluation conducted in the course of a negotiated procurement, 'the greatest deference possible is given to the agency.” · 6 citing courts
- Where it cites § 3553
- “After the Forest Service acted on July 9, 2007 under 31 U.S.C. § 3553 (d)(3)(C) to override the stay based on findings of exigent circumstances and the best interests of the government, the three helicopter operators filed suit in this court on July 11, 2007, seeking a temporary…”
- Where it cites § 3553
- “Pursuant to the automatic stay provisions of 31 U.S.C. § 3553 (d), on September 5, 2006, DeCA notified Four Seasons that the contract was suspended and that it was required to cease performance pursuant to FAR § 33.”
- The case’s holding
- An agency's decision to override an automatic stay is arbitrary and capricious if it fails to consider reasonable alternatives or the impact on competition and procurement integrity.
- Later courts cite it for
- “how the potential cost of proceeding with the override, including the costs associated with the potential that the gao might sustain the protest, compare to the benefits associated with the approach being considered for addressing the agency's needs” · 5 citing courts
- Where it cites § 3553
- “1200 (July 18, 1984) (codified, as amended, at 31 U.S.C. § 3553 ), an automatic stay of the award was engendered by these protests.”
- The case’s holding
- Uneven treatment of offerors in a federal procurement process violates the standard of equality and fair-play and constitutes an abuse of agency discretion.
- Later courts cite it for
- “uneven treatment goes against the standard of equality and fair-play that is a necessary underpinning of the federal government's procurement process and amounts to an abuse of the agency's discretion.” · 14 citing courts
- Where it cites § 3553
- “On August 16, 2003, TMA’s Director of Acquisition Management and Support issued a memorandum explaining TMA’s decision to override the CICA automatic stay pursuant to 31 U.S.C. § 3553 (d)(3)(C). In that memorandum, the Director invoked both of the bases listed in section…”
- The case’s holding
- A lost opportunity to compete constitutes irreparable harm for the purposes of seeking a preliminary injunction.
- Later courts cite it for
- “this court has acknowledged that a lost opportunity to compete may constitute an irreparable harm.” · 9 citing courts
- Where it cites § 3553
- “Keeton subsequently filed a protest with the General Accounting Office (“GAO”) on June 26, 2003, invoking the automatic stay provided for under the Competition in Contracting Act (“CICA”), 31 U.S.C. § 3553 (d). In response to Keeton’s protest, the BOP decided to take corrective…”
- The case’s holding
- An agency decision to override an automatic stay is arbitrary and capricious if the agency fails to consider using sole-source purchase orders to meet urgent needs.
- Later courts cite it for
- “must look to see whether the agency considered the relevant factors and made a rational determination.” · 6 citing courts
- Where it cites § 3553
- “§ 3551-56 (2006)), provides for an automatic stay that prevents an agency from proceeding with a protested contract provided that the agency is timely (that is, within ten days after the date of the contract award or five days after the debriefing date, whichever is later, 31…”
- Where it cites § 3553
- “See 31 U.S.C. § 3553 (2002). During the pendency of that protest, however, DISA exercised an “override” of the stay and authorized continued contract perform-anee by AES.”
- Where it cites § 3553
- “This case arises out of Plaintiffs bid protest pending at the Government Accountability Office (GAO), and the associated stay in contract performance imposed by the Competition in Contracting Act (CICA), 31 U.S.C. § 3553 . In the present action, Advanced Systems Development, Inc.”
- The case’s holding
- A best-interests override of the CICA automatic stay cannot rest merely on the claim that the new contract is cheaper or better than the old one; post-hoc justifications cannot cure that defect.
- Later courts cite it for
- “the automatic stay is intended to preserve the status quo during the pendency of the protest so that an agency would not cavalierly disregard the gao's recommendation to cancel the challenged award.” · 4 citing courts
- Where it cites § 3553
- “; see also 31 U.S.C. § 3553 (e)(1) (providing that with limited exceptions, “a contract may not be awarded in any procurement after the Federal agency has received notice of a protest with respect to such procurement from the Comptroller General and while the protest is…”
- The case’s holding
- The jurisdictional bar for bid protests applies to the issuance of a task order but does not extend to modifications of an existing task order.
- Later courts cite it for
- “although the protest in lbm, inc. concerned the underlying contracts . . ., the court nevertheless finds it instructive" because the protestor "did not challenge the issuance or proposed issuance of a task order under the existing contract.” · 2 citing courts
- Where it cites § 3553
- “The protestor asserts that the procurement at issue is within the jurisdiction of GAO and that the procuring agency, the Transportation Security Administration (“TSA”) must either stay performance of the contract until the conclusion of the protest in accord with 31 U.S.C. §…”
- Where it cites § 3553
- “GAO issued this order, presumably, to comply with CICA’s automatic stay provision at 31 U.S.C. § 3553 (d)(3)(A)(ii), which requires agencies to “direct the contractor to cease performance under the contract and to suspend any related activities that may result in additional…”
- The case’s holding
- An agency is not required to spoon-feed offerors to conduct meaningful discussions during a negotiated procurement.
- Later courts cite it for
- “an agency is not required to 'spoon-feed' offerors in order to have meaningful discussions.” · 3 citing courts
- Where it cites § 3553
- “The Navy’s submissions to the GAO were those required by 31 U.S.C. § 3553 (b)(2), and includ- ed an articulation of the agency’s reasoning in response to the protest.”
- The case’s holding
- Agencies are afforded broad discretion in evaluating past performance provided the agency considers the record in its entirety.
- Later courts cite it for
- “in a bid protest case, the inquiry is whether the agency's action was arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law and, if so, whether the error is prejudicial.” · 85 citing courts
- Where it cites § 3553
- “First, plaintiff points out that DEA’s Determinations and Findings (“D & F”), in which defendant justifies its decision to override the stay pursuant to 31 U.S.C. § 3553 (d)(3)(C) (2004), does not address whether and how overriding the stay will remedy the alleged adverse…”
- Later courts cite it for
- “an agency may override an automatic stay if it notifies the gao in writing that either 'performance of the contract is in the best interests of the united states,' or 'urgent and compelling circumstances that significantly affect interests of the united states will not permit waiting for the decision of the comptroller general concerning the protest.” · 3 citing courts
- The case’s holding
- A contracting officer may give unequal weight to different contracts when evaluating past performance based on their relative relevance.
- Later courts cite it for
- “apply with equal force to the interpretation of government solicitations.” · 3 citing courts
Show all 195 citing cases (list view) →
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
One bar per year. Tallest: 13 cases in 2005. 2026 is a partial year. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.
The 8 courts with the most citing cases, of 25 courts in all.
(c)1 case
(c)(1)1 case
(d)(3)(A)(ii)2 cases
(d)(4)(B)1 case
Amendment years (notes): 2021, 2017, 2004, 1996, 1994
Edition shown: U.S. Code current through Pub. L. 119-102 (OLRC release point). Syfert holds no earlier or later version of this section.